Z1DA--528-22-129 SUBBASEMENT EXCAVATION FOR STEAM REPAIRS
Solicitation number
36C24222B0057
Issued by

About this file

This federal contract opportunity solicitation requests proposals for a subbasement excavation and steam repairs project at the Buffalo VA Medical Center. Key details include:

  • The solicitation number is 36C24222B0057 for project 528-22-129.

  • The project scope involves general construction, electrical, mechanical, and plumbing work for subbasement excavation and replacement of waste, vent, steam supply, and condensate return lines exposed during demolition of walk-in coolers and freezers.

  • The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2.

  • The response due date and award date are not provided.

  • Pricing terms or set-asides are not specified.

  • The incumbent is not identified.

View the file

Other files

File Type Posted
S02 528-22-129 Drawings_rev1.pdf PDF
S02 Wage Determination.pdf PDF
36C24222B0057_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUB BASEMENT EXCAVATION FOR STEAM REPAIRS CONSTRUCTION DOCUMENTS

BUFFALO VA MEDICAL CENTER | BUFFALO, NY 05/17/2022

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 33 23 Shop Drawings, Product Data, and Samples 03-20 01 35 26 Safety Requirements 05-22 01 42 19 Reference Standards 11-21 01 74 19 Construction Waste Management 02-21

DIVISION 02 – EXISTING CONDITIONS

02 82 13.13 Glovebag Asbestos Abatement

DIVISION 03 – CONCRETE

03 30 53 Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 20 00 Unit Masonry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping

DIVISION 08 - OPENINGS

08 31 13 Access Doors and Frames 08 71 00 Door Hardware 01-21

DIVISION 22 - PLUMBING

22 05 11 Common Work Results for Plumbing 22 13 33 Submersible Sewage Pump Units

DIVISION 26 – ELECTRICAL

26 05 33 Raceway and Boxes for Electrical Systems 26 51 00 Interior Lighting 01-18

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 06-15

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI-001 TITLE SHEET AND DRAWING INDEX

HAZARDOUS MATERIALS

HA-101 ASBESTOS ABATEMENT PLAN

CIVIL

CP-101 SUB BASEMENT EXCAVATION PLAN

CP-501 SUB BASEMENT DOOR AND FILL PLAN

ELECTRICAL

ED-101 ELECTRICAL DEMOLITION PLAN

EL-101 ELECTRICAL LIGHTING & EMERGENCY POWER PLAN

PLUMBING

PP-101 DRAINAGE PLAN

- - - END - - -

Section 01 00 00 CFM: 01 Nov 2015 General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

SECTION 01 00 00

GENERAL REQUIREMENTS

INTRODUCTION

This document is a modified version of the 01 00 00 (General Requirements) available from the Technical Information Library (TIL). It has been modified by VA Western New York Healthcare System (VAWNYHS) to include site specific information and delete irrelevant information. This VAWNYHS modified version of the 01 00 00 (General Requirements) should be used as the basis of construction efforts conducted at VAWNYHS.

The unmodified version of 01 00 00 (General Requirements) can be found on the

Department of Veteran’s Affairs, Office of Construction and Facilities

Management (CFM) website:

http://www.cfm.va.gov/til/index.asp

As new versions of 01 00 00 (General Requirements) are posted on the TIL by

CFM, VAWNYHS will review, modify, and publish a new local version at:

G:\MS-Engineering-SOP\Projects\General\Doc Templates\SPECIFICATIONS- Local

Masters

When a project specific modification to this document has been made, enter the project information below and update the Record of Revisions table with the publish date and author.

VA Project Number: 528-22-129

VA Project Name: Sub Basement Excavation for Steam Repairs

A/E Firm: VAMC Buffalo Engineering

Recommended file name for the project specific revision is:

