This is a Statement of Work (SOW) for the complete overhaul, rewind, mechanical repair, testing, and reconditioning of one Vane Axial Ventilation Fan (Part Number XA28A4W6, 25/7.5 HP, 1800/1200 RPM, 440VAC, 3-Phase) for the USCGC TAMPA. The contractor must provide all labor, materials, packaging, equipment, and transportation to pick up the disassembled unit from Electric Motor & Contracting (3728 Profit Way, Chesapeake, VA 23323), rebuild it, and deliver the completed assembly to US Coast Guard Base Portsmouth (4000 Coast Guard Blvd, Portsmouth, VA 23703) within twenty-eight calendar days of contract award. The incoming equipment has visibly blown stator windings, a .006" oversized fan impeller bore requiring repair or replacement, and heavily rusted internal fan housing, though structural components remain sound.
The SOW is structured across six phases: on-site packaging and transportation; cleaning and non-destructive examination including core loss testing and dimensional inspection; mandatory baseline refurbishment including AC stator rewind with Class H inverter-duty wire, dip and bake varnish cure, impeller bore remediation, bearing replacement with premium-grade double-sealed bearings, marine-grade 316 stainless steel hardware, terminal box reconditioning, dynamic balancing per MIL-STD-167-1 and ISO 1940 Grade G1.0/G2.5, and marine-grade epoxy housing preservation per SFLC Std Spec 6310; conditional over-and-above repairs (endbell sleeving, stator core lamination repair) authorized only via Condition Found Reports (CFRs) submitted within five calendar days of pickup; reassembly and sixty-minute dual-speed shop testing at 440 VAC 60 Hz with vibration analysis; and final packaging and delivery. Pricing is structured with Item 0001 as a firm-fixed-price baseline (on-site packaging, pickup, refurbishment, and testing), Item 0002 as mandatory AC stator rewind firm-fixed-price, Item 0003 as mandatory impeller bore remediation firm-fixed-price, Items 0004–0006 as optional/conditional firm-fixed-price or time-and-materials rates (endbell bore/sleeve machining, general machinist labor at 10 hours evaluation quantity, and mechanical technician labor at 10 hours evaluation quantity), and Item 0007 as a material handling markup percentage applied to an estimated $2,500.00 direct material cost plug. All deliverables, including preliminary as-received reports, CFRs with photographs and dimensional data, certified dynamic balancing reports, shop test reports, and certificates of conformance, must be submitted in Adobe PDF format. Quality standards require compliance with OEM specifications and USCG SFLC Standard Specifications 3042 and 6310. Base access requires all contractor personnel and drivers to possess valid state-issued REAL ID-compliant driver's licenses or approved federal identification credentials (TWIC or US Passport).
View the file
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Vane Axial Ventilation Fan Rebuild & Reconditioning for USCGC TAMPA
1.0 Objective & Scope of Work
The objective of this Statement of Work (SOW) is to define the requirements for the complete overhaul, rewind, mechanical repair, testing, and reconditioning of one (1) Vane Axial Ventilation Fan. The contractor shall provide all labor, materials, packaging, equipment, and transportation necessary to package, pick up, rebuild, test, and deliver the completed fan assembly back to the Coast Guard.
The unit is currently disassembled and unpackaged at Electric Motor & Contracting (EMC).
The contractor is responsible for providing all necessary packaging, crating, and protection on-site prior to transport.
2.0 References
2712_512_A
901-WMEC_512_009
SFLC Std Spec 6310 SFLC Std Spec 3042
3.0 Places of Performance & Transportation
Pick-up Location: Electric Motor & Contracting 3728 Profit Way Chesapeake, VA 23323 Drop-off Location: US Coast Guard Base, 4000 Coast Guard Blvd, Portsmouth, VA. 23703
ATTN: USCGC TAMPA
4.0 Equipment & Incoming Condition Details
Motor Details:
P/N: XA28A4W6
3P 440VAC 60Hz HP rating: 25/7.5 1800/1200 RPM 440VAC VANE axial drive Drive motor diameter 12” Fan housing 36”x50”
4.1 Incoming Condition
4.1.1. Packaging Status: Currently disassembled, unboxed, and unpackaged.
4.1.2. Electrical: Stator Windings: Visibly Blown. No other electrical tests were completed due to blown windings.
4.1.3. Mechanical:
The Fan impeller bore is out of tolerance; the fan bore is .006” oversized on the shaft. A replacement impeller must be furnished or the existing impeller bore repaired/sleeved back to OEM fit tolerances.
The vent fan housing is heavily rusted internally but structurally sound for reuse. The internal vanes have wear spots, but no visible holes or missing vanes are present.
