55 OG B500 3C5 Comm PWS.pdf
PDF 218 KB Posted
- Solicitation number
- FA46003C5Connectivity
About this file
This document is a Performance Work Statement (PWS) that defines the requirements for the contractor to engineer, furnish, install and test new and existing premise wiring in Building 500, Room 3C5 at Offutt Air Force Base, NE. The PWS covers networking requirements for the Non-classified Internet Protocol Router Network (NIPRNet) and Secure Internet Protocol Router Network (SIPRNet), including procuring and installing new network switches. The contractor must comply with various industry standards, provide quality assurance, adhere to security requirements, and deliver project deliverables such as as-built drawings, test plans, and test reports. The period of performance is not to exceed three months. This PWS is related to a pre-solicitation federal contract opportunity seeking information for market research purposes on the multi-enclave premise wiring and network equipment installation supporting the 55th Operations Group in Building 500, Room 3C5 at Offutt AFB, NE.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK
STATEMENT – PWS
FOR
MULTI ENCLAVE PREMISE WIRING
AND NETWORK EQUIPMENT INSTALLS
SUPPORTING THE 55 OG IN
B500 3C5
AT
Offutt AFB, NE
30 April 2024
Table of Contents
1.0 INTRODUCTION
2.0 REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.2 NETWORKING REQUIREMENTS
2.3 BASE SUPPORT REQUIREMENTS
2.4 RESTORATION
2.5 PROJECT RESIDUE
2.6 SCHEDULE
2.7 PROJECT MANAGER ON SITE
2.8 QUALITY ASSURANCE
2.9 COMPLIANCE
2.10 CLEANUP
2.11 ENVIRONMENTAL MANAGEMENT
2.12 INTEGRATED PRODUCT TEAM
2.13 WALK0THROUGH
3.0 DELIVERABLES
3.1 LIST OF DELIVERABLES
3.2 CUTOVER PLAN
3.3 ACCEPTANCE TEST PLAN
3.4 AS-BUILT DRAWINGS
3.5 TESTING REQUIREMENTS
4.0 WARRANTY
5.0 PERFORMANCE
5.1 PERIOD OF PERFORMANCE
5.2 PLACE OF PERFORMANCE
5.3 HOURS OF WORK
6.0 GOVERNMENT FURNISHED INFORMATION
7.0 SECURITY
8.0 ATTACHMENTS
Page Intentionally Left Blank
1.0 INTRODUCTION. This Performance Work Statement (PWS) defines the requirements for the Contractor to engineer, furnish, install and test (EFI&T) new and existing premise wiring in building 500 3C5 at Offutt AFB, NE. Newly installed premise wiring will support Non-classified Internet Protocol Router Network (NIPRNet) and Secure Internet Protocol Router Network (SIPRNet). The PWS also defines requirements for the contractor to procure to 55 CYS/AT&T specifications and, upon arrival, engineer, furnish, install and test (EFI&T) new network switches for both NIPRNet and SIPRNet.
2.0 REQUIREMENTS.
2.1 General Requirements. The Contractor shall provide all new install materials, transportation, labor, management, tools, and other incidentals necessary to meet the requirements as stated in this PWS. All materials provided shall be new and not refurbished. The Contractor will work with AT&T EITaaS to determine what is deemed new install and preexisting install. All switches will be new and not refurbished. All materials will meet the Trade Act Agreement (TAA) compliance. The Contractor shall engineer, furnish, and install the infrastructure as defined herein.
2.2 Networking Requirements: The Contractor shall complete the following requirements.
2.2.1 3C5 Requirements
2.2.1.1 Contractor will procure the switches identified in the parts list provided by the 55 CYS.
2.2.1.2 Unless otherwise noted, all new install horizontal cabling will be GREEN or RED colored OM4 FIBER and shall be terminated in patch panels located in the 3C5 or the servicing Comm Rm as needed to fulfill customer requirements. For new cable installations, cables will terminate as proposed by 55 CYS. All NIPRNet and SIPRNet switches and patches shall be installed in appropriately marked racks, and patch panels located within 3C5 or the servicing Comm Rm.
