FCI ELKTON - PROJECT 26Z2AR9 SUPPLY REPLACEMENT LIGHTING INVERTERS
Solicitation number
15B21626Q00000013
Issued by

About this file

Summary

This is a Statement of Work (SOW) for a requirements contract with firm-fixed prices issued by the Federal Bureau of Prisons (FBOP), Field Acquisition Office in Grand Prairie, Texas, for Project 26Z2AR9 at Federal Correctional Institution Elkton in Lisbon, Ohio. The contract seeks a single award to a reputable, duly licensed contractor to procure, deliver, and install seven DSPM Eternalight 1-5.25 kW UL924 Emergency Lighting Uninterruptable Power Supply (UPS) units (Model OE1-5.25KW-277-277-90 or approved equal) with specifications including 277v input/output (single phase), valve-regulated lead-acid batteries with 90-minute runtime, 12 output breakers rated at 20A, and service startup for a minimum two-year warranty covering parts, labor, and travel. The contractor must supply all personnel, equipment, tools, materials, and vehicles necessary for acceptable work and is responsible for maintaining all electrical and mechanical components, providing repairs within 24 hours of notice, and completing the project within 90 calendar days.

The contractor must provide a full-time Project Manager with minimum three years' experience managing similar facilities, employ competent supervisory personnel with HVAC mechanical systems knowledge, and submit a quality control plan within five working days of award. Work access is limited to Monday through Friday, 7:30 A.M. to 3:30 P.M., excluding federal holidays and facility closures, though contractors may be required to work after hours or weekends for scheduled shutdowns without additional compensation. Upon completion, the contractor shall deliver all service and troubleshooting manuals to institution staff and haul away all demolished equipment and debris legally. All bidders must be registered on www.sam.gov and invoices require supporting documentation submitted to both the Contracting Officer's Representative and Contracting Officer. The contract requires contractor registration with the Department of Defense Contractor Performance Assessment Reporting System (CPARs) within 30 days of notification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Justice Federal Bureau of Prisons

Facilities Management

Washington, DC 20534

February 2, 2026

MEMORANDUM FOR GEORGE HOLISKY

FROM:

SUBJECT:

FACILITIES MANAGER, FCI ELKTON

Kimberly Hudson, Chief Construction and Environmental Review Section

Statement of Work Approval for Project 26Z2AR9

Replace Inverters

The Construction and Environmental Review Section, Facilities Management, has reviewed the Statement of Work (SOW) to be used for solicitation services at FCI Elkton for Project 26Z2AR9, Replace Inverters. The submittal is approved .

The following revisions have been made to the SOW.

1. This statement has been added to Introduction section of the SOW: "The contractor must be reputable, and duly licensed. Ifrequired, personnel must provide certifications or documented proof of experience, demonstrating competency in executing the project.

Proof must be provided to the Contracting Officer (CO) or COR upon request" .

2. This statement has been added to Completion Criteria section of the SOW: "The contractor shall provide all service manuals and troubleshooting manuals to institution staff at completion of the installation".

3. This statement has been added to Completion Criteria section of the SOW: "The contractor shall haul away and dispose of all demolished equipment, debris and trash legally after job completion."

If you have any additional questions or concerns, please contact Henry Guo, Architect, at sguo@bop.gov.

cc: Regional Facilities Administrator - NERO

By CERS-FMB at 9:18 am, Feb 02, 2026

STATEMENT OF WORK/SPECIFICATIONS

B&F Project 26Z2AR9

Replace Inverters

Federal Correctional Institution Elkton 8730 Scroggs Road Lisbon, OH 44432

January 28th, 2026

United States Department of Justice Federal Bureau of Prisons

B&F PROJECT 26Z2AR9 REPLACE INVERTERS

Table of Contents

Section 1.0 - Intent

• Introduction

• Action Submittals

• Equipment Specifications

• Manufacturer

Section 2.0 - Scope of Work

• Part A - Description of Work

• Project Work Description

• Required Product or Equal

• Repair/Maintenance

• Reporting

• Schedule

• Inclement Weather Schedule

• Observed Holidays

• Part B - General Conditions

• Quality Assurance/ Acceptance

• Rights to Project Data

• Part C - Project Management

• Contractor Quality Control

• Contractor Requirements

• Performance Evaluation

• Contracting Officer' s Representative

• Part D - Project Completion

• Completion Criteria

• Submission of Invoices

• System for Award Management

• Additional Information

1.0 Intent

Introduction The Federal Bureau of Prisons (FBOP), Field Acquisition Office in Grand Prairie, Texas, intends to make a single award to a responsible entity that will provide new lighting inverters to Correctional Institution - Elkton located at 8730 Scroggs Road in Lisbon, OH. The contract type is a requirements contract with firm-fixed prices . The Contracting Officer holds the rights for the dismissal of the awarded party and dissolution of the contract if contract goals and schedules are not met, or excessive damages have been accrued. The contract shall consist of a two-phase process to procure and deliver equipment meeting the specified qualifications, and successfully completing activation of that equipment to ensure operational compliance . The operation will be completed in an authorized manner to limit disruption to the institution(s) and provide isolated avenues to prevent unnecessary costs to the facility . The contractor is responsible for the safe operation of equipment during this contracted period ensuring schedule requirements are met and maintained throughout the term of the contract.

