This is an AAAP Project Specific Advertisement (PSA) Attachment detailing the post-award schedule for a federal real estate lease project. The schedule commences within 5 working days of lease award and establishes the timeframes for managing the design and construction process through government acceptance of the space.
The post-award schedule specifies 10 sequential activities totaling 305 working days from lease award to government acceptance. Key activities include: Government provision of Design Intent Drawings (45 days), Lessor review for code compliance (10 days), Lessor preparation and submission of construction documents at 50%, 75%, and 100% development phases (60 days), Government review of construction drawings at each phase (30 days total with 10 days per review), Lessor submission of TI and BSAC price proposal (20 days), Government pricing review and approval (30 days), Government issuance of Notice to Proceed (10 days), Lessor construction completion (90 days), and Government inspection and acceptance (10 days). This attachment replaces the attachment referenced in section 1.05 of the RLP (R100) and should be used in conjunction with section 4.01 of the Lease (L100). The schedule provides a comprehensive timeline governing the design, pricing, construction, and final acceptance phases of the leased space improvement project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5SC0131 Agency Space Requirements.pdf | ||
| 5SC0131 Delineated Area.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Government Provided Design Intent Drawings 45
Lessor review of Design Intent Drawings for code compliance 10
Lessor Preparation and Submission of Construction Documents to be provided at the 50%, 75% and 100% phase of development 60
Government Review of Construction Drawings at the 50%, 75% and 100% phase of development 30 (10 working days for each review)
Lessor Preparation and Submission of the TI and BSAC Price Proposal 20
Government Reviews and Approves Pricing 30
Government Issues Notice to Proceed with Construction 10
Lessor Completes Construction of TIs and Completion of Other Required Construction Work 90
Government Inspects and Accepts Finished Space 10
AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)
Total Workdays from Lease Award to Government Acceptance 305