01 00 00 - General Requirements – 2022.05.17 - 528-22-129.docx

RECORD OF REVISIONS

Date Nature of Revision Author

01 Nov 2015 Baseline document from TIL CFM

11 May 2016 VAWNYHS site specific modification VAWNYHS

17 May 2022 Modified for Sub Basement Excavation for Steam Repairs

(528-22-129) TCH

i

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

Part 1 - General

1.1 Safety Requirements

1.2 General Intention

1.3 Statement of Bid Item(s)

1.4 Specifications and Drawings for Contractor

1.5 Construction Security Requirements

1.6 Operations and Storage Areas

1.7 Alterations

1.8 Disposal and Retention

1.9 Protection of Existing Vegetation, Structures, Equipment, Utilities, And Improvements: NOT USED

1.10 Restoration

1.11 Physical Data

1.12 Professional Surveying Services: NOT USED

1.13 Layout of Work: NOT USED

1.14 As-Built Drawings

1.15 Use of Roadways

1.16 COR’s Field Office

1.17 Temporary Use of Mechanical and Electrical Equipment

1.18 Temporary Use of Existing Elevators:

1.19 Temporary Use of New Elevators: NOT USED

1.20 Temporary Toilets

1.21 Availability and Use of Utility Services

1.22 New Telephone Equipment: NOT USED

1.23 Tests / Commissioning

1.24 Instructions

1.25 Government-Furnished Property

ii

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

1.26 Relocated Equipment and Items

1.27 Storage Space for Department of Veterans Affairs Equipment

1.28 Construction Sign – Exterior: NOT USED

1.29 Construction Area Entrance Safety Signs

1.30 Safety Sign: Not Used

1.31 Photographic Documentation

1.32 Final Elevation Digital Images: NOT USED

1.33 Historic Preservation: NOT USED

1.34 VA Tririga CPMS: NOT USED

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Site Preparation: Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Project 528-22-

129, Sub Basement Excavation for Steam Repairs at the VA Western New

York Healthcare System as required by drawings and specifications.

B. Site Visits: Visits to the site by Bidders are highly recommended and may be made only by appointment with the Project Manager/Contracting

Officer’s Representative (COR). Contact information for the COR is contained within the Scope of Work of the solicitation. All bids will take into consideration of existing site conditions; it is the responsibility of the contractor to review the entire job site footprint and existing site conditions prior to bid submission. All proposals shall include a detailed cost breakdown (materials, labor, and equipment) by trade, specification division and section; lump sum costs are not acceptable.

C. Architect Engineer: Offices of VAMC Buffalo Engineering, as Architect

Engineers, will render certain technical services during construction.

Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory or other parties retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 notice shall be not less than seven calendar days unless otherwise designated by the Contracting Officer.

E. Security: All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the

VA police, be identified by project and employer, and restricted from unauthorized access. See Article 1.5Construction Security

Requirements.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, walks, grading, drainage, necessary removal of existing structures and construction and certain other items as described in the project narrative, drawing set, and specifications.

B. ITEM II, Electrical Work: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including lighting, telecommunications, and equipment power as described in the project narrative, drawing set, and specifications.

C. ITEM III, Mechanical Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including refrigeration equipment installation, refrigerant piping, and plumbing as described in the project narrative, drawing set, and specifications.

D. ITEM IV, Plumbing Work: Work includes all labor, material, equipment and supervision to perform the required plumbing construction work on this project including replacement of all waste, vent, steam supply, and condensate return lines exposed during the demolition of the walk-in coolers and freezers as described in the project narrative, drawing set, and specifications.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

3. Employee Listing

a. The General Contractor shall furnish to the COR and Contracting

Officer lists of employees that will be or may be on the construction site(s). The list shall:

Be on Company letter head that provides all of the company contact information, Provide the project number and title, Identify work locations, List names of the employees, their titles, their job types, and personal contact numbers (i.e. cell phone).

b. All sub-contractors, vendors and suppliers for the project shall furnish the same listing on their individual company letter heads to the GC whom will provide the lists to the COR and Contracting

Officer.

c. These lists shall be updated as necessary during the entire duration of the project.

d. These lists shall be used by the COR to complete the key control and badge control records.

e. These lists may be used by the contractor as a check list record of personnel on-site each day to be provided with the contractor’s Daily Log reports.

f. These lists may be used by the contractor as a check list record of personnel on-site each day to be provided to the COR Field

Office where normal daily sign in and sign out occurs.

B. Security Procedures

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

1. General Contractor’s employees shall not enter the project site without appropriate badge (See paragraph D: Badge Control). They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. The required General Contractor

Employee List (paragraph A.3) must be received by this time. Lists of sub-contractor employees are not required at this time but must be provided prior to them arriving at the work site. This notice is separate from any notices required for utility shutdown described later in this section.

3. For working outside the “regular hours” as defined in the contract, The General Contractor shall provide a request for approval 14 calendar days prior to the requested date, to the Contracting

Officer and COR, so that security, escort and other appropriate arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown or access closure described later in this section

4. No photography of VA premises is allowed without written permission of the Contracting Officer.

5. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards

1. The General Contractor shall not be required to provide unarmed guards at the project site 24 hours a days, 7 days a week or after construction hours.