The contractor must be reputable, and duly licensed. If required , personnel must provide certifications or documented proof of experience, demonstrating competency in executing the project. Proof must be provided to the Contracting Officer (CO) or COR upon request.

Background

2.0 SCOPE OF WORK

A. Description of Service

Project Work Description The contractor must also provide all personnel , equipment, tools, materials, vehicles, and other items and services necessary to provide acceptable work to the facility within this project.

The contractor is responsible to ensure the following :

• Equipment supplied will be seven DSPM Etemalight 1- 5.25 kW UL924 Emergency Lighting Uninterruptable Power Supply (UPS) Model OEl-5.25KW-277-277-90 or approved equal.

• Equipment Input is 277v and Equipment Output is 277v - I phase.

• Battery type provided will be Valve Regulated Lead-Acid (VRLA), also known as, sealed maintenance-free

(AGM) lead-calcium , with a runtime of90 minutes:

• Equipment has 12 Output Breakers rated at 20A single pole, Normally On at 277YAC

• Provide Service Startup for DSPM Eternalight 1- 5.25 kW UL924 Emergency Lighting Uninterruptable Power

Supply (UPS) Model OE1-5 .25KW-277-277-90 or approved equal , (one visit up to two days long) for all four units to secure a minimum two-year warranty which includes parts, labor, and travel

Required Product or Equal A brand name or equal product will be accepted. Should a quotation be issued by a contractor for equal products, the contractor shall submit all product information/specification for the equal products in the contractor' s bid/proposal. Failure to submit the product information/specifications with your bid/proposal will be considered non-responsive and the contractor's bid/proposal will not be considered.

• The contractor shall meet the standards of the contract and comply with all local, state, and federal regulations .

• The contractor will be responsible for all licenses, permits, and fees associated with the transportation of deliverables.

• The contractor shall remain responsible for all equipment and property.

Repair/Maintenance It will be the responsibility of the contractor to maintain all electrical and mechanical components of the new equipment both internally and externally. This includes the monetary cost of all material , equipment, and labor required and provided to repair, replace, or upgrade any part of the existing and future system associated . This contract also encompasses all makes and models of existing equipment. If any part of this system requires replacement or upgrade, it will be the responsibility of the contractor to provide it within 30 days or duration set by the Contracting Officer or Contracting Officer' s Representative . Repair needs must be met within 24-hours of written, digital, or verbal notice from the Contracting Officer and or Contracting Officer' s Representative.

Reporting Upon completion of activation , the contractor's supervision will notify the Contracting Officer ' s Representative through a designated email of this development. All reports and documentation will be provided to the Bureau of Prisons Facility Manager no later than 30 days after processing the material.

It will be the Contractors responsibility to prepare and submit reports of significant accidents at the site and anywhere on the institution property. A significant accident is defined to include events that pose a security breech, damage to Government Property and/or any injury. Record and document date and actions.

Schedule The approved access for contracted personnel throughout the duration of this project, as designated by the Contracting Officer, will be the following weekly schedule:

• Sunday : No access granted

• Monday : 7:30 A.M - 3:30 P.M.

• Tuesday: 7:30 A.M - 3:30 P.M.

• Wednesday: 7:30 A.M. 3:30 P.M.

• Thursday: 7:30 A.M. - 3:30 P.M.

• Friday: 7:30 A.M - 3:30 P.M.

• Saturday: No access granted

This schedule does not account for Federal holidays or when the institution/facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The contractor is required to work after hours or weekends for scheduled shutdowns to make utility service connections in the event disruption to the daily operations of the institution will occur due to incomplete milestones . The Federal Bureau of Prisons will therefore not absorb financial costs for this additional work . For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons . The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this statement of work when the government facilities are not disrupted for the above reasons. When hiring personnel, the Contractor should keep in mind that the stability and continuity of the workforce are essential.

Inclement Weather Schedule In cases of severe weather, the contracting office may authorize exceptions . When exceptions are granted, the contractor shall make all postponed deliveries within 24 hours after the severe weather has terminated, unless the contracting officer authorizes additional time.

Observed Holidays Contractor is not required to perform services on holidays listed below:

perform services on holidays listed below.