2.2.1.3 User drop locations indicated on sketch are approximate. The Contractor shall verify all locations with 55 CYS.
2.2.1.4 Areas indicated in the sketches are composed of various types of workspaces, the Contractor shall verify appropriate hardware required for cable routing, installation, and termination.
2.2.1.5 Existing cable pathways within walls may be reused if within general location of User drop indicated on sketches and meet data throughput requirements.
2.2.1.6 New Data Drop installation(s) shall be at the same height as existing electrical outlets above the finish floor for easy access for patch cord connections. see BICSI TDMM and TIA-569-E sections
6.7.3. If ADA or modular furniture is a factor see TIA-569-E sections 6.7.3. through 6.7.7
2.2.1.7 Install cable support hardware for the entire cable run per Industry and Installation standards.
Table of standards located in section 6.1. All cables shall be routed with a structured and orderly manner. Secure cable(s) with support hardware i.e. J-hooks or Cable tray, and/or furniture where applicable. If J-hooks are utilized, they shall be spaced every 36 inches.
2.2.1.8 The Contractor shall make use of existing room penetrations for switch uplink fiber.
2.2.1.9 The Contractor shall NOT cut, core, drill into walls without express permission of the 55 CYS/CYEP, 55 CYS/CYESS, 55 WG/IP, and 55 WG/SSO.
2.2.1.10 Install plenum rated cables where required by industry and applicable standards. Table of standards located in section 6.1.
2.2.1.11 Install OS2 single mode (Switch Uplink) and/or OM4 multi-mode (End User Devices) fiber cables as applicable at the locations indicated in sketches. Note: Building Floor plans are not to scale.
2.2.1.12 Fiber optic cables shall be terminated in new fiber optic distribution panels (FODPs) using LC fusion splice pigtails or fusion direct connectors. Distribution panels shall be designed for rack mounting in 19-in (48 cm) racks. Panels shall be sized accordingly to cable capacity and method of termination. Fiber Optic Distribution Panels shall be compatible with Offutt’s existing fiber optic distribution panels.
2.2.1.13 End user Wall Outlet (WO) fiber terminations shall be: NIPR: LC, SIPR: LC.
2.2.1.14 NIPRNET End user Wall Outlets (WO) shall be placed in a separate Wall Outlets (WO) than SIPRNET with a separation of a minimum of 5cm from all other networks. The wall jacks will be green.
2.2.1.15 SIPRNET End user Wall Outlets (WO) shall be placed in a separate Wall Outlets (WO) than NIPRNET with a separation of a minimum of 5cm from all other networks. The wall jacks will be red.
2.2.1.16 End user Wall Outlets (WO) shall have cable installed for each network: NIPRNet and SIPRNet.
Refer to attachment 1 for Building Layout.
2.2.1.17 All NIPRNet cabling shall have a “GREEN” colored sheath for identification or “GREEN” tape marked every 3 ft of cable per standard for secure areas. If J-Hooks are utilized, tape markings will remain unobstructed.
2.2.1.18 All SIPRNet cabling shall have a “RED” colored sheath for identification or “RED” tape marked every 3 ft of cable per standard for secure areas. If J-Hooks are utilized, tape markings will remain unobstructed.
2.2.1.19 All termination hardware, cable components, and cables shall meet industry standard and be compliant with BICSI/TIA and Unified Facilities Code (UFC) 3-580-1 standards specified in table 6.1. Termination hardware to include but not limited to termination modules, patch panels, FODPs, etc. All cabling and terminations hardware shall be new and not refurbished.
2.2.1.20 Label all new premise wiring installations with Offutt AFB/AT&T label scheme. Faceplate and patch panels shall both be labeled. Labeling will be completed via permanent method.
Handwritten labeling is not authorized. Labeling scheme shall be coordinated with AT&T for their standard.
2.2.1.21 Test and certify all new cable installations to the specifications listed in Table 6.1. Document test results for review and reference.
