This solicitation is for a construction project to renovate medical/surgical inpatient units at a Department of Veterans Affairs medical center. Work includes interior demolition and renovation, system upgrades and replacements, new patient rooms and support spaces. Bids are due within three weeks of issuance, with award expected four weeks later. The estimated budget is $5 million. The prime contractor must complete all work over 12 months, coordinating closely with ongoing facility operations.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract No.: 564-17-140
Specifications
For:
At:
Renovate Med Surge Wards
Specifications
Divisions 01 Through 48
Department of Veterans Affairs
Veterans Healthcare System of the Ozarks
Fayetteville, AR
Issue: Bid Documents March 23, 2023
Property of Department of Veterans Affairs
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
Renovate Med Surge Ward
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 13 Seals Page
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21
01 33 23 Shop Drawings, Product Data, and Samples 06-21
Master Submittal List
01 35 26 Safety Requirements 11-21
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 11-21
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 01-21
02 41 00 Demolition 08-17
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
00 01 10-2
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 16 63 Cementitious Sheathing 01-21
06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 21 13 Thermal Insulation 01-21
07 21 19 Foamed-in-Place Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 72 00 Roof Accessories 01-21
07 81 00 Applied Fireproofing
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 17 10 Integrated Door Assemblies 01-21
08 31 13 Access Doors and Frames 01-21
08 52 13 Aluminum-Clad Wood Double-Hung Windows
08 71 00 Door Hardware 01-21
08 71 13 Automatic Door Operators 01-21
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 30 13 Ceramic/Porcelain Tiling 01-21
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 05-18
09 65 19 Resilient Tile Flooring 05-18
09 67 23.30 Resinous (Epoxy Resin Composition) Mortar Flooring
(RES-3)
01-21
09 72 16 Vinyl-Coated Fabric Wall Covering 01-21
09 91 00 Painting 01-21
09 96 59 Resinous Specialty Glazed Coating Systems for Ceilings 07-14
DIVISION 10 – SPECIALTIES
10 11 13 Chalkboards and Markerboards 01-21
00 01 10-3
10 14 00 Signage 01-21
10 21 23 Cubicle Curtain Tracks 01-21
10 25 13 Patient Bed Service Walls 01-20
10 26 00 Wall and Door Protection 01-21
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT
11 05 12 General Motor Requirements for Equipment 01-21
11 73 00 Ceiling Mounted Patient Lift System 08-20
DIVISION 12 – FURNISHINGS
12 22 16 Drapery Track and Accessories 01-21
12 24 00 Window Shades 08-17
12 32 00 Manufactured Wood Casework 01-21
12 36 00 Countertops 12-18
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-21
DIVISION 14– CONVEYING EQUIPEMENT – NOT USED
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-15
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-20
22 40 00 Plumbing Fixtures 09-15
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 02-20
00 01 10-4
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
02-20
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 02-20