New Year's Day Independence Day Labor Day Columbus Day Martin Luther King Jr. ' s Birthday Veteran's Day President' s Day Thanksgiving Day Memorial Day Christmas Day

B. General Condition

Rights to Project Data The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges ofownership/copyright belonging exclusively to the

Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

C. Project Management

Contractor Quality Control The contractor shall provide a Job Superintendent/manager or equivalent who speaks and writes fluent English and is always accessible when contractor personnel are on the premises. The Superintendent will: a) review and approve submittals, b) inspect the quality of work performed, and c) certify the completed work for payment and other purposes.

The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this statement of work. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor' s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. The Contractor shall submit QCP on or before the scheduled preconstruction meeting. Three copies ofa comprehensive written QCP shall be submitted to the CO and COR within 5 working days when changes are made thereafter. After acceptance of the quality control plan , the contractor shall receive the contracting officer' s acceptance in writing of any proposed change to his QC system.

The government shall evaluate the contractor's performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied , the frequency of surveillance, and the minimum acceptable defect rate(s).

Contractor Requirements It is the contractor's responsibility to survey the work site and carry out all work in compliance with OSHA, EPA, and NEC national codes and regulations .

The contractor shall provide a full-time Project Manager who shall be physically on-site all normal work hours and be responsible for performance of all work. The project manager shall possess a minimum of three years ' experience within the last five years simultaneously managing facilities of similar magnitude and scope of the total requirements of the contract. The contractor shall employ competent supervisory personnel capable of training employees in methods of completing the work performance and quality standards in this contract. The supervisor shall have in-depth knowledge of performance based and prescriptive HY AC Mechanical systems and quality control processes, procedures, supplies, and equipment. The supervisor shall, at a minimum, have completed a supervisory training course for 5 of this type of work and have prior HV AC Mechanical system experience in similar size and type facilities. The on-site supervisor(s) is required to be fully conversant in English.

Permits and Permission It will be required of the service provider to obtain all permits associated with this contract if required by policy or written request of the Contracting Officer.

Prior to the arrival of equipment, a written request must be submitted to the Contracting Officer and consent returned . The contractor will provide the Contracting Officer with the date the on-site work is planned to begin no less than 14-calander days prior to the arrival of the contractor's representative. Written permiss ion must be obtained to store material on the institutional grounds. It will , therefore, be the responsibility of the contractor to ensure the materials will be secured in the designated locations procured by institutional staff and indicate when access to these materials will be required moving forward .

Performance Evaluation ln accordance with FAR 42.1502 & 42.1503: Agencies shall prepare an evaluation of Contractor Performance and submit to Federal Past Performance Information Retrieval System (PPIRS) . The Department of Justice, Federal Bureau of Prisons utilizes the Department of Defense (DOD) web-based Contractor Performance Assessment Reporting System (CPARs) to provide contractor performance evaluations. Contractor shall provide and maintain a current e-mail address throughout the life of the contract. The Contractor shall register with DOD within 30 days of receiving an e-mail from the Focal Point. The e-mail will contain a "USER ID" to complete the registration. The Contractor must be registered to access and review its evaluation and/or provide a response. If assistance is required when registering, please contact the institutional Contracting Staff/Focal Point for assistance, guidance, and instructions.

Contracting Officer's Representative The COR is responsible for the technical aspects of the project and serves as the technical liaison for the contractor. The COR is also responsible for final inspection and acceptance of all reports and other responsibilities as specified by the contract. The COR is not authorized to make any commitments, obligate the government, or authorize any changes, which affect the price, terms, or conditions of this project. All changes shall be made through the authorization of the Contracting Officer. The COR may designate an assistant COR(s) to act for the COR by naming such assistant(s) n writing and sending a written, formal document, to both the Contracting Officer and contractor prior to them assuming that duty.

D. Project Completion

Completion Criteria The project site shall be protected and/or restored to a condition equal to that existing, prior to the commencement of work . Existing work disturbed or removed as a result of performing the required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

The Contracting Officer reserves the right to implement a deficiency list to ensure standards and conditions are met prior to the closeout and final payment of the contract.

The contractor shall provide all service manuals and troubleshooting manuals to institution staff at completion of the installation.

The contractor shall haul away and dispose of all demolished equipment, debris and trash legally after job completion.

System for Award Management Contractors intending on submitting formal bids for this work must be registered on the System for Award Management website at www.sam.gov. Only those vendors registered will be considered.

Submission of Invoices No invoice will be considered for payment unless accompanied by the relevant documentation . All invoices should be on an official company letterhead including that organization's name, address, bank number, and this project title. Submit invoices to both the COR and Contracting Officer for review and approval.

Additional Information

• Time of Completion: 90-Calander Days

• Submittals After Award: Submit samples, cut sheets, and shop drawings to the Contracting Officer's

Representative for review.