2.2.1.22 Contractor will remove and dispose of any unused cabling, wall terminations, patch panels, and within furniture. Contractor must coordinate what is considered unused with the 55 CYS and 55 SCS before removal.
2.2.1.23 Any cabling removed in error will be replaced by the contractor and tested and certified.
2.2.1.24 All working area(s) shall be restored to original condition IAW Offutt AFB policy.
2.2.1.25 All NIPRNet and SIPRNet switches and networking hardware must be coordinated with AT&T to meet the EITaaS/AT&T network and BAN transformation model moving forward at Offutt
AFB, NE.
2.2.1.27. Should a situation occur that has two or more of the above stated requirements in conflict, Clarification will be provided by 55 CYS/CYEP
2.2.1.28 Contractors are responsible to remove all Abandoned In Place (AIP) and dead cabling with in the space. Coordination with 55 CYS/CYEP is required before removal.
2.2.1.29 LC-LC 1m and 3m FO patch cords will be provided for the comm room equipment and the end user Wall Outlet areas. The patch cords will be the color of the network it is serving. Consult 55 CYS/CYEP for clarification.
2.3 Base Support Requirements. The Contractor must identify any base support requirements (for example, laydown and storage areas) necessary to complete this project. The Contractor shall coordinate with 55CYS/CYEP for storage space and staging area requirements. Any questions or concerns that come up shall be brought up to 55CYS/CYEP before commencement. The Contractor will work with AT&T to determine what is deemed new install and preexisting install, coordination for access to the spaces and comm rooms.
2.4 Restoration. The Contractor shall restore all disturbed grounds/base property to the “as found” condition or better after installation. Base grounds/property restoration requirements shall be complied with.
2.5 Project Residue. All residues from this project shall be disposed off base and IAW Federal, State, local, and base environmental laws and regulations. The Contractor is wholly responsible for project waste removal. Any removed copper premise wiring shall be transported to base Recycling Center.
Contractor may use base Recycling Center to dispose of other project waste materials but shall verify which waste materials the Recycling Center will accept. Any unused material that was purchased by the government for this project will be turned over to the government.
2.6 Schedule. The Contractor shall provide a complete milestone schedule that denotes major activities to include time-phased start and completion dates for this project and sub-projects associated with the installation of the components and systems.
2.7 Project Manager on Site. The Contractor shall provide a full time, on-site Project Manager (PM) to oversee all facets of the project.
2.8 Quality Assurance. The Contractor shall provide quality assurance support for the entire life of the project. This support shall allow and assist the government representative in performing random spot checks and in performing the system acceptance tests. Contractor QA and Government representatives shall be responsible for identifying system and outside/inside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) will be submitted indicating project progress/statuses and listings any deficiencies/discrepancies found and actions to correct them.
2.9 Compliance. The Contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.
2.10 Clean up. At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Equipment and materials required to complete the work effort may remain on site if they are organized/stored in a manner that does not cause a safety hazard.
2.11 Environmental Management. The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The installer shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Offutt AFB NE. The Prime Contractor shall ensure their sub-contractors (if any) comply with these specifications. Asbestos may be present at all buildings within the scope of this project. But the presence of asbestos along, adjacent, or within existing cable runs is not anticipated. If asbestos is discovered during the installation phase of this project, the Contractor shall stop work and contact 55CYS/CYEP for disposition.
2.12 Integrated Product Team (IPT). The Contractor shall chair a weekly IPT meeting consisting of
Contractor representatives, the Contracting Officer, Program Manager, Engineer, and representatives of the 55 Cyberspace Squadron. The purpose of this meeting is to discuss project progress, problems being encountered, and other discussions necessary/beneficial to ensure success and timely completion of the PWS.
2.13 Walk-Through. The Contractor shall schedule a final project walk-through of all work completed prior to close out with the government Project Manager. This should be scheduled at least 72 hours prior to the event.