All other mechanical checks SAT.
4.1.4. Independent Verification of Open & Inspect Findings:
The findings above represent an initial Open & Inspect baseline. Because testing was halted upon discovering the blown stator, the contractor shall not rely solely on this initial O&I report as an exhaustive assessment. The contractor is explicitly required to perform a comprehensive, independent inspection, measurement, and validation of all electrical, mechanical, and structural components upon receipt. The contractor is responsible for identifying and documenting any additional out-of-tolerance fits, latent defects, unrecorded wear, or missing hardware not captured during the initial O&I.
5.0 Technical Requirements & Sequence of Work
The contractor shall perform all work in accordance with the following logical phases and tasks:
5.1 Phase 1: On-site Packaging, Transportation, and Inventory
a. On-Site Packaging: The unit is currently disassembled and unpackaged from the prior O&I.
The contractor shall supply all necessary industrial packaging, protective wrapping, custom timber rotor cradles, and heavy-duty shipping containers/crates on-site at the pickup facility to properly protect the disassembled motor components, shaft journals, stator, impeller, and housing prior to transport.
b. Pick-up and Logistics: Safely rig, secure, and transport the complete vane axial ventilation fan assembly from address below to the contractor's repair facility. The contractor assumes full custodial responsibility and transit protection for the equipment.
Electric Motor & Contracting
3728 Profit Way Chesapeake, VA 23323
c. Inventory & Baseline Verification: Log all nameplate data, conduct an initial parts inventory verification against the disassembled components received, and record initial mechanical condition. The contractor shall physically verify the condition of all received items and immediately flag any discrepancy, missing hardware, or transit-related issues.
5.2 Phase II: Cleaning, Non-Destructive Examination, and Inspections
a. Winding Stripping & Data Logging: Strip the blown stator copper windings and record all original winding data.
b. Stator Core Loss Testing: Complete a core loss test once the windings are stripped to verify that the stator core laminations are not damaged. If core damage or excessive core loss is found, a Condition Found Report (CFR) shall be generated
c. Steam Cleaning and Drying: Degrease and steam-clean all disassembled metallic parts, duct housing, rotor, and stator core using non-destructive, non-corrosive industrial degreasers to remove carbon dust, oil, and contaminants. Bake dry the stator and metallic parts in a temperature-controlled industrial oven.
d. Mechanical & Dimensional Inspection: Measure and record total indicated runout (TIR) on the rotor shaft, inspect keyways and key seats for deformation or wallowing, measure bearing journal diameters and fits, conduct physical verification of the .006” oversized impeller bore and shaft mating surface, measure motor endbell bearing housing internal diameters with precision micrometers to verify roundness, concentricity, and fit tolerances. Compare all measurements against OEM allowable engineering tolerances.
e. Housing and Impeller Inspection: Inspect the fan duct casing and guide vanes for deformation, wall thinning, pitting, cracking, or weld failures that may not have been detected during the initial O&I. Clean and thoroughly assess the extent of internal casing rust, measuring localized pit depths and wall thickness. Perform a liquid penetrant examination (PT) at high-stress fan blade root fillets and hub bore mating surfaces to detect surface-breaking fatigue cracks or weld defects.
5.3 Phase III: Mandatory Baseline Refurbishment (FIRM-FIXED-PRICE)
The contractor shall perform the following baseline reconditioning tasks on the fan assembly regardless of inspection findings:
a. AC Stator Rewind and Dip & Bake:
1. Rewind the two-speed stator (25/7.5 HP, 1800/1200 RPM, 440VAC, 3-Phase) using as-found winding data with Class H inverter-duty magnet wire and high-grade insulation materials.
2. Dip and bake the windings (submerge in high-grade varnish and bake-cure in a controlled oven).
3. Clean and machine stator core and frame mating faces to remove excess varnish and ensure true alignment fits.
b. Mandatory Impeller Bore Remediation (.006" Oversized Bore): Based on the confirmed O&I finding of a .006” oversized bore on the shaft, the contractor shall machine, sleeve, and precision-bore the existing impeller hub back to true OEM shaft fit tolerances (or furnish an approved OEM-compliant replacement impeller). The finished bore fit and keyway shall comply strictly with drawing tolerances to ensure zero runout and proper interference fit on the motor shaft.
c. Rotor Reconditioning: Recondition and re-insulate the rotor assembly.
d. Bearing Replacement: Furnish and install brand-new, premium-grade double-sealed or shielded deep-grove ball bearings matching OEM manufacturer specifications and clearance ratings.
e. Fasteners and Seals: Furnish and install new marine-grade 316 stainless steel casing and motor assembly hardware, lock washers, silicone gaskets, and terminal box cable seals.
f. Terminal Box Reconditioning: Recondition terminal box, replacing cracked terminal blocks, grounding hardware, and lead lugs.
g. Dynamic Balancing: Dynamically balance the complete rotating assembly (motor rotor and vane axial fan impeller) in accordance with MIL-STD-167-1 and ISO 1940 Grade G1.0/G2.5.