23 09 23 Direct-Digital Control System for HVAC 08-20
23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20
23 22 13 Steam and Condensate Heating Piping 02-20
23 22 23 Steam Condensate Pumps 04-20
23 23 00 Refrigerant Piping 02-20
23 31 00 HVAC Ducts and Casings 02-20
23 34 00 HVAC Fans 02-20
23 36 00 Air Terminal Units 02-20
23 37 00 Air Outlets and Inlets 02-20
23 40 00 HVAC Air Cleaning Devices 03-20
23 73 00 Indoor Central-Station Air-Handling Units 03-20
23 81 00 Decentralized Unitary HVAC Equipment 03-20
23 82 16 Air Coils 03-20
DIVISION 25 – INTEGRATED AUTOMATION – NOT USED
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 09 23 Lighting Controls 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 51 00 Interior Lighting 01-18
26 55 71 Medical and Surgical Lighting Fixtures 01-18
26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Control, Communication and Signal Wiring 06-15
27 11 00 Communications Equipment Room Fittings 06-15
27 15 00 Communications Structured Cabling 01-16
00 01 10-5
27 52 23 Nurse Call and Code Blue Systems 12-20
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
28 16 00 Intrusion Detection System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 31 40 High Security Fences and Gates 08-16
32 90 00 Planting 08-16
DIVISION 33 – UTILITIES – NOT USED
DIVISION 34 – TRANSPORTATION – NOT USED
DIVISION 48 – Electrical Power Generation – NOT USED
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
VOLUME 1
Drawing No. Title
GENERAL
GI001 COVER SHEET
GI002 EQUIPMENT MOUNTING LEGEND
GI003 ACCESSIBILITY LEGEND
GI100 FIRST FLOOR LIFE SAFETY PLAN
GI101 SECOND FLOOR LIFE SAFETY PLAN
GI102 THIRD FLOOR LIFE SAFETY PLAN
GI501 PROJECT-WIDE PARTITION TYPES AND STANDARD
DETAILS
GENERAL CONDITIONS
GC050 BASEMENT FLOOR ICRA PLAN
GC100 FIRST FLOOR ICRA PLAN
GC101 SECOND FLOOR ICRA PLAN
GC102 THIRD FLOOR ICRA PLAN
GC119 BASEMENT FLOOR PHASING PLAN – PHASES 1-2
GC120 FIRST FLOOR PHASING PLAN – PHASES 1
GC121A PARTIAL FIRST FLOOR REFLECTED CEILING PHASING
PLAN – PHASES 1 & 2
GC122 SECOND FLOOR PHASING PLAN – WARD 2B - PHASE 1
GC123 SECOND FLOOR PHASING PLAN – WARD 2 – PHASE 2
GC123A SECOND FLOOR PHASING PLAN – WARD 2 - PHASE 2
GC123B SECOND FLOOR PHASING PLAN – WARD 2 - PHASE 2
GC124 THIRD FLOOR PHASING PLAN
SOC-3 STATEMENT OF CONDITIONS FIRST FLOOR
SOC-6 STATEMENT OF CONDITIONS SECOND FLOOR
SOC-9 STATEMENT OF CONDITIONS THIRD FLOOR
HAZARDOUS
HA050 BASEMENT FLOOR HAZARDOUS ABATEMENT PLAN
HA102 SECOND FLOOR HAZARDOUS ABATEMENT PLAN
00 01 15 - 2
STRUCTURAL
SS001 STRUCTURAL GENERAL NOTES
SS103 EAST STAIR PLANS
SS301 STRUCTURAL SECTIONS AND DETAILS
SS302 STRUCTURAL SECTIONS AND DETAILS
ARCHITECTURAL
AI001 NOTES AND LEGENDS
AI002 ARCHITECTURAL ABBREVIATIONS
AS001 ARCHITECTURAL SITE PLAN
AD050 BASEMENT FLOOR DEMOLITION PLAN – PHASE 1
AD051 OVERALL FIRST FLOOR DEMOLITION PLAN - PHASES 1
-2
AD052 PARTIAL 2B SECOND FLOOR DEMOLITION PLAN WARD 2
– PHASE 1
AD053 PARTIAL WARD 2 SECOND FLOOR DEMOLITION PLAN –
PHASE 2
AD054 PARTIAL THIRD FLOOR DEMOLITION PLAN – WARD 3B
AE050 BASEMENT FLOOR PLAN – PHASES 1-3
AE100 FIRST FLOOR PLAN – PHASES 1-2
AE101 OVERALL SECOND FLOOR PLAN – NEW WORK
AE102 PARTIAL WARD 2B SECOND FLOOR CONSTRUCTION PLANS
– PHASE 1
AE103 PARTIAL WARD 2 SECOND FLOOR CONSTRUCTION PLAN –