3.0 DELIVERABLES.
3.1 List of Deliverables. All deliverables are subject to Government acceptance and approval.
They shall meet professional standards and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:
Data Item Title
As Built Work Schedule Status Report Meeting Minutes Test Report Test Plan
3.2 Cutover Plan: Reserved.
3.3 Acceptance Test Plan: The Contractor shall provide a detailed acceptance test plan of the installation covering all aspects of the installation and demonstrate the acceptability of the work on meeting the government requirement. The Contractor shall perform all tests and document results of tests with government witnesses overseeing the acceptance testing per TIA-526-7, TIA-526-14-C and
TIA568.2-D.
3.4 As-Built Drawings: The Contractor shall provide as-built drawings for the installed equipment to include where and how they connect/interface with each other and existing base. As-built red line drawings (either in CAD or MS VISIO with a courtesy copy in PDF format) shall depict new cables, panels terminated and test results. Drawings shall contain floorplans, comm closet locations, rack elevations, grounding, and locations of installed cable routes/trays, etc.
3.5 Testing Requirements: The Contractor shall perform testing and inspections of all systems solutions to ensure the technical adequacy and accuracy of all work, including reports and other documents required in support of that work. The Contractor shall conduct on-site testing in accordance with the Original Equipment Manufacturer’s installation manuals, practices, and the appropriate vendor’s test procedures. The Contractor shall provide a detailed test plan to be performed per TIA-526-7 for single mode fiber, TIA-526-14-C for multi-mode fiber and TIA568.2-D for balanced twisted-pair.
4.0 WARRANTY
The vendor shall provide a one-year warranty or manufacturer’s standard commercial warranty, whichever is longer. The vendor shall also provide a one-year workmanship warranty. The warranty period shall start from the date of system and or project acceptance.
5.0 PERFORMANCE.
5.1 Period of Performance. The period of performance for the project shall not exceed three months after the start of the project.
5.2 Place of Performance. The place of performance is Offutt AFB NE.
5.3 Hours of Work. The Contractor shall routinely work during normal operating hours (0700 to
1630) of the site. Monday through Friday, excluding federal holidays. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the Base POC at least five working days in advance. The Contracting Officer must be notified in advance if there is any cost impact for this work.
6.0 GOVERNMENT FURNISHED INFORMATION/ACCESS/STANDARDS.
6.1 The Contractor shall comply with all base installation standards. Installation technicians shall be familiar with appropriate Commercial/Military/Local Installation Standards. Installation tasks shall be performed in accordance with the appropriate installation standards and practices.
Installation Contractor shall comply with all commercial codes and standards to include but not limited to the following:
NUMBER TITLE WEBSITE OR LOCATION
BICSI Building Industry Consulting Service
International, Inc (BICSI) http://www.bicsi.org/
BICSI Telecommunications Distribution Methods Manual (TDMM) 14 Edition Vol I and II http://www.bicsi.org/
NFPA 70 (2020) National Fire Protection Association (NFPA), National Electric Code (NEC) http://www.nfpa.org/
ANSI American National Standards Institute (ANSI) and Internet Standards Resources http://www.ansi.org/
TIA Telecommunications Industry Association Engineering: TIA Standards See Commodity Specific Appendices and Individual Task Orders http://www.tiaonline.org/
TIA-526-7 Measurement of Optical Power Loss of Installed Single-Mode Fiber Cable Plant https://www.ansi.org/ http://www.tiaonline.org/
TIA-526-14-C Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-568-0.E
(2020)
Generic Telecommunications Cabling for Customer Premises https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-568-1.E
(2020)
Commercial Building Telecommunications Cabling Standard https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-568.2-D
(2018)
Balanced Twisted-Pair Telecommunications Cabling and Components Standard https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-568-3.D
(2016)
