SOW Joseph Tezanos Sewage and Gray Water Clean and Inspect.pdf

PDF 410 KB Posted

Attached to
52000QR260027597- CGC JOSEPH TEZANOS SEWAGE SYSTEM CLEAN
Solicitation number
52000QR260027597
Issued by

About this file

This is a Statement of Work (SOW) for cleaning and inspecting the sewage and gray water system of the USCGC JOSEPH TEZANOS, a U.S. Coast Guard vessel located in San Juan, Puerto Rico.

The contract requires the contractor to clean and inspect the sewage collection and gray water piping systems, tanks, and related components to remove buildups, calcifications, clogs, and waste that have degraded system operations. The work encompasses cleaning all interior surfaces of sewage and gray water piping, pumps, valves, tank vents, vacuum switch manifolds, fire main sprinkler pipes, and discharge equipment. The contractor must submit a cleaning plan prior to work commencement that details qualified personnel, chemical safety data sheets for all proposed cleaning agents, step-by-step procedures, and specific piping locations where openings will occur (minimum three separate locations for each system for before-and-after inspections). The SOW specifies that chemical cleaning using biodegradable descalers is recommended for sewage piping while mechanical cleaning (waterjetting) is suggested for gray water system piping. The contractor must provide temporary HVAC support if cleaning operations degrade continuous vessel climate control and must manage all waste disposal in compliance with federal, state, and local regulations. The Period of Performance is September 7–11, 2026, with working hours 0730–1600 at CGC EDGAR CULBERTSON in San Juan, PR. The contractor is responsible for ensuring all personnel possess valid REAL ID-compliant identification for base access. Post-cleaning operational testing includes vacuum pressure switch verification, level switch and pump operation verification, leak testing, and smoke testing of disturbed mechanical joints.

View the file

Other files

File Type Posted
FAR Matrix.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

Sewage and Gray Water System, Clean and Inspect for USCGC JOSPEH TEZANOS

1. Background and Current Observed Issues

CGC JOSEPH TEZANOS has suffered multiple casualties to their sewage collection and vacuum piping.

Build up and calcification on the inside of the vacuum and collection system causes constant clogs and has degraded the operation of this critical system.

Work Items:

1. Sewage and Grey Water System, Clean and Inspect

2. REFERENCES:

(a) SFLC TECHNICAL STANDARD 074-2

(b) Listed within each work item, as applicable.

3. REQUIREMENTS

See each work item for requirements.

4. PERIOD OF PERFORMANCE (POP)

September 7th, 2026- September 11th, 2026. Working hours shall be 0730-1600. Upon award finalized schedule shall be confirmed with the Cutter POC.

5. PLACE OF PERFORMANCE

The primary place of performance shall be at CGC EDGAR CULBERTSON located at below address:

CGC JOSEPH TEZANOS

Calle La Puntilla- Final Street San Juan, PR 00901

6. CUTTER POINT OF CONTACT

Adrian Lopez-Smith Cell: 831-207-8084 Email: Adrian.C.Lopez-Smith@uscg.mil

7. SECURITY REQUIREMENTS

All contractor personnel requiring access to the place of performance in order to perform work under this contract must possess a valid-state issued REAL ID-compliant driver’s license or identification card, or an acceptable alternative form of identification as defined by the Department of Homeland Security (DHS) [https://www.dhs.gov/real-id]. It is the contractor’s responsibility to ensure that all personnel are properly credentialed to gain base access. Failure to comply with access requirements may result in delays to performance and will not constitute an excusable delay.

Sewage and Grey Water System, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage and grey water system (e.g. tanks, piping, etc.).

1.2 Government-furnished property.

None.