PHASE 2
AE104 OVERALL THIRD FLOOR CONSTRUCTION PLAN – PHASE 1
AE105 PARTIAL WARD 2B SECOND FLOOR TOPPING PLAN –
PHASE 1
AE120 OVERALL SECOND FLOOR REFLECTED CEILING PLAN
AE121 ENALRGED BASEMENT REFLECTED CEILING PLAN
AE122 PARTIAL WARD 2 SECOND FLOOR REFLECTED CEILING
PLAN – PHASE 1
AE123 PARTIAL WARD 2 SECOND FLOOR REFLECTED CEILING
PLAN – PHASE 2
AE130 PARTIAL ROOF PLANS
AE301 PARTIAL BUILDING SECTIONS
AE302 PARTIAL BUILDING SECTIONS
00 01 15 - 3
AE401 ENLARGED PARTIAL PLAN – PHASE 1 – WARD 2 AND 2B
NORTH
AE402 ENLARGED PARTIAL PLAN – PHASE 1 – WARD 2B SOUTH
AE403 ENLARGED PARTIAL PLANS – PHASE 2 – WARD 2 NORTH
AND SOUTH
AE404 ENLARGED – TYPICAL FLOOR AND REFLECTED CEILING
PLAN
AE405 INTERIOR ELEVATIONS
AE406 INTERIOR ELEVATIONS
AE410 3D VIEWS – INTERIORS
AE411 3D VIEWS – INTERIORS
AE450 EXTERIOR STAIR EAST – PLANS
AE451 ENLARGED STAIR PLANS – EAST
AE452 EXTERIOR STAIR EAST – ELEVATIONS
AE453 EXTERIOR STAIR PARAPET RAILING ELEVATIONS-EAST
AE454 SECTION DETAIL AT EAST STAIR
AE455 3D VIEW – FIRE STAIR - EAST
AE460 STAIR TYPICAL DETAILS
AE500 INTERIOR DETAILS AT PATIENT BATHROOM
AE501 MISCELLANEOUS DETAILS
AE511 INTERIOR DETAILS
AE512 INTERIOR DETAILS
AE513 ENLARGED CASEWORK PLANS
AE514 ENLARGED CASEWORK PLANS AND ANCHORAGE DETAIL
AE515 CASEWORK DETAILS
AE601 DOOR SCHEDULE AND DETAILS
AE602 WINDOW TYPES AND DETAILS
INTERIORS
AF101 PARTIAL WARD 2B SECOND FLOOR FINISH PLAN –
PHASE 1
AF102 PARTIAL WARD 2 SECOND FLOOR FINISH PLAN – PHASE
AF500 THRESHOLD DETAILS
AF501 WALL PROTECTION / SIGNAGE TYPES
AF601 INTERIOR FINISH SCHEDULE AND SIGNAGE SCHEDULE
AF602 INTERIOR MATERIALS LEGEND
00 01 15 - 4
EQUIPMENT
QH102 SECOND FLOOR ENLARGED EQUIPMENT PLANS – PHASE 1
- NORTH
QH103 SECOND FLOOR ENLARGED EQUIPMENT PLAN – PHASE 1
- SOUTH
QH104 SECOND FLOOR ENLARGED EQUIPMENT PLANS – PHASE 2
- SOUTH
QH601 EQUIPMENT SCHEDULES
VOLUME 2
GENERAL
GI001B COVER SHEET
FIRE ALARM
FA001 GENERAL NOTES AND SCHEDULES
FA101 PARTIAL 2B SECOND FLOOR FIRE ALARM PLAN –
PHASE 1
FA102 PARTIAL 2 SECOND FLOOR FIRE ALARM PLAN –
PHASE 2
FA103 THIRD FLOOR FIRE ALARM PLAN
FIRE PROTCTION
FX001 GENERAL NOTES & LEGENDS
FD100 BASEMENT AND FIRST FLOOR DEMOLITION FIRE
PROTECTION PLANS
FD101 PARTIAL 2B SECOND FLOOR DEMOLITION FIRE
PROTECTION PLAN – PHASE 1
FD102 PARTIAL 2 SECOND FLOOR DEMOLITION FIRE
PROTECTION PLAN - PHASE 2
FX100 BASEMENT FIRST FLOOR FIRE PROTECTION PLANS
FX101 PARTIAL SECOND FLOOR FIRE PROTECTION PLANS -
PHASES 1 AND 1A
FX102 PARTIAL 2 SECOND FLOOR FIRE PROTECTION PLAN -
PHASE 2
FX501 DETAILS
00 01 15 - 5
PLUMBING
PL001 GENERAL NOTES, LEGENDS, & SCHEDULES
PD051 BASEMENT DEMOLITION SUPPLY PLAN
PD052 FIRST FLOOR DEMOLITION SUPPLY PLAN
PD053 PARTIAL 2B SECOND FLOOR DEMOLITION WASTE PLAN –
PHASE 1
PD054 PARTIAL 2 SECOND FLOOR DEMOLITION WASTE PLAN -
PHASE 2
PD055 PARTIAL 2B SECOND FLOOR DEMOLITION SUPPLY PLAN
– PHASE 1
PD056 PARTIAL 2 SECOND FLOOR DEMOLITION SUPPLY PLAN –
PHASE 2
PD057 PARTIAL 2B SECOND FLOOR DEMOLITION MED GAS PLAN
– PHASE 1
PD058 PARTIAL 2 SECOND FLOOR DEMOLITION MED GAS PLAN
– PHASE 2
PL101 BASEMENT SUPPLY PLAN
PL102 FIRST FLOOR SUPPLY PLAN
PL103 PARTIAL 2B SECOND FLOOR WASTE PLAN – PHASE 1
PL104 PARTIAL 2 SECOND FLOOR WASTE PLAN – PHASE 2
PL105 PARTIAL 2B SECOND FLOOR SUPPLY PLAN – PHASE 1
PL106 PARTIAL 2 SECOND FLOOR SUPPLY PLAN – PHASE 2