Optical Fiber Cabling Components https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-569-E
(2019)
Commercial Building Standards for Telecommunications Pathways and Spaces https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-606-C
(2017)
Administration Standard for Commercial Telecommunications Infrastructure https://www.ansi.org/ http://www.tiaonline.org/
ANSI/TIA-607-D
(2019)
Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises https://www.ansi.org/ http://www.tiaonline.org/
EIA/ECA-310-E
(Dec 2005)
Cabinets, Racks, Panels, and Associated Equipment https://www.ansi.org/ http://www.tiaonline.org/
ISO/IEC 111801
(2017)
Generic Cabling for customer premises https://www.iso.org/home.html https://www.iec.ch/
IEEE 802 Standards Generic Cabling for Customer Premises https://www.ieee.org/ http://www.bicsi.org/ http://www.bicsi.org/ http://www.nfpa.org/ http://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.ansi.org/ http://www.tiaonline.org/ https://www.iso.org/home.html https://www.iec.ch/ https://www.ieee.org/
ICEA S-80-576
(2002)
-IEEE 802.3af Power over Ethernet (PoE) Standard -IEEE 802.3at Power over Ethernet+ (Plus) Standard -IEEE 802.3an Physical Layer and Management Parameters for 10 Gbps Operation Type 10GBASE-T -IEEE 802.3ba Media Access Control Parameters, Physical Layers and Management Parameters for 40 Gbps and 100 Gbps Operation -IEEE 802.11 Wireless Standard
Insulated Cable Engineer Association, Inc., P.O.
Box P, South Yarmouth MA 02664; Telephone
(508) 394-4424
NEMA TC 2
(2013)
Telecommunications Wire and Cable for Wiring of Premises http://www.nema.org/index_nema.cfm/1260/
UFC 3-580-01
(2016)
Electrical Polyvinyl Chloride (PVC) Tubing and Conduit https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-580-01
I3A (2016) Whole Building Design Guide Telecommunications Interior Infrastructure Planning and Design https://www.lrl.usace.army.mil/Portals/64/docs/ Engineering/Design_Army_Res/i3a.pdf
The Contractor shall obtain and comply with any other applicable manuals not identified above that would be required to meet industry standards.
7.0 SECURITY
7.1 Stated work and associated products shall be performed at the UNCLASSIFIED level.
However, when access to classified areas will be required, selected personnel who install network equipment, test network equipment and cutover network equipment may be required to obtain a minimum of DoD Secret Security Clearance. Government escorts will be required, as work will be performed in secure facilities. It is the Government’s responsibility to provide escorts.
7.2 The Contractor shall process a Site Visit Request Letter (will be provided as needed). This letter shall identify the names, social security numbers, driver’s license numbers and state of issue, and birth date of the personnel who will performing on this PWS. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.
7.3 Complete Installation Access Application form (will be provided as needed). Access requests should be made thru 55CYS/CYEP and AT&T. Access requests shall be submitted at least one
(1) week prior to scheduled arrival.
7.4 All personnel working in the secure area must be U.S. Persons and comply with all security vetting and protocols. After the company has been properly vetted and a contract has been awarded, the company will be required to submit employee information on all employees that will be working within the facility in electronic form, within five business days of receipt of the request from the contracting office, 55 CONS. Personnel vetting can take up to 30 days. Each employee will be vetted by the facility accrediting official. Only upon a positive vetting will an employee be permitted to work in the facility.
http://www.nema.org/index_nema.cfm/1260/ https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-580-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-580-01 https://www.lrl.usace.army.mil/Portals/64/docs/Engineering/Design_Army_Res/i3a.pdf https://www.lrl.usace.army.mil/Portals/64/docs/Engineering/Design_Army_Res/i3a.pdf
Attachments
Attachment 1: Full Requirement Diagrams (3C5 Comm Requirements)
| 2.0 REQUIREMENTS. |
| 2.2.1 3C5 Requirements |
| 3.0 DELIVERABLES. |
| 3.2 Cutover Plan: Reserved. |
| 4.0 WARRANTY |
| 5.0 PERFORMANCE. |
| 6.0 GOVERNMENT FURNISHED INFORMATION/ACCESS/STANDARDS. |
| 7.0 SECURITY |
File details come from the government source that posted it. Updated .