Contract # 36C24419C0200
Project # 529-14-102
Date: June 8, 2020
Status: Final Bid Submission
Prepared For:
Butler VA Medical Center
325 New Castle Road
Butler, PA 16001
Prepared By:
Acela Architects + Engineers, PC
4969 Hamilton Blvd.
Allentown, PA 18106
(610) 365-4023
SPECIFICATIONS
FOR: Repave Hospital Roads
LOCATION: Department of Veterans Affairs
Butler VA Medical Center
Butler VA Medical Center Contract #36C24419C0200 Repave Hospital Roads Project #529-14-102
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18 01 01 10 Medical Center Requirements 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 03-19 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 08-16 02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 07-19
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 02-16 04 05 13 Masonry Mortaring 10-17
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
Not Used
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
Not Used
DIVISION 09 – FINISHES
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 13 00 Directories 05-15 10 14 00 Signage 10-15
00 01 10-2
DIVISION 11 – EQUIPMENT
Not Used
DIVISION 12 – FURNISHINGS
Not Used
DIVISION 13 - SPECIAL CONSTRUCTION
Not Used
DIVISION 14– CONVEYING EQUIPEMENT
DIVISION 21- FIRE SUPPRESSION
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16 22 14 00 Facility Storm Drainage 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
DIVISION 25 – INTEGRATED AUTOMATION
Not Used
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
Not Used
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
Not Used
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16 31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 17 23 Pavement Markings 08-16 32 90 00 Planting 08-16
00 01 10-3
DIVISION 33 – UTILITIES
33 40 00 Storm Sewer Utilities 12-17
DIVISION 34 – TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
DIVISION 48 – Electrical Power Generation
Butler VA Medical Center Contract #36C24419C020 0
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specifi cation form a part of the contract.
Drawing No. Title
GI001 TITLE SHEET
GI002 GENERAL NOTES SHEET
CS101 OVERALL EXISTING FEATURES & DEMOLITION PLAN
CS102 EXISTING FEATURES & DEMOLITION PLAN ‘A’
CS103 EXISTING FEATURES & DEMOLITION PLAN ‘B’
CS104 EXISTING FEATURES & DEMOLITION PLAN ‘C’
CS105 EXISTING FEATURES & DEMOLITION PLAN ‘D’
CS106 EXISTING FEATURES & DEMOLITION PLAN ‘E’
CS107 EXISTING FEATURES & DEMOLITION PLAN ‘F’
CS108 EXISTING FEATURES & DEMOLITION PLAN ‘G’
CS109 EXISTING FEATURES & DEMOLITION PLAN ‘H’
CS110 EXISTING FEATURES & DEMOLITION PLAN ‘I’
CS111 OVERALL SITE IMPROVEMENT PLAN
CS112 SITE IMPROVEMENT PLAN ‘A’
CS113 SITE IMPROVEMENT PLAN ‘B’
CS114 SITE IMPROVEMENT PLAN ‘C’
CS115 SITE IMPROVEMENT PLAN ‘D’
CS116 SITE IMPROVEMENT PLAN ‘E’
CS117 SITE IMPROVEMENT PLAN ‘F’
CS118 SITE IMPROVEMENT PLAN ‘G’
CS119 SITE IMPROVEMENT PLAN ‘H’
CS120 SITE IMPROVEMENT PLAN ‘I’
CS121 GRADING & UTILITY PLAN ‘A’
CS122 GRADING & UTILITY PLAN ‘B’
CS123 GRADING & UTILITY PLAN ‘C’
CS124 GRADING & UTILITY PLAN ‘D’
CS125 GRADING & UTILITY PLAN ‘E’
CS126 GRADING & UTILITY PLAN ‘F’
CS127 GRADING & UTILITY PLAN ‘G’
CS128 GRADING & UTILITY PLAN ‘H’
CS129 GRADING & UTILITY PLAN ‘I’
CS130 SPOT GRADE PLAN ‘A’
