5-Phase 2 Scope of Work.pdf
PDF 258 KB Posted
- Attached to
- Tyrone Township Municipal Building - Phase 2
- Solicitation number
- US.261453
- Issued by
- Philadelphia County, Pennsylvania
About this file
This is a Scope of Work document for Tyrone Township, Pennsylvania, detailing Phase 2 of the Municipal Building project located at 3129 Shermans Valley Road, Loysville, PA 17047. The project encompasses construction of a community hall addition attached to the main building completed in Phase 1, along with paving of a gravel parking lot and related appurtenances. Sealed proposals are due by 5:00 p.m. on November 18, 2026, via the PennBid Program, with bid opening scheduled for the same date at the Loysville Community Center during a Tyrone Township Supervisors meeting. No optional pre-bid meeting is being held. The contractor is responsible for all construction debris removal and disposal and must ensure compliance with all applicable building and zoning regulations, industry standards, and building codes throughout project execution.
The scope of work includes carpentry and mechanical, electrical, and plumbing (MEP) work encompassing framing, exterior sheathing, electrical and plumbing installations per code, roof truss procurement with engineered specifications, roofing and siding installation with pre-approval samples, interior finishes including doors, windows, hardware, cabinetry, flooring, paint, and lighting fixtures, handicap signage installation per 2009 ANSI standards, and HVAC unit placement coordination. Parking lot work requires removal of bumper blocks and gravel, installation of 4 inches of HMA Base Course and 1.5 inches of HMA Wearing Course with tack coat application, and line painting per PennDOT specifications followed by bumper block reinstallation. The successful bidder must post performance, labor and material, and maintenance bonds each at 100 percent, 100 percent, and 10 percent of the bid price, respectively. Pennsylvania's Prevailing Wage Act applies to all contractors and subcontractors, requiring workers to be paid prevailing minimum wages as established by the Department of Labor and Industry.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TYRONE TOWNSHIP MUNICIPAL BUILDING PHASE 2
The scope of work is related to the construction of a community hall addition, the paving of a gravel parking lot, and related appurtenances at 3129 Shermans Valley Road, Loysville.
The contractor shall inspect all on-site conditions and become knowledgeable with the aspects of the project. Some aspects of the project may not be represented on the drawings due to onsite conditions that will require field adjustments as the project is performed.
ALL WORK SHALL BE COMPLETED IN A PROFESSIONAL WORKMANSHIP MANNER AND
STANDARDS ACCEPTABLE TO THE INDUSTRY AND ALL APPLICABLE BUILDING AND
ZONING REGULATIONS.
General Scope of work:
This project consists of the construction of a new community hall addition which is to be attached to the main building that is being constructed in Phase 1. Utilities shall be connected through the Phase 1 portion of the building. This phase also includes the paving of the parking lot.
The contractor shall be responsible for removal and disposal of all construction debris.
Section 2: Carpentry & MEP
a. Construct all framing per plan.
b. Install exterior sheathing per plan.
c. Install all electric per code (see owner prior to construction for any specific items not shown on plan and included in bid (this is not an extra).
d. Install all plumbing per code (see owner prior to construction for any specific items not shown on plan and included in bid (this is not an extra).
e. Order roof trusses and provide engineered specifications to township and inspectors.
f. Roofing and siding material, (Contractor shall provide sample to Township prior to ordering roofing and siding for approval).
g. Provide cut sheets for any and all interior doors, windows, stone, exterior doors, hardware, and lighting and light fixtures for approval.
h. Provide cut sheets for water closets and sinks in restrooms.
i. Provide samples of all cabinetries, flooring, paint colors, ceiling tiles, carpet, floor tile and wall trim.
j. Contractor shall review plans and determine with the owner the exact locations of heating and cooling units.
k. Contractor shall provide all handicap signage, installed in accordance with the 2009
ANSI.
Section 1: Parking Lot Paving
a. Remove bumper blocks from gravel area and stockpile on site.
b. Remove gravel that was placed during Phase 1 to ensure 6” of subbase.
c. Contractor to pave the parking lot in two layers:
a. 4” HMA Base Course, PG 64-22, 0 - 0.3 million ESALS, 25mm mix, SRL-M
b. 1.5” HMA Wearing Course, PG 64-22, 0 – 0.3 million ESALS, 9.5mm mix, SRL-M
d. A tack coat shall be used between the base course and wearing course if the wearing course is not applied within eight (8) hours of the base course being constructed.
e. Contractor shall paint lines using approved paint from PennDOT Bulletin 15, Publication 35. Lines shall be four (4) inches wide.
f. After paving and striping, the contractor shall reinstall the bumper blocks to the parking spaces.
Note: The contractor shall become familiar with the project and any items not shown on the plan shall be the contractor’s responsibility to accommodate and provide for compliance with any and all applicable building codes, locations of EXIT SIGNAGE, SMOKE DETECTORS AND FIXTURES. The contractor shall take steps to be in compliance with the building codes and requirements of BIU, any cost associated with items that are required by the building code and/or building official/inspector shall be the responsibility of the contractor.
The project shall not provide for additional work orders/change orders unless directed and approved by the Township or the Townships Appointed representative.
*Disclaimer: Failure to include any item from this scope of work does not relieve the contractor of the obligations to complete the items specified in any of the other contract documents.