PG101 PARTIAL 2B SECOND FLOOR MED GAS PLAN – PHASE 1
PG102 PARTIAL 2 SECOND FLOOR MED GAS PLAN – PHASE 2
PL501 DETAILS
PW701 SECOND FLOOR PIPING RISER DIAGRAMS – PHASE 1
PW702 SECOND FLOOR PIPING RISER DIAGRAM – PHASE 2
MECHANICAL
MH001 GENERAL NOTES & LEGENDS
MS101 MECHANICAL SITE PLAN
MD050 PARTIAL WARD 2 & 2B SECOND FLOOR MECHANICAL
DEMOLITION PLANS – PHASES 1 AND 1A
MD051 PARTIAL WARD 2 SECOND FLOOR MECHANICAL
DEMOLITION PLAN – PHASE 2
MD052 ENLARGED MECHANICAL ROOM DEMOLITION PLANS
00 01 15 - 6
MH050 MECHANICAL ROOM M2-4 TEMPORARY UNIT FIRST FLOOR
PLANS – PHASE 1A
MH051 PARTIAL MECHANCAL TEMPORARY UNIT ROOF PLAN –
PHASE 1A
MH101 PARTIAL WARD 2 & 2B SECOND FLOOR MECHANICAL
PLANS – PHASES 1 AND 1A
MH102 PARTIAL WARD 2 SECOND FLOOR MECHANICAL PLAN –
PHASE 2
MP050 PARTITIAL BASEMENT FLOOR PLAN MECHANICAL PIPING
PLAN – PHASE 1
MP101 PARTIAL WARD 2 & 2B SECOND FLOOR MECHANICAL
PIPING PLANS – PHASES 1 AND 1A
MP102 PARTIAL WARD 2 SECOND FLOOR MECHANICAL PIPING
PLAN – PHASE 2
MH201 ENLARGED MECHANICAL PLANS - PHASE 1
MH301 MECHANICAL SECTIONS
MH401 ENLARGED MECHANICAL ROOMS PLANS AND SECTIONS
MH501 DETAILS
MH502 DETAILS
MH503 DETAILS
MH504 DETAILS
MH601 SCHEDULES
MH602 SCHEDULES
MI701 CONTROLS SCHEMATICS
MI702 CONTROLS SCHEMATICS
MI703 CONTROLS POINTS
ELECTRICAL
EG001 GENERAL NOTES AND SCHEDULES
ES101 ELECTRICAL SITE PLAN
ED050 FIRST FLOOR OVERALL DEMOLITION PLAN
ED051 PARTIAL 2B SECOND FLOOR DEMOLITION PLAN
– PHASE 1
ED052 PARTIAL 2 SECOND FLOOR DEMOLITION PLAN
– PHASE 2
EL101 PARTIAL 2B SECOND FLOOR LIGHTING PLAN
– PHASE 1
00 01 15 - 7
EL102 PARTIAL 2 SECOND FLOOR LIGHTING PLAN – PHASE 2
EL103 THIRD FLOOR LIGHTING PLAN – PHASE 1
EP101 OVERALL BASEMENT – ELECTRICAL PLAN
EP102 OVERALL FIRST FLOOR – POWER PLAN
EP103 PARTIAL 2B SECOND FLOOR POWER PLAN – PHASE 1
EP104 PARTIAL 2 SECOND FLOOR POWER PLAN – PHASE 2
EP105 ATTIC PLAN - POWER
EY101 PARTIAL 2B SECOND FLOOR SYSTEMS PLAN – PHASE 1
EY102 PARTIAL 2 SECOND FLOOR SYSTEMS PLAN – PHASE 2
EY103 THIRD FLOOR SYSTEMS PLAN
EE501 ELECTRICAL DETAILS
EE502 ELECTRICAL DETAILS
EE503 ELECTRICAL DETAILS
EE601 RISER DIAGRAM
EE602 RISER DIAGRAM
EE701 PANEL SCHEDULES
EE702 ELECTRICAL CONNECTION SCHEDULES
- - - END - - -
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor must completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to renovate existing Wards 2 and 2B in Main Building 1 for in-patient medical surgical units. This project converts existing Wards 2 and 2B into a new Unit with single, bariatric and non-bariatric, patient rooms. Project renovates approximately 14,000 square feet. Work is accomplished in multiple phases and requires coordination with occupied operations in spaces alongside, above, and below the project area, to modify and/or install new engineering systems. HVAC systems receive replacement and rebalancing. Electrical branches are separated per NEC and new electrical panels installed. Demolition and renovation require window replacement, patient normal and bariatric rooms, meds rooms, storage, nurse stations, lighting, ceiling, floors, doors and hardware, interior finishes, bedside computers, televisions, nurse call system, mechanical, electrical, plumbing, phasing, commissioning, sustainable design, and other features not described herein, but denoted in drawings and specifications.