00 01 15 - 2
CS131 SPOT GRADE PLAN ‘B’
CS132 SPOT GRADE PLAN ‘C’
CS133 SPOT GRADE PLAN ‘D’
CS134 SPOT GRADE PLAN ‘E’
CS135 SPOT GRADE PLAN ‘F’
CS136 SPOT GRADE PLAN ‘G’
CS137 SPOT GRADE PLAN ‘H’
CS138 SPOT GRADE PLAN ‘I’
CS139 ROAD PROFILE PLAN ‘A’
CS140 ROAD PROFILE PLAN ‘B’
CS141 ROAD PROFILE PLAN ‘C’
CS142 ROAD PROFILE PLAN ‘D’
CS143 ROAD PROFILE PLAN ‘E’
CS144 ROAD PROFILE PLAN ‘F’
CS145 ROAD PROFILE PLAN ‘G’
CS146 ROAD PROFILE PLAN ‘H’
CS147 ROAD PROFILE PLAN ‘I’
CS148 ROAD PROFILE PLAN ‘J’
CS149 ROAD PROFILE PLAN ‘K’
CS150 ROAD PROFILE PLAN ‘L’
CS151 ROAD PROFILE PLAN ‘M’
CS152 ROAD PROFILE PLAN ‘N’
CS153 TYPICAL CROSS SECTION PLAN ‘A’
CS154 TYPICAL CROSS SECTION PLAN ‘B’
CS155 TYPICAL CROSS SECTION PLAN ‘C’
CS156 TYPICAL CROSS SECTION PLAN ‘D’
CS157 TYPICAL CROSS SECTION PLAN ‘E’
CS158 RAMP DETAIL PLAN
CS159 SOIL & EROSION CONTROL PLAN ‘A’
CS160 SOIL & EROSION CONTROL PLAN ‘B’
CS161 SOIL & EROSION CONTROL PLAN ‘C’
CS162 SOIL & EROSION CONTROL PLAN ‘D’
CS163 SOIL & EROSION CONTROL PLAN ‘E’
CS164 SOIL & EROSION CONTROL PLAN ‘F’
CS165 SOIL & EROSION CONTROL PLAN ‘G’
CS166 SOIL & EROSION CONTROL PLAN ‘H’
CS167 SOIL & EROSION CONTROL PLAN ‘I’
00 01 15 - 3
CS168 SOIL & EROSION CONTROL DETAILS
CS169 SOIL & EROSION CONTROL DETAILS
CS170 CONSTRUCTION DETAILS
CS171 CONSTRUCTION DETAILS
- - - END - - -
i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 WARRANTY MANAGEMENT
1.16 USE OF ROADWAYS
1.17 RESIDENT ENGINEER'S FIELD OFFICE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 TEMPORARY USE OF NEW ELEVATORS
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
1.23 NEW TELEPHONE EQUIPMENT
1.24 TESTS
1.25 INSTRUCTIONS
ii
1.26 GOVERNMENT-FURNISHED PROPERTY
1.27 RELOCATED // EQUIPMENT // ITEMS //
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.29 CONSTRUCTION SIGN
1.30 SAFETY SIGN
1.31 PHOTOGRAPHIC DOCUMENTATION
1.32 FINAL ELEVATION Digital Images
1.33 HISTORIC PRESERVATION
1.34 VA TRIRIGA CPMS
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for bui lding operations, including demolition and removal of existing struct ures, and furnish labor and materials and perform work for Project #5 29-14-102 as required by drawings and specifications.
B. For the purposes of these project specifications , all references to resident engineer shall be Contract Office Represen tative
(COR)/Resident Engineer.
C. Visits to the site by Bidders may be made only b y appointment with the
Medical Center Engineering Officer or COR.
D. Offices of Acela Architects + Engineers, PC, as Architect-Engineers, will render certain technical services during const ruction. Such services shall be considered as advisory to the Gov ernment and shall not be construed as expressing or implying a contra ctual act of the
Government without affirmations by Contracting Offi cer or his duly authorized representative.
E. Before placement and installation of work subjec t to tests by testing laboratory retained by Department of Veterans Affai rs, the Contractor shall notify the COR in sufficient time to enable t esting laboratory personnel to be present at the site in time for pro per taking and testing of specimens and field inspection. Such pri or notice shall be not less than three work days unless otherwise desi gnated by the COR.