Record dynamic balance weights and residual unbalance.
h. Housing Preparation & Preservation: In accordance with SFLC Std Spec 6310, prepare the interior and exterior surfaces of the ventilation housing (remediating the heavy internal rust noted during the O&I) and motor exterior to SSPC-SP 10 (Near-White Metal) and apply a high-durability marine-grade epoxy coating system. Mask and preserve machined mating flanges and fits.
5.4 Phase IV: Conditional/ Over-and-Above Repairs (As Authorized Via CFR)
The following repair items are conditional and shall only be performed if inspections in Section
5.2 demonstrate that parts are defective or outside OEM operational tolerances:
a. Endbell Machining (Bore and Sleeve): If micrometer measurements indicate bearing housing bores are out of round, grooved, or worn oversized beyond OEM fit tolerances, the contractor shall machine, bore, and install precision steel sleeves in the endbells, finish-machining them back to true OEM centerline and diameter tolerances.
b. Stator Core Lamination Repair: If core loss testing reveals damaged or shorted laminations exceeding acceptable limits, corrective repair shall be quoted via CFR.
c. Latent Defects & Corrective Repair Authorization: If the contractor's independent verification reveals any additional mechanical damage, shaft runout, blade cracks, or structural deficiencies not captured in the O&I baseline notes, or if any conditional repair is required, the contractor shall immediately submit a detailed Condition Found Report (CFR) with supporting measurements, color photographs, recommended corrective actions, and pricing in accordance with Section 6.2. No conditional or over-and-above repair work shall proceed without written authorization or formal contract modification from the Contracting Officer.
5.5 Phase V: Reassembly, Shop Testing, and Acceptance
a. Motor Assembly: Assemble the refurbished motor with new bearings, properly torque all internal fasteners, and verify mechanical tolerances prior to housing installation.
b. Initial Motor Electrical & Shop Run Testing: Perform preliminary cold resistance, winding balance, insulation resistance (Megger), and no-load shop testing on the assembled bare motor.
c. Fan Installation & Final Assembly: Re-install the motor and balanced fan impeller into the refurbished ventilation housing, verifying alignment, tip clearances, and free rotation.
d. Final Operational Run & Vibration Testing: Operate the complete vane axial fan assembly at full rated operating voltage (440 VAC, 60 Hz) across both High (1800 RPM) and Slow (1200 RPM) speeds for a minimum continuous duration of sixty (60) minutes. Record no-load running current draw, operating phase balance, operating bearing temperatures, and tri-axial vibration velocities (MIL-STD-167-1). Perform trim balancing if needed.
e. Final Preservation & Painting: Paint and preserve the completed unit in accordance with SFLC Std Spec 6310.
5.6 Phase VI: Packaging and Delivery
a. Apply protective rust inhibitor to all unpainted machined surfaces.
b. Affix a stainless steel or aluminum overhaul tag to the fan housing recording contractor name, contract number, date of overhaul, and dynamic balancing data.
c. Secure the fan assembly onto a heavy-duty wooden shipping skid and wrap in heavy-duty weatherproof plastic protection.
d. Transport and deliver the completed assembly to:
CG Base Portsmouth-CGC Tampa
4000 Coast Guard Blvd
Portsmouth, VA 23703
6.0 Deliverables & Documentation
All deliverables shall be submitted electronically in Adobe PDF format to the Contracting Officer and COR.
6.1 Preliminary Receiving & “As-Received” Report
Includes initial inventory verification, packaging receipt, recorded winding data from teardown, validation/reconciliation of initial O&I condition findings, and initial visual condition notes.
6.2 Condition Found Reports (CFRs)
The contractor shall submit a CFR within five (5) calendar days of equipment pick-up whenever conditional repairs (e.g., core lamination repair, endbell sleeving) or newly discovered latent defects/discrepancies from the initial O&I are identified. Each CFR must include:
a. Clear description of condition with color photographic evidence.
b. Dimensional inspection data comparing measured values to OEM tolerances.
c. Recommended corrective action.
d. Firm price proposal based on the contracted hourly rates and parts pricing established at award
e. Impact on final delivery schedule, if any.
