This Statement of Work outlines requirements for repairing three elevators in Building 381 at Travis Air Force Base, California. The contractor must provide design, labor, materials and supervision to repair all three elevators, including developing a 35% design submittal with drawings, specifications, cost estimates and catalog cuts stamped by a structural engineer.
The work includes specific repairs for each elevator such as counterweight barrier adjustments, steel girder replacements, installation of safety devices, preventative maintenance, lighting upgrades to LED fixtures, and thorough cleaning of elevator rooms, car-tops, pits and hoistways. Additional requirements include installing Lunar key capabilities at 15 door locations across all three elevators on 5 floors, CAT-5 testing, and third-party inspections. The contractor must repair only one elevator at a time to minimize disruption to the occupied building. The 35% design submittal will be reviewed within 21 calendar days, with 15-day windows for any required resubmittals. All work must comply with specified UFC, IBC codes and industry standards, including ASME elevator safety codes.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPAIR ELEVATORS, B381
TRAVIS AFB CALIFORNIA
XDAT # 23-1026
Updated 16Jan2025
1. SCOPE OF WORK
The contractor (Ktr) shall provide all design, labor, materials, and supervision to repair 3 elevators. Contractor shall field verify existing conditions and review existing as-built drawings then submit proposed repair design submittals for review and approval by the government. The ktr shall have approved drawings and submittals for all material prior to any new work or installation of equipment, including accessory items. Work shall comply with environmental laws and regulations, including abatement of any hazardous materials. Travis Air Force Base (TAFB) Specification Section 01000 and 01 56 00 have been provided for reference. Any work not specifically covered by the specifications shall comply with current governing UFC, IBC codes and industry standards. The performed tasks shall be based on the project description and other data furnished in this SOW.
DESIGN
DESIGN SUBMITTAL (35 PERCENT):
The ktr shall develop the preliminary design phase (35 percent design completion) to include the following:
Drawings: Developed site plans, floor plans, elevations, and sections. Single line schematic drawings for electrical.
Design Analysis: shall design and provide a 35% design stamped by a structural engineer.
Specifications: The ktr shall provide a list of technical specification sections which are applicable and identify major work requirements to include equipment. Provide 1 hard copy of specifications printed on both sides of paper.
Cost Estimate: Three electronic copies of an updated itemized cost estimate and value engineering considerations shall be furnished by the contractor. The estimate shall be summarized by major work categories and shall include unit man-hour labor and material estimates. A MS Excel version of AF Form 3052 is available from the CE Project Manager.
Catalog Cuts: Electronic copies of catalog information or manufacturer’s data for materials and equipment used as the basis of the design and specifications.
Meeting Minutes: The ktr shall submit meeting minutes of all design review meetings and meetings with government personnel.
CONSTRUCTION TASKS
ELEVATOR #1
| a. | Car Contacts Counterweight Barrier: The elevator car is making contact with the counterweight barrier when the elevator is on the bottom floor. The elevator counterweight assembly needs adjustment and the elevator shall sit level on the bottom while stopped at the bottom floor. |
| b. | Steel Girder Replacement: A steel I-beam was installed on the ceiling of the hoistway that is not long enough to reach across the hoistway and the bolts were bent in order to mount it. The Ktr shall remove and replace the girder with a properly sized girder and install new bolts without the need of bending them. Ktr shall provide a structural engineer’s design drawings for steel replacement. |
c. Replace/Install the Following Parts:
Anti-Rotation device on the counterweight shackles; ASME A17.1, 2.20.9.8.
The missing dust covers in the hoistway; ASME A17.2, 3.13.1 (b) The inaudible alarm bell with 110V secured; ASME A17.1, 2.27.1.1.5 Car Top Railing; ASME A17.1, 2.14.