F. All employees of general contractor and subcontr actors shall comply with VA security management program and obtain perm ission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I,REPAVE HOSPITAL ROADS: Work includes all labor, tools, resources, material, equipment, temporary fencing, signage, permits, supervision, and traffic control to complete all im provements, and other items identified within and per the design pl ans and specifications titled “REPAVE HOSPITAL ROADS”; incl uding, all demolition, asphalt pavement reconstruction, paveme nt mill/overlay, curbing and gutters, sidewalk improvements, ramp im provements, parking lot and road striping, grading, drainage and stormw ater improvements, utility improvements, lighting relocation and assoc iated electrical work including wiring, conduits, light poles, light bases, light fixtures, and connection to existing circuits, relo cation of solar emergency communication boxes, laboratory equipment , landscaping and lawn restoration.
B. BID DEDUCTS:
1. Removes work associated with the reconstruction of Hospital Road between Evans City Road and B Street, including all improvements south of the deduct line shown on the plans. Deduct 1 includes all demolition, pavement, curb and gutter, utility, dra inage, landscaping, and lighting improvements. The contrac tor shall coordinate with the COR to determine tie in locatio ns of the proposed improvements to Hospital Road and B Street .
2. Removes work associated with the reconstruction of Building 46 parking lot, including all improvements east of the deduct line shown on the plans. Deduct 2 includes all demolitio n, pavement, utility, and drainage improvements. The contractor shall coordinate with the COR to determine tie in locations of the p roposed improvements along Second Street.
3. Removes work associated with the reconstruction of First Street, west of Hospital Road (between Buildings 6, 7, 8, a nd 46, including all improvements west of the deduct line shown on t he plans. Deduct
3 includes all demolition, pavement, utility, and d rainage improvements. The contractor shall coordinate with the COR to determine tie in locations of the proposed improvem ents along
Hospital Road, Second Street (west of Building 46), and the Salt
Shed Road.
01 00 00 -3
4. Removes work associated with the reconstruction of concrete curb and gutter along the south side of Hospital Road betwee n station 31+50 and station 33+30. Deduct 3 includes the demolition and replacement of the existing block curb in this area.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and admi nistrative security procedures that will remain effective for the entir e duration of the project.
2. The General Contractor is responsible for assuri ng that all sub-contractors working on the project and their employ ees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter t he project site without appropriate badge. They may also be subjec t to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shal l give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is sepa rate from any notices required for utility shutdown described lat er in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the pr emises in the event of a national emergency. The General Contrac tor may return to the site only with the written approval of the Cont racting Officer.
C. Guards:
01 00 00 -4
D. Key Control:
1. The General Contractor shall provide duplicate k eys and lock combinations to the Contracting officers representa tive (COR)for the purpose of security inspections of every area of pr oject including tool boxes and parked machines and take any emergen cy action.
E. Document Control:
1. Before starting any work, the General Contractor /Sub Contractors shall submit an electronic security memorandum desc ribing the approach to following goals and maintaining confide ntiality of
“sensitive information”.
2. The General Contractor is responsible for safeke eping of all drawings, project manual and other project informat ion. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photograp hs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Re turn the information to the Contracting Officer upon request .
4. These security documents shall not be removed or transmitted from the project site without the written approval of Co ntracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Off icer immediately when there is a loss or compromise of “sensitive in formation”.
7. All electronic information shall be stored in sp ecified location following VA standards and procedures using an Engi neering Document
Management Software (EDMS).
01 00 00 -5
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and track ed through the
EDMS system.
b. “Sensitive information” including drawings and o ther documents may be attached to e-mail provided all VA encryptio n procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitt ed 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be is sued for General
Contractor and its employees for parking in designa ted areas only.
G. Working Hours
1. The regular working hours are from 7:30 am to 4: 00 pm, Monday through Friday. The contractor shall not perform wo rk outside regular working hours, or on Saturdays, Sundays, or legal holidays.
The contractor shall receive approval from the COR to work outside the regular working hours, weekends, or legal holid ays. The contractor shall coordinate the schedule of all wor k with the COR.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (inc luding storage of materials) on Government premises to areas authoriz ed or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harml ess from liability of any nature occasioned by the Contractor's perfor mance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the appr oval of the
Contracting Officer and shall be built with labor a nd materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor a t its expense upon completion of the work. With the written consent of the Contracting
01 00 00 -6
Officer, the buildings and utilities may be abandon ed and need not be removed.