TABLE 1

USE OF COAST GUARD SEWAGE AND GREY WATER DISPOSAL FACILITIES

(PARA 3.3.5.2)

NO

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 127-302, Rev C, Potable Water & Sewage Tank Fabrication Details

Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows

Coast Guard Drawing 154B WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows

Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram

Coast Guard Drawing 154 WPC 528-301, Rev B, Grey Water System Diagram

Coast Guard Drawing 154 WPC 593-201, Rev F, Sewage System Arrangement

Coast Guard Drawing 154 WPC 593-301, Rev C, Sewage System Diagram

Coast Guard Drawing 154B WPC 593-201, Rev A, Sewage System Arrangement

Coast Guard Drawing 154B WPC 593-301, Rev -, Sewage System Diagram

Coast Guard Drawing 154 WPC 593-303, Rev A, Sewage Control System

Coast Guard Drawing 154 WPC 601-302, Rev D, General Arrangement

Coast Guard Drawing 154B WPC 601-302, Rev -, General Arrangement

Coast Guard Drawing 154 WPC 633-301, Rev C, Cathodic Protection System

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

3. REQUIREMENTS

3.1 General.

3.1.2 Tech Rep.

None.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.1.5 Temporary HVAC. If the Contractor’s proposed cleaning plan will degrade continuous operation of the ship’s HVAC system then the Contractor must provide temporary ventilation to all impacted areas equivalent to the normal zonal ventilation rating for those spaces (i.e. maintain existing climate control) for the duration of work as described in SFLC Std Spec 0000.

3.1.6 Refer to all references beneath section 2 above, as applicable.

NOTE

Be aware that the grey water system has few isolation valves and many openings that must be plugged or blanked to contain cleaning media.

Be aware that AC condensate drains into the Grey Water Tank at 8 separate locations. Any temporary disruption or degradation of climate control must be fully addressed by the cleaning plan.

For these reasons, based on lessons learned, it is suggested that chemical cleaning be used on sewage piping and grey water system piping be cleaned mechanically (e.g. waterjetting, etc.)

3.1.7 Cleaning Plan. Prior to the start of cleaning work, the Contractor must submit a cleaning plan to the COR that contains the following:

A list of qualified personnel who will disassemble machinery or handle chemicals.

An SDS for every chemical proposed for use.

A step-by-step description of the procedures and methods that will be used to clean the systems

A list of locations in the sewage and grey water piping system where piping lines will be opened and components will be removed. At a minimum the piping must be opened at 3 separate sewage system clean-out locations and 3 separate grey water system clean-out locations for “before and after” inspections to determine the extent of cleaning required and to verify cleaning was adequately performed.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test and inspection - initial. Prior to commencement of cleaning work, the Contractor must witness Coast Guard personnel perform an operational pre-test of all items and shipboard devices to be disturbed, used, repaired, or altered, (e.g. TLIs, pumps, etc.) to demonstrate existing operational condition and to determine a more precise scope of cleaning required.

3.2.1 Tanks Open and Inspect the Grey Water Tank (3-17-0-W) and the Sewage Holding Tank (3-6-0-W).

Inspection must be completed in the presence of the COR or Coast Guard Inspector.

TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)

Grey water tank, (3-17-0-W) 2,668 gal.

Sewage collection tank, (3-6-0-W) 429 gal.

3.3 Cleaning and Inspection Requirements. After the COR approves the “Cleaning Plan” the Contractor must clean the piping and tanks and in accordance with the approved “Cleaning Plan”, and as described below. Clean, in their entirety, all sewage and grey water system interior surfaces (e.g. sewage and grey water ppg interiors, pump interiors, valve interiors, all sewage and grey water tank vent lines interiors, sewage vacuum switch manifold interiors, fire main sprinkler pipe interiors and spray hole interiors in main sewage tank used to flush sewage tank, overboard/to shore connection discharge pump and all related valve and pipe interiors, etc.) that may come in contact with sewage or grey-water, by removing all obstructions, clogs, uric scale, and waste build-up on piping and component interiors, ensuring subsequent free unobstructed flow of waste solids and fluids.

NOTE

Depending on the condition of the system, chemical cleaning may not adequately remove all obstructions, scale, and build-up present. More intrusive cleaning methods, such as pressure washing, flexible auger cleaning, or other mechanical means of cleaning, may be required to remove all obstructions, scale, etc. These more intrusive methods are in scope of this work item and the Contractor may be required to use one or more them, in the appropriate quantities, to achieve minimum cleaning requirements.

NOTE

Before filling a system with descaler ensure all openings below the fill point are blanked off or plugged.