2. Any guard provided shall have communication devices to report events as directed by VA Police.

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

3. The General Contractor is not required to install equipment for recording guard rounds to ensure systematic checking of the premises.

4. The General Contractor may need to provide a guard as required by the contract drawings and specifications, including specification sections for Asbestos Abatement.

D. Badge Control

1. General: Identification badges (Photo and Orange Temporary) will identify contractor and sub-contractor employees as personnel authorized to be conducting work on the Medical Center campus.

Assigned/issued badges shall be worn by contractor employees prominently above the waist while on the Medical Center campus. All badges are property of the Federal Government. Any badge assigned to the contractor, which is lost or stolen will result in a replacement cost of $100.00 per badge. Any badge either lost or stolen shall be reported to the COR; it is the contractor’s responsibility to inform VA Police and give a detailed report about the badge loss. The contractor shall take a copy of the official police report and make payment to the Agent Cashier before any additional replacement badges are made. A copy of the Police Report and receipt of payment shall be provided to the VA COR.

2. Orange Temporary Badges: Contractor may be issued identification badges for their employees and sub-contractor employees through the

COR. Badges are individually numbered and will be assigned to individual employees by name. All badges must be turned in at the end of Contract. Final payment may be withheld and/or reduced until all badges are returned or accounted for.

3. Photo Identification Badges: Contractor may be issued identification badges for their employees and sub-contractor employees by the VA

Police after required safety training has been completed (See

Section 01 35 26 – SAFETY REQUIREMENTS). Badges will be assigned to individual employees and include their photo and their full name.

Photo ID badges will be valid for three years from issuance.

E. Key Control

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officer and the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

3. Contractor may be issued keys and/or keycard for construction through the COR and Contracting Officer. All keys and/or keycard must be turned in at the end of Contract. Any key and/or keycard assigned to the contractor, which is lost or stolen will result in a replacement cost of $100.00 per key and/or keycard. Any key and/or keycard either lost or stolen shall be reported to the COR; it is the contractor’s responsibility to inform VA Police and give a detailed report about the key and/or keycard loss. The contractor shall take a copy of the official police report and make payment to the Agent Cashier before any additional replacement keys and/or keycards are made. Final payment may be withheld and/or reduced until all keys and/or keycards are returned or accounted for. A copy of the Police Report and receipt of payment shall be provided to the VA COR.

F. Document Control

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

G. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. Two permits shall be issued for General Contractor and its employees for parking in designated areas only.

3. Contractors will register their vehicle(s) with Facilities

Management Service. Contractors are prohibited from parking in patient/visitor and employee parking areas. Parking, if available, shall be in designated locations only. Violators will be ticketed.

1.6 OPERATIONS AND STORAGE AREAS

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR and

Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any

Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads (See Article 1.15Use of Roadways).

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

E. Construction workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR and Contracting Officer where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Phasing: The Medical Center must maintain its operation 24 hours a day

7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

1. To insure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, Contracting Officer, COR and Contractor.

2. The contractor is to submit his phasing schedule in writing to the

Contracting Officer for review and approval no later than twenty-one

(21) calendar days after issuance of the Notice to Proceed. This includes utility outages and access closures.

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

3. All work, such as corridor work, which is outside the main construction area, shall be done on evenings or weekends, so as not to disrupt the normal operations.

4. The contractor shall have all submittals completed and turned in to the Government for review by the A/E firm no later than thirty (30) calendar days from the date of the signed Notice to Proceed. The government will return submittals within twenty-one (21) calendar days from acceptance from the contractor. NO WORK SHALL BE STARTED

UNTIL ALL RELATED SUBMITTALS ARE APPROVED. All materials shall be approved by the Government prior to delivery to the job site and start of work.

5. All renovation activities will take place at a busy Medical Center.

The contractor shall not interfere with existing, on-going functions, or normal activity of the hospital. The contractor will provide walk-off mats for dust control, appropriate construction barriers, and keep noise & vibration to a minimum during normal business hours. Certain portions of the work will be confined to evenings, and/or weekends, as identified in the specifications and/or on the drawings.