The Contractor must furnish all management, supervision, labor, material, equipment, tools, supplies, parts, and related services, in accordance with Statement of Work (SOW), drawings, and specifications to be a complete and working system. Electronic copies of drawings and specifications to this work will be furnished by VA upon Contractor’s written request to the Contracting Officer (CO) or Contracting
Officer’s Representative. Hard copies of SOW, Drawings, and
Specifications are Contractor’s responsibility and expense. Contractor is responsible to verify existing and new dimensions, locations, measurements, and quantities. This project is located on the Main
Campus of the Veterans Healthcare System of the Ozarks (VHSO) at 1100
North College Avenue, Fayetteville, AR.
01 00 00 - 2
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Contracting Officer and Contracting Officer’s
Representative.
C. Offices of Harrell Design Group, PC, as Architect-Engineers, will render certain technical services during construction. Such services will be considered as advisory to the Government and will not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or Contracting Officer’s
Representative or duly authorized representative.
D. All employees of General Contractor and Subcontractors must comply with
VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM 1; GENERAL CONSTRUCTION: The contractor shall provide all necessary tools, labor, materials, equipment, permits, license, and supervision for "Renovate Med Surge Inpatient Wards," project number 564-17-140, located at the Veterans Healthcare System of the
Ozarks in Fayetteville AR, in accordance with the drawings and specifications. Work includes, but is not limited to, interior renovation, window replacement within project limits (second floor window replacement only), general demolition, construction, plumbing, structural, HVAC, electrical, and fire protection.
B. ITEM 2; DEDUCT ALTERNATE 1: Perform all work as stated in Bid Item 1, except replace base bid patient lift fixed rails flush-mounted into ceiling grid with surface-mounted, fixed rails.
C. ITEM 3; DEDUCT ALTERNATE 2: Perform all work as stated in Bid Item 2, except remove base bid, dialysis boxes and associated plumbing work from 2B's patient rooms.
D. ITEM 4; Not Used.
E. ITEM 5; DEDUCT ALTERNATE 4A, 4B, 4C, 4D: Perform all work as stated in
Bid Item 3, except:
4A. Substitute plastic laminate for solid surface wall protection in soiled utility and meds rooms.
4B. Replace base bid, reveal-edge ceiling tiles (AT-1) with flush, non-reveal-edge, acoustical ceiling tiles (AT-2).
01 00 00 - 3
4C. Replace base bid, antimicrobial copper, cabinet hardware, electrical switch, plate covers and outlet plates with 304 stainless steel covers and plates.
4D. Remove vertical, fire-retardant treated marine-grade plywood from behind cementitious backer board in all patient showers and their adjacent, adjoining patient shower wall; see partition suffix type T1 on drawing GI501. In place of the removed, marine-grade plywood, use 5/8" moisture-resistant, impact-resistant gypsum wall board.
F. ITEM 5; DEDUCT ALTERNATE 5: Perform all work as stated in Bid Item 5, except remove Phase 2 work in its entirety associated with Ward 2. Note that Phase 1 work occurring within Ward 2 remains in base bid and is not removed from scope.
G. ITEM 6; DEDUCT ALTERNATE 6: Perform all work as stated in Bid Item 6, except remove booster pump and associated work.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all
Subcontractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees must not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor must give one week’s notice to the Contracting Officer or Contracting Officer’s
Representative so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer or Contracting Officer’s Representative.
01 00 00 - 4
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer or Contracting Officer’s Representative.
