This document is a project specification sheet for the Easton ADA Sidewalk Ramp Project (2026-DSR) in Easton, Pennsylvania. The City of Easton is soliciting bids for the construction and installation of multiple Americans with Disabilities Act (ADA)-compliant sidewalk ramps throughout the Downtown historic district. The scope of work includes demolition of existing sidewalk corners and adjacent sections, removal and replacement of signage as needed, installation of new ADA-compliant corner ramps, inlet protection where required, and minor piano key pavement markings in pedestrian crosswalks. The project designates ramps south of Northampton Street as base bid items, with ramps north of Northampton Street classified as alternate bid items. The document references detailed plans and specifications contained in associated plan sheets (Title, Index, Details, and multiple ADA Plans).
Cold weather construction requirements are specified in the document, requiring contractors to implement protective measures when temperatures reach 40°F within any 24-hour period. These measures include the use of insulated blankets and hot water during concrete pouring, finishing, and curing operations, with forms remaining in place for a minimum of three days to ensure proper concrete strength development. The City of Easton retains the right to refuse any bids submitted for the project. Specific pricing terms, set-asides, response deadlines, and award information are not detailed in this specification excerpt.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4-Bid Package - Full.pdf | ||
| 2-Contract Forms.pdf | ||
| 6-Addendum No. 1.pdf | ||
| 3-Prevailing Wages.pdf | ||
| 1-Traffic Notification List 2023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOUTH
ALL RAMPS SOUTH OF NORTHAMPTON STREET (BELOW RED
LINE) ARE THE BASE BID ITEMS. RAMPS NORTH OF
NORTHAMPTON STREET ARE ALTERNATE BID ITEMS
WEATHER NOTES:
CONTRACTOR SHALL TAKE PROPER MEASURES WHEN
TEMPERATURES REACH 40F IN ANY 24-HOUR PERIOD. INSULATED
BLANKETS AND HOT WATER SHALL BE UTILIZED WHILE POURING,
FINISHING, AND CURING. FORMS SHALL BE KEPT IN PLACE FOR 3
DAYS TO ENSURE PROPER STRENGTH
1.
S
| 01-209302_Easton ADA Ramps_Title |
| 02-209302_Easton ADA Ramps_Index |
| 03-209302_Easton ADA Ramp_Details |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
| 209302_Easton ADA Ramps_ADA Plans |
File details come from the government source that posted it. Updated .