C. The Contractor shall, under regulations prescrib ed by the Contracting
Officer, use only established roadways, or use temp orary roadways constructed by the Contractor when and as authorize d by the Contracting
Officer. When materials are transported in prosecut ing the work, vehicles shall not be loaded beyond the loading cap acity recommended by the manufacturer of the vehicle or prescribed by an y Federal, State, or local law or regulation. When it is necessary to cr oss curbs or sidewalks, the Contractor shall protect them from d amage. The
Contractor shall repair or pay for the repair of an y damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing ma terials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center a pplicable to their conduct.
Execute work in such a manner as to interfere as li ttle as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
F. Execute work so as to interfere as little as pos sible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any e xisting equipment, and with work being done by others. Use of equipmen t and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during co nstruction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR where required by limited work ing space.
1. Do not store materials and equipment in other th an assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas. Provide unobstructed ac cess to Medical
Center areas required to remain in operation.
01 00 00 -7
3. Where access by Medical Center personnel to vaca ted portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and saf ety requirements.
G. Utilities Services: Where necessary to cut exis ting pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (excep t telephone), they shall be cut and capped at suitable places where sh own; or, in absence of such indication, where directed by the COR. All such actions shall be coordinated with the COR or Utility Company invo lved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the c onstruction project, for such items as water, sewer, electricit y, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses i n operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim lif e safety measure to be used during the work, and a schedule defining th e duration of the work with milestone subtasks. The work to be outli ned shall include, but not be limited to:
To ensure such executions, Contractor shall furnis h the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, b uilding or portion thereof. In addition, Contractor shall notify the C OR two weeks in advance of the proposed date of starting work in ea ch specific area of site, building or portion thereof. Arrange such pha sing dates to ensure accomplishment of this work in successive phases mu tually agreeable to
Medical Center Director, COR and Contractor, as fol lows:
H. (Deleted)
01 00 00 -8
I. Construction Fence: Before construction operatio ns begin, Contractor shall provide a chain link construction fence, 2.4m (eight feet) minimum height, around the construction area indica ted on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails wi th tie wires spaced at maximum 375mm (15 inches). Bottom of fences shal l extend to 25mm
(one inch) above grade. Remove the fence when direc ted by COR.
J. When a building and/or construction site is turn ed over to Contractor, Contractor shall accept entire responsibility inclu ding upkeep and maintenance therefore:
1. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for p re-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility se rvices for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uni nterrupted services.
Where necessary to cut existing water, steam, gases , sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (incl uding telephone), they shall be cut and capped at suitable places whe re shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, se wers or electricity, or fire protection systems and communications syste ms may be interrupted without prior approval of COR. Electric al work shall be accomplished with all affected circuits or equipmen t de-energized.
When an electrical outage cannot be accomplished, w ork on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s p rior knowledge and written approval. Refer to specification Sectio n 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for addit ional requirements.
01 00 00 -9
2. Contractor shall submit a request to interrupt a ny such services to
COR, in writing, 7 days in advance of proposed inte rruption. Request shall state reason, date, exact time of, and approx imate duration of such interruption.
3. Contractor will be advised (in writing) of appro val of request, or of which other date and/or time such interruption w ill cause least inconvenience to operations of Medical Center. Inte rruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be reques ted, in writing, at least 15 calendar days prior to the desired time an d shall be performed as directed by the COR.
5. In case of a contract construction emergency, se rvice will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the c onstruction project, for such items as water, sewer, electricit y, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires , cables, conduits, ducts, pipes and the like, and their hangers or sup ports, which are to be abandoned but are not required to be entirely re moved, shall be sealed, capped or plugged at the main, branch or pa nel they originate from. The lines shall not be capped in finished are as, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or par titions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activit ies with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to p arking and to occupied areas of buildings clear of construction m aterials, debris and standing construction equipment and vehicles. Wherever
01 00 00 -10 excavation for new utility lines cross existing roa ds, at least one lane must be open to traffic at all times with appr oval.
2. Method and scheduling of required cutting, alter ing and removal of existing roads, walks and entrances must be approve d by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the sc heduling of traffic and the use of roadways, as specified in Article, U SE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contract or shall make a thorough survey with the COR and a representative o f VA Supply Service.