| d. | Preventative Maintenance: Deflector sheaves show visible signs of bearing grease leaks. Selector Tape show signs of excessive rust. Excessive metal shavings under rope grippers. Various leaks (pedestal, drive sheave, shaft seal, etc.). These are findings by elevator service technicians and need inspection and maintenance. Load Side Conductors: The ktr shall install load side conductors of the same amperage rating as the line side conductors and attach them to the existing main sub panel. The ktr shall ensure the new main panel and existing sub panel fit seamlessly next to each other so no exposure of the switchgear insides is exposed. |
| e. | Car Sensor on floor 5: Car sensor for floor 5 is currently mounted higher than the car and needs to be remounted properly. Ktr shall remount car sensor in order to properly perform the 5-year load test. |
| f. | Pit Lighting: The lighting and light fixture(s) in the elevator pit are at the end-of-life. Ktr shall remove existing lighting and install energy efficient LED light fixtures in accordance with UFC 3-490-06. Provide lighting fixture housings that are dust tight and rated for damp locations. Lighting shall provide minimum of 10 fc at floor level and a color temperature of 5000K. |
| g. | Cleaning: Ktr shall provide a thorough cleaning of the elevator room, car-top, pit, and hoistway. |
| h. | CAT-5 Testing: Ktr shall perform CAT-5 testing of elevator and ensure elevator meets proper CAT-5 testing specifications. |
| i. | Inspection: Ktr shall hire a third-party inspection employed by the governing authority to perform inspection (ASME A17.1 8.10.1.1.3) in accordance with ASME A17.1 & ASME A17.2. |
ELEVATOR #2
| a. | Steel Girder Replacement: A steel I-beam was installed on the ceiling of the hoistway that is not long enough and the bolts were bent in order to mount it. The Ktr shall remove and replace the girder with a properly sized girder and install new bolts without the need of bending them. Ktr shall provide a structural engineer’s design drawings for steel replacement. |
| b. | Preventative Maintenance: Deflector sheaves show visible signs of bearing grease leaks. Selector Tape show signs of excessive rust. Excessive metal shavings under rope grippers. Various leaks (pedestal, drive sheave, shaft seal, etc.). These are findings by elevator service technicians and need inspection and maintenance. |
c. Replace/Install the Following Parts:
Anti-Rotation device on the counterweight shackles; ASME A17.1, 2.20.9.8.
The missing dust covers in the hoistway; ASME A17.2, 3.13.1 (b) The inaudible alarm bell with 110V secured; ASME A17.1, 2.27.1.1.5 Car Top Railing; ASME A17.1, 2.14.
| d. | Repair Ascending Car Overspeed/Unintended Car Movement Protection: The rope gripper engages properly in normal mode, but it does not engage when manually setting off for inspection purposes, ASME A17.1, 2.19.1. |
| e. | Car Sensor on floor 5: Car sensor for floor 5 is currently mounted higher than the car and needs to be remounted properly. Ktr shall remount car sensor in order to properly perform the 5-year load test. |
| f. | Hoist Ropes Space Clearance: Hoist ropes are extremely close to concrete/steel floor. Ktr shall adjust the ropes and/or floor to allow more distance between the ropes and structure. |
| g. | Pit Lighting: The lighting and light fixture(s) in the elevator pit are at the end-of-life. Ktr shall remove existing lighting and install energy efficient LED light fixtures in accordance with UFC 3-490-06. Provide lighting fixture housings that are dust tight and rated for damp locations. Lighting shall provide minimum of 10 fc at floor level and a color temperature of 5000K. |
| h. | Cleaning: Ktr shall provide a thorough cleaning of the elevator room, car-top, pit, and hoistway. |
| i. | CAT-5 Testing: Ktr shall perform CAT-5 testing of elevator and ensure elevator meets proper CAT-5 testing specifications. |
| j. | Inspection: Ktr shall hire a third-party inspection employed by the governing authority to perform inspection. |
ELEVATOR #3
| a. | Cab Lighting: The lighting and light fixture(s) in the elevator cab are at the end-of-life and currently due not illuminate the cab sufficiently. Ktr shall remove and install energy efficient LED light fixtures in accordance with UFC 3-490-06 with a color temperature of 5000K at a minimum of 15fc. |
| b. | I/O Board Upgrade: The current relays system is providing erroneous faults into the control system which causing serious faults to be erased. Ktr shall remove the din rail mounted relays and replace them with a din rail mounted PCB I/O card(s). Ktr shall install the same model I/O board as the ones installed in the elevator systems in the Westwind Inn hydraulic elevators. |
c. Replace/Install the Following Parts:
Car Top Railing; ASME A17.1, 2.14.
Install dust covers in Hoistway; ASME A17.2, 3.13.1.