C. Key Control:
1. The General Contractor must provide duplicate keys and lock combinations to the Contracting Officer’s Representative (COR) or
Contracting Officer’s Representative for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor must turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Subcontractors must submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information must be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer or Contracting Officer’s
Representative upon request.
4. These security documents must not be removed or transmitted from the project site without the written approval of Contracting Officer or
Contracting Officer’s Representative.
5. All paper waste or electronic media such as CD’s and diskettes must be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer, Contracting Officer’s Representative, and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
01 00 00 - 5
7. All electronic information must be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic must be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request will be required for any vehicle entering the site and such request must be submitted 24 hours before the date and time of access. Access must be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits will be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor must confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer or Contracting Officer’s Representative. The
Contractor must hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer or Contracting Officer’s Representative and must be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities will remain the property of the Contractor and must be removed by the
Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer or Contracting Officer’s
Representative, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor must, under regulations prescribed by the Contracting
Officer or Contracting Officer’s Representative, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer or Contracting Officer’s
Representative. When materials are transported in prosecuting the work, 01 00 00 - 6 vehicles must not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor must protect them from damage. The Contractor must repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials must be as determined by the COR.
E. Workmen are subject to rules of Medical Center applicable to their conduct.
F. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they must be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions must be coordinated with the COR:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, 01 00 00 - 7 payment of such fee must be the responsibility of the Government and not the Contractor.
H. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the Contractor’s responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To ensure such executions, Contractor must furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor must notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases as indicated on the drawings.
I. Building 1 will be continuously occupied during performance of work, although the immediate areas of work will be vacated.
Contractor must take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor must permit access to Department of Veterans
Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress must be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc.
to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
J. When a building and/or construction site is turned over to Contractor, Contractor must accept entire responsibility including upkeep and maintenance therefore:
01 00 00 - 8
1. Contractor must maintain a minimum temperature of 65 degrees F at all times and a maximum of 75 degrees F at all times, except as otherwise specified.
2. Contractor must maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor must arrange pre-inspection of site with Fire
Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they must be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work must be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment must not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS for additional requirements.
2. Contractor must submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request must state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and must be performed as directed by the COR.
01 00 00 - 9
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee must be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, must be sealed, capped or plugged at the main, branch or panel they originate from. The lines must not be capped in finished areas, but must be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor must make a thorough survey with the Contracting Officer’s Representative of areas of building in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the
Contracting Officer or Contracting Officer’s Representative. This report must list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, 01 00 00 - 10 shades, etc., required by drawings to be either reused or relocated, or both.
3. Must note any discrepancies between drawings and existing conditions at site.
4. Must designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, must be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together must make a thorough re-survey of the areas of buildings involved. They must furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report must also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they must be protected against water infiltration. In case of leaks, they must be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place must be adequately
01 00 00 - 11 protected prior to starting work, and this protection must be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, must be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags as items to be stored. Items that remain property of the Government must be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved will become property of the Contractor and be removed by Contractor from Medical Center at Contractor’s expense.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract must remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor must preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor must only remove trees when specifically authorized to do so, and must avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor must trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer or
Contracting Officer’s Representative.
B. The Contractor must protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor must repair any damage to those
01 00 00 - 12 facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer or Contracting Officer’s Representative may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected
Subcontractors must furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, 01 00 00 - 13 do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, must be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, must conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, must be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor must immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA - NOT USED
1.12 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own
01 00 00 - 14 expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.
The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the
Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the
Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each stair and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such stair structure are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark
(through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed. Contractor’s registered surveyor is required to perform and show on the survey drawing
01 00 00 - 15 the underground utility locating and ground penetrating radar
(GPR) to determine locations of the underground utilities.
D. During progress of work, and particularly as work progresses from landing to landing and connects to floors and roofs, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.
Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The Contractor must maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations must be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings must be made available for the COR review, as often as requested.
01 00 00 - 16
C. Contractor must deliver two approved completed sets of “as-built” drawings in electronic versions of scanned PDF’s and editable AutoCad files to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C also applies to all shop drawings.
E. Prior to project close out, Contractor to furnish “As Built” drawings to include (but is not limited to) electrical, plumbing, mechanical, and architectural.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads must be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.16 COR’S FIELD OFFICE - NOT USED
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment must be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements must be properly sized, coordinated and adjusted.
01 00 00 - 17
Installation of temporary electrical equipment or devices must be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations.