523A4-13-210 AE Security Single Source Justification MPT to SAT signed.pdf

PDF 272 KB Posted

Attached to
C1DA--523A4-13-210 Site Security WX - Type C Services Sole Source Federal contract opportunity
Solicitation number
36C24123R0015
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1

View the file

Other files for this federal contract opportunity

Other files attached to C1DA--523A4-13-210 Site Security WX - Type C Services Sole Source, newest first.
File Type Posted
36C24123R0015.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHAPG Part 813.106 Simplified Acquisition Procedures: Soliciting from a Single Source Attachment 1: Single Source Justification for SAP under the SAT

Last Updated: 02/01/22 Page 1 of 2

DEPARTMENT OF VETERANS AFFAIRS

Justification for Single Source Awards IAW FAR 13.106‐1 For

Over Micro‐Purchase Threshold but Not Exceeding the SAT ($250K)

Acquisition Plan Action ID: 36C241‐22‐AP‐3581

1. Contracting Activity: Department of Veterans Affairs, VISN 01, Boston VAMC West Roxbury, MA

2. Brief Description of Supplies/ Services required and the intended use/Estimated Amount:

The Boston West Roxbury VA Medical Center Facilities Projects team is initiating the construction of the Site Security project. This sole source justification is to contract to Woodard & Curran who serves as the Architect/Engineer (A/E) Designer of Record to provide Construction Period Services (CPS) for the project. These services were previously awarded to the A/E Designer of Record but were descoped due to availability of funding for construction. The proposed action is to provide follow on CPS during the construction phase of the project.

Construction Period Services are to include, but are not limited to, review and approval of construction submittals, samples, shop drawings, schedules, phasing plans; response to Request for Information (RFI); change order review and recommendations; preparation of cost estimates to Request for Proposal (RFP); cost/time/impact estimates and recommendations relevant to apparent construction plan deviations; site visits as required and/or requested by the VA Contracting Officer and Project Engineer for inspection of ongoing construction including final tests and inspections; documentation of all necessary site visits to the VA Contracting Officer and Project Engineer within one (1) week after the visit; verification and preparation of as‐built drawings from contractor supplied marked up prints which the VA will retain permanently. The design firm shall provide all labor, supervision, materials, and equipment to provide type C services for NRM Project 523A4‐13‐210 Site Security at the West Roxbury VA Medical Center.

The total estimated value of the proposed action is $197,754.00

3. Unique characteristics that limit availability to only one source, with the reason no other supplies or services can be used:

Woodard & Curran is the A/E Designer of Record and were previously awarded the design and

CPS for this project but was descoped due to availability of funding at the time. The AE IDIQ it was previously awarded on is now expired. Awarding this project to another A/E firm would add significant risk to the facility due to a loss of technical familiarity with the project. Specifically, the technical review for familiarity of and changes to conditions, hazardous materials, Industrial Hygiene, and the Commissioning review.

The proposed sole source contractor has worked very closely with the technical and functional resources in the West Roxbury VA and gained significant knowledge of the requirements to facilitate the previously completed design. The exposure to the VA and design work will be crucial as the Site Security project is completed. Woodard & Curran has intimate knowledge of the design due to their execution of the design under a previous contract. If another vendor is selected, additional risk

VHAPG Part 813.106 Simplified Acquisition Procedures: Soliciting from a Single Source Attachment 1: Single Source Justification for SAP under the SAT

Last Updated: 02/01/22 Page 2 of 2 would be incurred as the new contractor’s staff may not fully understand the intent and context of the complex requirements included in this design. Furthermore, another source would require a steep learning curve while gaining familiarity with the design itself.

Additionally, the A/E designer of record needs to be retained for CPS for warranty and liability issues. CPS is a continuation of the design and procuring a different A/E for these services will relieve Woodard & Curran of their responsibilities and could forfeit VA’s total liability for faulty design and selection. Woodard & Curran is liable for making any corrections to the design if problems occur during construction.

4. Description of market research conducted and results or statement why it was not conducted:

The project’s design was produced by Woodard & Curran (A/E designer of record). CPS was provided within their initial project proposal which included Concept, Design, and CPS. Woodard & Curran are therefore best positioned to provide these services without additional delay and performance risk associated with engaging a different contractor.

5. Contracting Officer's Certification: Purchase is approved in accordance with FAR13.106‐1(b). I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.

Prepared by: Contract Specialist, Alexis Duda, Central Western VAMC MA

Stephen Slaby Contracting Officer

2022-10-31T13:11:31-0400
Stephen E. Slaby 3463391

File details come from the government source that posted it. Updated .