B. Any items required by drawings to be either reus ed or relocated or both, found during this survey to be nonexistent, o r in opinion of the
COR and/or Supply Representative , to be in such co ndition that their use is impossible or impractical, shall be furnishe d and/or replaced by
Contractor with new items in accordance with specif ications which will be furnished by Government. Provided the contract w ork is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "D IFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.24 3-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial o r final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas involved. They shall furnish a report on conditions then existing, as compared with conditions of same as no ted in first condition survey report:
1. Re-survey report shall also list any damage caus ed by Contractor and will form basis for determining extent of repair wo rk required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective mea sures:
01 00 00 -11
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, ma terials handled and equipment moved and/or relocated.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work remov ed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of t he Government are identified by attached tags or noted on drawings o r in specifications as items to be stored. Items that re main property of the Government shall be removed or dislodged from p resent locations in such a manner as to prevent damage which would b e detrimental to re-installation and reuse. Store such items where d irected by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings loca ted in rooms and spaces in which work is to be done under this contr act shall remain the property of the Government. When rooms and spac es are vacated by the Department of Veterans Affairs during the alter ation period, such items which are NOT required by drawings and s pecifications to be either relocated or reused will be removed by th e Government in advance of work to avoid interfering with Contracto r's operation.
4. The Department of Veteran Affairs shall reserve the right to accept any salvaged materials.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all st ructures, equipment, and vegetation (such as trees, shrubs, and grass) o n or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contrac t. The Contractor shall only remove trees when specifically authorize d to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract per formance, or by the careless operation of equipment, or by workers, the Contractor shall
01 00 00 -12 trim those limbs or branches with a clean cut and p aint the cut with a tree-pruning compound as directed by the Contractin g Officer’s
Representative.
B. The Contractor shall protect from damage all exi sting improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any dam age to those facilities, including those that are the property o f a third party, resulting from failure to comply with the requireme nts of this contract or failure to exercise reasonable care in performin g the work. If the
Contractor fails or refuses to repair the damage pr omptly, the
Contracting Officer may have the necessary work per formed and charge the cost to the Contractor. Any damage to existing steam tunnel facilities that occurs during construction shall be repaired by the
Contractor, including damages discovered to facilit ies nearby and within improvement areas.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENT AL CONTROLS, for additional requirements on protecting vegetation, s oils and the environment. Refer to Articles, "Alterations", "Res toration", and
"Operations and Storage Areas" for additional instr uctions concerning repair of damage to structures and site improvement s.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair ex isting work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, an d do not disturb any ducts, plumbing, steam, gas, or electric work witho ut approval of the
COR. Existing work to be altered or extended and th at is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restor ing work, shall conform in type and quality to that of original exi sting construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work comple te and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and
01 00 00 -13 electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work , shall be patched, repaired, reinstalled, or replaced with new work, a nd refinished and left in as good condition as existed before commenc ing work.
C. At Contractor's own expense, Contractor shall im mediately restore to service and repair any damage caused by Contractor' s workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications sy stems (including telephone) which are not scheduled for discontinuan ce or abandonment, including damage to existing steam tunnels and shal low facilities.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered b y adjustment to contract time and price in accordance with clause e ntitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING S ITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to be low is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(FAR 52.236-4)
B. Subsurface conditions have been developed by cor e borings. Core borings were performed in roadways in asphalt. The eighteen (18) core borings provide information related to existing pavement th ickness. Logs of subsurface exploration are shown diagrammatically o n drawings.
D. Government does not guarantee that other materia ls will not be encountered nor that proportions, conditions or cha racter of several materials will not vary from those indicated by exp lorations. Bidders are expected to examine site of work and logs of bo rings; and, after investigation, decide for themselves character of m aterials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
01 00 00 -14
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registe red civil engineer whose services are retained and paid for by the Con tractor shall perform services specified herein and in other spec ification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contrac tor, and that the land surveyor or civil engineer has no financial in terest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Gover nment established base lines and bench marks, indicated on the drawings, a nd shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expen se, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor sha ll be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contra ctor shall also be responsible for maintaining and preserving all stak es and other marks established by the Contracting Officer until author ized to remove them.