6. No work shall start until the preconstruction survey and inspection is completed.

7. The Contractor shall provide a detailed asbestos abatement schedule, if required by the project scope.

8. Any utility service, parking lot, roadway, loading dock, and/or

Grounds interruptions requests shall be submitted in writing twenty-one (21) calendar days in advance of the planned utility interruption/access closure.

9. Set up phasing by buildings, wings, floors, or areas in accordance with information received from the Medical Center through the COR and the Contracting Officer.

Phase I:

Phase one will consist of the installation of five temporary 8’ x 20’ walk-in units. These units will be installed outside, along the Eastern

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 wall of the kitchen area, at grade. Preparation of the site for cooler placement will include the removal of an existing loading dock, greenhouse, and miscellaneous mechanical equipment. The yard area will be graded to allow for cooler placement and the existing sidewalk to the east of the kitchen will be expanded to allow for cart access between the kitchen and temporary coolers. Temporary power will be installed on the exterior wall of the building to supply the five units.

Phase II:

Phase two will consist of the installation of all outside equipment to be utilized by the renovated cooler and freezer units. This will include installation of equipment pads, the unitized refrigeration system, permanent power, and refrigeration runs to the exterior wall of the hospital. Phase two may be performed concurrently with phase one.

Phase III:

Once temporary refrigeration is established and the installation of the outside refrigeration unit is completed, the VA personnel will relocate food pantry (RM 71), offices (RM 72 and 73), transfer perishable goods from existing walk-in coolers and freezers to the temporary walk-in refrigeration units, and will remove equipment from RM 51-1.

Phase IV:

Once all construction area spaces have been vacated by the VA, demolition activates may begin on the existing coolers and freezers. Phase four will consist of construction of a temporary, sealed, 2-hour fire rated smoke barrier around the east and west sides of the cooler/freezer area, and demolition and abatement of the existing cooler/freezer area.

Temporary 2-hour fire rated construction barriers shall be installed outside the normal operating hours of the VA kitchen (overnight).

When the existing walk-in coolers and freezers are shutdown for demolition, the high humidity levels that will be generated during the warming process may attract pests. The contractor shall take the following measures to prevent pests within the construction area and kitchen:

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

Proactively retain the services of an insect exterminator to prevent pests

Prior to shutting down the existing walk-in coolers and freezers, disconnect and seal all floor drains within the construction area at the sub-basement level (Most of these floor drains are to be removed and/or relocated as part of this project as well)

Final connection of newly installed floor drains will be one of the final steps prior to construction completion

At the completion of this phase, the area shall be completely deconstructed and ready for installation for the new units.

Phase V:

Phase five will consist of the construction of the new walk-in modular structures along with mechanical, electrical, and plumbing fit out. To ensure proper function and reliable service of the plumbing and steam systems in the future all waste, vent, steam supply, and condensate return lines exposed during the demolition of the walk-in coolers and freezers shall be replaced during construction (A full listing is located in

Paragraph 1.3). At the completion of the construction activities, all equipment will be commissioned for use and VA personnel will be trained in proper operation.

Phase VI:

Phase six will consist of removal of temporary equipment and restoration of all affected interior areas to pre-construction condition. Temporary refrigeration units will be removed, along with portions of the access walkways and the temporary electrical connection point for the units.

Areas adjacent to the renovated walk-in units will be filled with crushed stone to match base grade elevation.

Temporary 2-hour fire rated construction barriers shall be removed outside the normal operating hours of the VA kitchen (overnight).

Phase VII:

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

Phase seven will consist of removal of the existing blast chillers and associated mechanical equipment and restoration of area to adjacent finishes.

H. Occupied Buildings: Building 1 will be occupied during performance of work; but immediate areas of alterations will be vacated.

I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by the COR and

Contracting Officer.

J. Deleted

K. Existing Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems

(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the

COR and Contracting Officer.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR and Contracting

Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center

Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL

INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC

SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 14 calendar days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical. On the next business day, the contractor’s Daily Log report shall explain the circumstances causing the emergency and the corrective actions taken.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

M. Roads, Parking Lots, Docks and Grounds: To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Deleted

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

3. Interruptions of these areas must be requested, in writing, at least

21 calendar days prior to the desired time and shall be performed as directed by the COR and Contracting Officer.

4. Interruptions will follow the same procedures as outlined in Article

1.6Operations and Storage Areas, Section K.2 Existing Utility

Services.