6.3 Final Service Report & Closeout Dossier
Upon delivery of the fan, the contractor must submit a formal Service Report containing:
a. "As-Received" and final electrical and mechanical test sheets.
b. Stator Core Loss test results.
c. Impeller bore machining / sleeving dimension verification sheet confirming OEM fit tolerances.
d. Certified Dynamic Balancing Report.
e. Shop No-Load Run Test Report detailing voltage, running current draw, vibration levels, and temperature readings across both operating speeds.
f. Certificate of Conformance signed by the contractor's Quality Assurance representative confirming compliance with all drawing references and SFLC standards.
7.0 Pricing and Evaluation Structure
To ensure full and open competition while guaranteeing fair and reasonable pricing for any conditional repairs identified during inspection, offerors shall submit pricing for the following items:
Item 0001: On-Site Packaging, Pickup, Baseline Refurbishment, and Testing (Firm-Fixed-Price) Includes on-site packaging/crating at the pickup facility, round-trip transportation, cleaning/baking, complete electrical and dimensional inspections (including independent verification of prior O&I baseline findings), bearing replacement, rotor reconditioning, hardware renewal, junction box servicing, dynamic balancing, preservation/painting (SFLC Std Spec 6310) including internal housing rust remediation, 60-minute dual-speed run testing with vibration analysis, and Service Report.
Quantity: 1 Each
Unit: Each
Item 0002: Mandatory – AC Stator Rewind and Dip & Bake (Firm-Fixed-Price Unit Rate) Includes stripping blown windings, recording winding data, complete Class H rewind of the two-speed motor (25/7.5 HP, 1800/1200 RPM, 440V, 3-Phase) using as-found data, core loss testing, dip and bake varnish cure, and stator frame clean-up.
Item 0003: Mandatory Impeller Bore Remediation (.006" Oversize Fit) (Firm-Fixed-Price) Includes all labor, machining, precision sleeving, boring, and keyway fitting (or furnishing an OEM-compliant replacement impeller) to correct the confirmed .006” oversized bore back to true OEM shaft fit tolerances.
Item 0004: Optional / Conditional Repair – Motor Endbell Bore & Sleeve Machining (Firm- Fixed-Price Unit Rate)
Quantity: 2 Each (Government evaluation quantity; funded only if approved via CFR)
Unit: Each
Item 0005: Over-and-Above Labor – General Machinist (Time & Materials Rate) Fully burdened hourly labor rate for unexpected lathe, milling, or shaft repairs outside Items 0001–0004.
Quantity: 10 Hours (Government evaluation plug; funded only if approved via CFR)
Unit: Hour
Item 0006: Over-and-Above Labor – Mechanical Technician (Time & Materials Rate) Fully burdened hourly labor rate for unexpected mechanical casing or structural repairs outside Items 0001–0004.
Quantity: 10 Hours (Government evaluation plug; funded only if approved via CFR)
Unit: Hour
Item 0007: Replacement Parts and Specialty Materials Handling Markup Fixed contractor material handling and G&A markup percentage applied to direct vendor costs for unforeseen replacement components.
Quantity: Government estimated evaluation plug of $2,500.00 direct material cost.
Offeror specifies markup percentage (e.g., 10%).
Total Evaluated Material Cost = $2,500.00 + (Evaluated Markup % × $2,500.00).
Total Evaluated Price for Award Selection = Item 0001 + Item 0002 + Item 0003 + (Extended Total of all Item 0004-0007 quantities and rates).
8.0 Quality Assurance Standards
New parts, particularly bearings, seals, wire insulation, and varnishes, must meet or exceed original equipment manufacturer (OEM) specifications and USCG SFLC Standard Specifications 3042 and 6310.
9.0 Period of Performance
The contractor shall complete the entire scope of work, including pick-up, inspection, overhaul, authorized repairs, testing, and final delivery, within twenty-eight (28) calendar days of contract award.
The planned window for performance is: 01DEC2026 – 28DEC2026 (or as mutually adjusted by the Contracting Officer).
10.0 Points of Contacts
Point of Contact (POC):
LT David Rose, EO Teams: (571) 607-9605 David.M.Rose@uscg.mil
Contracting Officer Technical Representative (COR):
CWO Brandon Moe, SFLC MECPL Asset Manager Teams: 571-613-3488 Email: Brandon.A.Moe@USCG.mil
11.0 Security & Base Access Requirements
All contractor personnel and transport drivers entering Coast Guard Base Portsmouth must possess a valid state-issued REAL ID-compliant driver's license or an approved federal identification credential (e.g., TWIC or US Passport). It is the contractor's sole responsibility to ensure drivers and personnel meet base physical security requirements prior to scheduled pick-up and delivery.