If such marks are destroyed by the Contractor or th rough Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the repl acement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark lines and grades that are reasonably necessary to properly assure that location, orienta tion, and elevations established for roads and parking lots are in accor dance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficien t additional survey control points or system of points as may be necess ary to assure proper alignment, orientation, and grade of all major feat ures of work.
1. Such additional survey control points or system of points thus established shall be checked and certified by a reg istered land
01 00 00 -15 surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor sl abs, columns, walls, utilities and other major controlling featur es) is placed.
D. Contractor shall furnish to the COR certificates from a registered land surveyor or registered civil engineer that the foll owing work is complete in every respect as required by contract d rawings:
1. Lines and elevations of roads, streets, sidewalk s, and parking lots
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a re producible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. The Contractor shall perform the surveying and l ayout work of this and other articles and specifications in accordance wit h the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of t he project, to include all contract changes, modifications and cla rifications.
B. All variations shall be shown in the same genera l detail as used in the contract drawings. To ensure compliance, as-built d rawings shall be made available for the COR review, as often as requ ested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all sho p drawings.
1.15 WARRANTY MANAGEMENT (DELETED)
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads a nd roads on Medical
Center property and, when authorized by the COR, su ch temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performe d by the Contractor at Contractor's expense. When necessary to cross cu rbing, sidewalks, or
01 00 00 -16 similar construction, they must be protected by wel l-constructed bridges.
B. When new permanent roads are to be a part of thi s contract, Contractor may construct them immediately for use to facilitat e building operations. These roads may be used by all who have business thereon within zone of building operations.
1.17 RESIDENT ENGINEER'S FIELD OFFICE (DELETED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical e quipment to provide heat, ventilation, plumbing, light and power will b e permitted subject to written approval and compliance with the followi ng provisions:
1. Permission to use each unit or system must be gi ven by the COR in writing. If the equipment is not installed and main tained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipme nt.
2. Electrical installations used by the equipment s hall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. tran sformers, relays, circuit breakers, fuses, conductors, motor controll ers and their overload elements shall be properly sized, coordina ted and adjusted.
Installation of temporary electrical equipment or d evices shall be in accordance with NFPA 70, National Electrical Cod e, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be corr ect and it shall be determined that motors are not overloaded. The e lectrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuu m cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, an d aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for prehea t coils shall function properly and all safety controls shall fun ction to prevent coil freeze-up damage.
01 00 00 -17
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elemen ts shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distributi on system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
Boilers, pumps, feedwater heaters and auxiliary equ ipment must be operated as a complete system and be fully maintain ed by operating personnel. Boiler water must be given complete and continuous chemical treatment.
B. Prior to final inspection, the equipment or part s used which show wear and tear beyond normal, shall be replaced with iden tical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear du e to prolonged use will be repaired replaced by the contractor at the contr actor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS (DELETED)
1.20 TEMPORARY USE OF NEW ELEVATORS (DELETED)
1.21 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contract or's workers) ample temporary sanitary toilet accommodations with suita ble sewer and water connections; or, when approved by COR, provide suit able dry closets where directed. Keep such places clean and free fro m flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfec tly clean.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably require d amounts of utilities available to the Contractor from existing outlets a nd supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevail ing rates charged to
01 00 00 -18 the Government. The Contractor shall carefully cons erve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Con tracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to meas ure the amount of electricity used for the purpose of determining cha rges. Before final acceptance of the work by the Government, the Contr actor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the inf rastructure as required.
C. At the discretion of the COR, Contractor shall i nstall meters at
Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafte r specified.
D. Electricity (for Construction and Testing): Furn ish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisti ng devices, electrical welding devices and any electrical heati ng devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish te mporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no co st to the
Contractor.
2. Maintain connections, pipe, fittings and fixture s and conserve water-use so none is wasted. Failure to stop leakag e or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
01 00 00 -19
1.23 NEW TELEPHONE EQUIPMENT (DELETED)
1.24 TESTS (DELETED)
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operati ng manuals (hard copies and electronic) and verbal instructions when requir ed by the various sections of the specifications and as hereinafter s pecified.