N. Deleted

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and Contracting Officer, of buildings, grounds, areas of buildings and grounds in which alterations occur and areas which are anticipated routes of access, and furnish a report, which lists the current conditions noted at that time. This report shall be approved by the VA prior to the start of any work. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout // affected areas of building(s) and grounds. //

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site(s).

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor, COR and Contracting

Officer.

B. Relocated Items: Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and Contracting Officer, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR

852.236-88).

C. Deleted

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

4. Once the contractor is notified by the VA of problems or damage to

VA property, the contractor shall take immediate corrective action to protect and restore said property. During normal duty hours, corrective action shall be initiated within two (2) hours. After normal duty hours, corrective action shall be initiated within four

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

(4) hours. The Daily Log for that day shall explain the problem(s) and corrective action(s) taken.

5. Dampen debris to keep down dust and provide temporary construction, dust-proof, asbestos containment, smoke rated, and/or fire rated barriers where specified, where indicated on the drawings, and as directed by the COR. Access doors in barriers shall be hinged and secured with locks. Walk-off mats shall be provided at all access doors.

6. Block off all ducts and diffusers to prevent circulation of dust into occupied areas during construction. Provide Negative Air

Machines as specified, to maintain negative pressure within the construction area(s).

7. The contractor shall not allow trash and debris to accumulate on the job site. As a minimum, trash and debris shall be removed once daily, with no flammable materials or trash left on the construction site overnight. All debris shall be removed from the job site in a closed container and disposed of in a proper manner.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags, noted on drawings, and/or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re installation and reuse. Store such items where directed by COR and Contracting Officer.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. During above ceiling work, the contractor will have to clear rooms, protect VA property and finishes, and move furnishings as necessary to protect the area an items from dust and debris, in the performance of the work above the ceiling.

5. Deleted

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS: NOT USED

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR and Contracting Officer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the

COR and Contracting Officer before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below, in the contract specification sections, on the contract drawings, and/or in other VA furnished documentation is for the Contractor's information. The

Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. The contractor shall be responsible for conducting a thorough site investigation, before bidding, to satisfy themselves as to actual conditions.

1.12 PROFESSIONAL SURVEYING SERVICES: NOT USED

1.13 LAYOUT OF WORK: NOT USED

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Upon completion of the project and before final settlement, Contractor shall deliver two (2) approved completed detailed sets of as-built drawings to the COR and Contracting Officer within fifteen calendar days after project acceptance. These drawings shall show sizes, materials, connections to existing structures, utilities, building

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 service equipment, circuits, electrical conduit and junction box locations and routes, and other required information.

E. Paragraphs A, B, C, & D shall also apply to all shop drawings and installation drawings provided by equipment suppliers and vendors.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads and parking lots on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.16 COR’S FIELD OFFICE

A. The COR’s field office is physically located on site at the Medical

Center. The physical address of the Facilities Management Services

(FMS), Project Section (138P) is:

1. Buffalo VAMC: 3495 Bailey Avenue, Buffalo, NY 14215

2. Batavia VAMC: 222 Richmond Ave, Batavia, NY 14020

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze up damage. ALL controls for the equipment shall be functioning properly to prevent damage to the equipment.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.18 TEMPORARY USE OF EXISTING ELEVATORS

A. The use of patient or employee elevators is prohibited, except as noted below in 1.18.C.

B. For workers there should be very limited use of stair #3 located adjacent to the work area, as this exits directly to the main entrance.

The preferred entry point shall be the stairwell in building 6 and limited use of the stairwell adjacent to the loading dock.

C. All waste materials shall be taken from the basement using the bulkhead barndoors in Wing-A. New finish materials too large to be carried down a stairwell (ex. doors, lights, ect.) can be brought through the loading dock to the employee elevators.

1.19 TEMPORARY USE OF NEW ELEVATORS: NOT USED

1.20 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

B. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022 chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. Temporary Utilities: The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the

Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges.

Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Meters: Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Deleted.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

General Requirements VAWNYHS: 11 May 2016 528-22-129: 17 May 2022

G. Steam: Furnish steam system for testing required in various sections of specifications.

1. Obtain steam for testing by connecting to the Medical Center steam distribution system. Steam is available at no cost to the

Contractor. The Contractor may connect to existing systems at their own expense.

2. Maintain connections, pipe, fittings and fixtures and conserve steam use so none is wasted. Failure to stop leakage or other waste will be cause for revocation (at the COR and Contracting Officer discretion), of use of steam from the Medical Center's system.

H. Fuel: Natural and LP gas and burner fuel oil required…