Push/pull pit STOP switch for stopping elevator motor, independent of regular operating device; UFGS 14 24 00, Item 2.8.3.1 The inoperative battery lowing system; ASME A17.1, 3.26.10.2
| d. | Motor Starter: The motor starter is reaching end-of-life and needs to be upgraded or replaced. |
| e. | Digital position: The digital position indicators are not fully illuminating on floors 1 & 2. Ktr shall install new car position display for that match the existing displays of elevator 1 & 2. |
| f. | Pit Lighting: The lighting and light fixture(s) in the elevator pit are at the end-of-life. Ktr shall remove existing lighting and install energy efficient LED light fixtures in accordance with UFC 3-490-06. Provide lighting fixture housings that are dust tight and rated for damp locations. Lighting shall provide minimum of 10 fc at floor level and a color temperature of 5000K. |
| g. | Cleaning: Ktr shall provide a thorough cleaning of the elevator room, car-top, pit, and hoistway. |
| h. | CAT-5 Testing: Ktr shall perform CAT-5 testing of elevator and ensure elevator meets proper CAT-5 testing specifications. |
| i. | Inspection: Ktr shall hire a third-party inspection employed by the governing authority to perform inspection. |
LUNAR KEYS
| a. | Lunar Key Assessment: Ktr shall conduct a thorough assessment of the existing elevator system to verify if Lunar keys can be configured for use with the current system. |
| b. | Lunar Key Installation: Ktr shall install Lunar key capabilities for each elevator door location (15) in building 381, 3 elevators on 5 floors. Ktr shall that one lunar type functions for all 3 elevators. |
| c. | Lunar Key Testing: Ktr shall test and verify all installed Lunar keys for proper functionality. |
| d. | Lunar Key Training: Ktr shall demonstrate Lunar key use to Travis AFB emergency services personnel. |
| e. | Lunar Key: Ktr shall provide 15 Lunar key copies to the building 381 facility manager along with a model and part number of the key. |
2. SPECIFICATIONS
1. DAFMAN 91-203 Air Force Occupational Safety, Fire, And Health Standards
2. UFC 1-200-01 DoD Building Code (General Building Requirements)
3. UFC 3-301-01 Structural Engineering
4. UFC 3-490-06 Elevators
5. UFC 3-501-01 Electrical Engineering
6. UFC 3-520-01 Interior Electrical Systems
7. UFC 3-530-01 Interior and Exterior Lighting Systems and Controls
8. NFPA 70 National Electrical Code
9. NFPA 70E Standard for Electrical Safety in the Workplace
10. ASME A17.1 Safety Code for Elevators and Escalators
11. ASME A17.2 Guide for Inspection of Elevators
12. SECTION 01000
3. TIME SCHEDULE AND SUBMITTALS
3.1 SCHEDULE A pre-design conference will be held in conjunction with the post-award conference.
3.2 SUBMITTALS
Number of electronic copies to be provided via DoDSAFE(https://safe.apps.mil/) directly to the agency listed below by the contractor.
| AGENCY |
| 35% DESIGN |
| 65% DESIGN |
| 100% DESIGN |
Travis AFB, CA 94535-2632
| 2 |
| N/A |
| N/A |
3.3 REVIEW SCHEDULE
A government design review conference will be held by the Air Force at Travis AFB within 21 calendar days after the receipt of the 35% design submittal.
NOTE: In the event that a re-submittal is required, the contractor and the Government will be allowed a maximum of 15 calendar days each for submittal preparation and review.
4. CONFERENCES/MEETINGS
In addition to normal design review conferences (Pre-design, 35%), formal interchange meetings may be held if deemed necessary by both parties. Otherwise, the contractor may informally call, e-mail, or visit the CE Project Manager at any time to clarify the work or expedite the preparation of plans and specifications.
The contractor shall be responsible for making memoranda for record of any conversations and minutes of any meetings with Government personnel concerning this project.
5. ADDITIONAL REQUIREMENTS
5.1. Work Clearance Request/Digging Permit: Obtain a blank 60 AMW FM 66 (often called a digging permit) from 60 CES Customer Service, (707) 424-7525. Contractors shall request a digging permit at least thirty (30) working days in advance. In-place utility locations shall be verified by the Contractor with on-site pit verification as needed prior to the start of construction activities.
5.2. Working 35% drawings shall provide sufficient detail to provide a clear and complete understanding of the work.
5.3. The ktr shall implement means and methods that will limit disturbance to the facility B381 and base activities to the greatest extent practicable throughout the project. The ktr shall only service and repair 1 elevator at a time in order to limit disruptions in the daily operation of building 381
5.4. The contractor shall ensure installation of all items included in the contract. The contractor shall be accountable for all related costs of items not installed per negotiations.
5.5. Any existing items encountered during construction shall be identified and included in the finished as-builts.
5.6. Facility Occupancy: B381 will be occupied during construction.
5.7. Welding: Welding shall not be performed without first obtaining a welding permit issued by the Base Fire Department.
5.8. Fire Regulations and Preventative Practices: The Contractor shall comply with fire prevention practices as set forth by the National Fire Protection Association (NFPA), other recognized fire prevention agencies, and base regulations.