B. Manuals: Maintenance and operating manuals and o ne compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidenta l with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipme nt. They shall include complete information necessary for starting , adjusting, maintaining in continuous operation for long period s of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrati ons. Illustrations shall include "exploded" views showing and identify ing each separate item. Emphasis shall be placed on the use of specia l tools and instruments. The function of each piece of equipmen t, component, accessory and control shall be clearly and thorough ly explained. All necessary precautions for the operation of the equi pment and the reason for each precaution shall be clearly set forth. Man uals must reference the exact model, style and size of the piece of equ ipment and system being furnished. Manuals referencing equipment simi lar to but of a different model, style, and size than that furnishe d will not be accepted.
C. Instructions: Contractor shall provide qualified , factory-trained manufacturers' representatives to give detailed tra ining to assigned
Department of Veterans Affairs personnel in the ope ration and complete maintenance for each piece of equipment. All such t raining will be at the job site. These requirements are more specifica lly detailed in the various technical sections. Instructions for differ ent items of equipment that are component parts of a complete sy stem, shall be given in an integrated, progressive manner. All instructo rs for every piece of component equipment in a system shall be availab le until instructions for all items included in the system h ave been completed.
01 00 00 -20
This is to assure proper instruction in the operati on of inter-related systems. All instruction periods shall be at such t imes as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough covera ge. The contractor shall submit a course outline with associated mater ial to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the co ntractual requirements. The Department of Veterans Affairs r eserves the right to request the removal of, and substitution for, any i nstructor who, in the opinion of the COR, does not demonstrate suffic ient qualifications in accordance with requirements for instructors abo ve.
1.26 GOVERNMENT-FURNISHED PROPERTY
A. Government-furnished property shall be utilized as appropriate. These materials shall be determined by and approved by th e COR.
1.27 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necess ary, remove and reinstall in new location, all existing equipment a nd items indicated on the drawings or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as ste am, condensate return, water, drain, gas, air, vacuum and/or electrical, a t the main whenever such lines are disconnected from equipment to be re located. Remove abandoned lines in finished areas and cap as specif ied herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service co nnections, fittings, fastenings and any other materials necessary for as sembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for reloca ted equipment shall be in place at point of relocation ready for use befor e any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
01 00 00 -21
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT (DELETED)
1.29 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by th e COR. All wood members shall be of framing lumber. Cover sign frame with 0 .7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) int o ground. Set bottom of sign level at 900 mm (three feet) above ground a nd secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats o f white gloss paint.
Border and letters shall be of black gloss paint, e xcept project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
D. Detail Drawing of construction sign showing requ ired legend and other characteristics of sign can be found on VA TIL.
1.30 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Fac e of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shal l be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR .
D. Standard Detail Drawing Number SD10000-02 of saf ety sign showing required legend and other characteristics of sign c an be found on VA
TIL.
E. Post the number of accident free days on a daily basis.
01 00 00 -22
1.31 PHOTOGRAPHIC DOCUMENTATION (DELTED)
1.32 FINAL ELEVATION DIGITAL IMAGES (DELETED)
1.33 HISTORIC PRESERVATION
Where the Contractor or any of the Contractor's em ployees, prior to, or during the construction work, are advised of or dis cover any possible archeological, historical and/or cultural resources , the Contractor shall immediately notify the COR verbally, and then with a written follow up.
1.34 VA TRIRIGA CPMS (DELETED)
- - - E N D - - -
01 01 10 - 1
SECTION 010110
MEDICAL CENTER REQUIREMENTS
PART 1 GENERAL
1.0 GENERAL INTENTION: This section pertains to station policy for construction projects performed at the Veterans Affairs Medical Center, Butler, Pennsylvania. Safety and health concerns are taken seriously at this facility. Both our staff and yours are expected to strictly adhere to the regulations and requirements. This is exceedingly important, since we must be primarily concerned for the safety of our patients. In this regard, OSHA Standards may protect worker safety and health, but they have minimal benefit for protecting the safety and health of our patients, due primarily to their differing medical conditions. Review this information as orientation with your personnel performing work on site. Where the requirements as outlined in this and section 01010 are differing, the more stringent shall apply.
2.0 REQUIREMENTS
A. Security:
1. Secure all construction areas, especially mechanical and electrical rooms against entry of unauthorized individuals including patients.
2. Notify the COTR for permission to work after hours and weekends.