3.3.1 Chemical Cleaning of Piping. When chemically cleaning piping and component interiors use a commercially available biodegradable sewage/grey-water system descaler (e.g. SEW CLEAN, etc.) safe for use on stainless steel. Fill the systems with descaler and hold for a long enough period to clean the systems as described above. After cleaning is complete drain and dispose of all sewage and grey water system contents.

3.3.2 Tank Cleaning. Interior surfaces of the Grey Water Tank 3-13-0-W, the Sewage Holding Tank 2-4- 0-W, sewage vacuum accumulation tank must be cleaned until free of all foreign materials, sediment, and sludge. Remove all persistent residues, residual wash media, and moisture with clean lint-free cloths.

Remove, clean, and re-install all tank interior components (e.g. TLIs, limit switches, eductors, etc.).

Reuse the existing zinc anodes in the tanks, unless degraded more than 50% then renew. Remove and dispose of all sewage system contents and collect, contain, and dispose of all wash media and cleaning materials in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item.

3.3.4 Inspections. After cleaning, inspect the piping interior at the locations specified in the “Cleaning Plan” using a borescope in the presence of the COR or Coast Guard Inspector, verify that all solid deposits, visible to the unmagnified eye, have been removed. Visually inspect all system components

(e.g. TLIs, limit switches, pressure switches, tank interior surfaces, fasteners, gasket seating surfaces, manhole cover surfaces, etc.) for excessive wear, damage, and all other notable discrepancies.

3.3.5 Miscellaneous. Do not drain any fluids (e.g. sewage, grey water, fresh water, etc.) into any space, bilge, or exterior location. Take all precautions required to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations. Renew all disturbed soft components (e.g. seals, gaskets, o-rings, etc.). Do not use the sewage pump installed in the system to offload sewage system contents.

3.3.5.1 Plug log. Plug all unattended openings in the system. Plugs must be fitted with a lanyard, ring or other device to prevent loss of the plug inside the system. Create and maintain a written log of each plug that specifies the location of each. Remove and dispose of all plugs upon completion of work. If requested, furnish the plug log to the Coast Guard Inspector during the performance of close-out inspections.

3.3.5.2 Use of Coast Guard Sewage and Grey Water Disposal Facilities. If “YES” is denoted in Table 1 – (Use of Coast Guard Sewage and Grey Water Disposal Facilities), beneath paragraph 1.1 (Intent), the Contractor may offload and dispose sewage and grey water system contents into the Coast Guard pier facility tanks in lieu of a Contractor furnished tank truck, otherwise the Contractor must dispose of all waste using the Contractor’s disposal facilities.

3.4 Closing tanks. The Contractor must notify the COR at least 24 hours prior to closing the tank. After completion of all authorized repairs and after the COR inspects all work performed, close the tanks.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test – post repairs. After completion of work, the Contractor must thoroughly test all disturbed components and systems and accomplish the following tasks in conjunction with each other as appropriate, in the presence of the Coast Guard Inspector:

3.5.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.

3.5.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory or original operating condition.

3.5.3 Leak test. After all system components are reinstalled, the Contractor must test all disturbed piping for leaks, as follows:

Run water down all disturbed grey water system piping runs for 5 minutes.

Ensure the system holds vacuum without cycling for at least 20 mins.

Place both vacuumarator selection switches in the "RUN" position. Allow vacuumarator pump to run until system operating pressure of -0.40 to -0.55 bar is reached. Observe vacuum tank pressure gauge. Place both vacuumarator selection switches in the "OFF" position. (NOTE: A vacuum loss of more than 0.14 bar indicates an air leak exists in the system.) Verify vacuum system pressure remains between -0.40 to -0.55 bar for 20 minutes.

Record pressure value and include in the final report.

Perform smoke leak test on vacuum portions of the sewage system where the Contractor has disturbed a mechanical joint.

Closely monitor the systems for leaks. Repair all leaks detected. Repeat test and inspection tasks until no leaks are detected.

3.5.4 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tanks to the limit of the ship’s installed pumps.

4. NOTES

This section is not applicable to this work item.