5-6730 Addendum 001 Write Up.pdf

PDF 97 KB Posted

Attached to
RFP - Welding Lab
Solicitation number
RFP VBI 260000002075 2
Issued by
Van Buren County, Michigan

About this file

This is an Addendum 001 document issued by the Van Buren Intermediate School District for Project 5-6730, the VBISD CTE Improvements, dated May 28, 2026. The addendum modifies the bidding documents and specifications for an architect-engineer project managed by GMB (616.796.0200) with construction management by GDK Construction (616.355.0300). The addendum introduces three new specifications covering pipe and tube railing (05 52 13), door hardware schedule (08 06 71), and door hardware requirements (08 71 00), and reissues eleven existing specification sections and drawing sheets to incorporate project clarifications and revisions. Key changes include the addition of protective railings to the mezzanine edge, paint stain system specifications for benches in rooms A105, A108, and A109, expanded door and frame schedules with hardware set numbers, compressed air routing to a dust collector, revised HVAC supply and exhaust grille details with an updated dust collector size, additional hydronic system components including finned tube elements and sensor locations, mechanical control diagram revisions, updated equipment schedules, and electrical plan modifications including additional fire alarm pull stations and circuit clarifications. Bidders are required to acknowledge receipt of this addendum on the proposal form.

No pricing information, set-asides, incumbent contractors, funding sources, or contract term details are provided in this addendum document.

View the file

Other files

File Type Posted
Bid Ad.pdf PDF
01. Invitation to Bid .pdf PDF
1 Cover Sheet.pdf PDF
03 Work Category Descriptions (1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM

VAN BUREN INTERMEDIATE SCHOOL DISTRICT ADDENDUM 001

5-6730 VBISD CTE IMPROVEMENTS MAY 28, 2026

A/E PROJECT 5-6730 PAGE 1 OF3

SECTION 00 91 11.01 - ADDENDUM 001

OWNER VAN BUREN INTERMEDIATE SCHOOL DISTRICT

PROJECT 5-6730 VBISD CTE IMPROVEMENTS

A/E PROJECT 5-6730

PURPOSE THIS ADDENDUM SHALL FORM PART OF THE

BIDDING DOCUMENTS. CHANGES, ADDITIONS,

CLARIFICATION OR DELETIONS HEREIN

SUPERSEDE THE DRAWINGS AND

SPECIFICATIONS. BIDDERS SHALL INCLUDE

ON THE PROPOSAL FORM

ACKNOWLEDGEMENT OF THE RECEIPT OF

THIS ADDENDUM.

ATTACHMENTS

NEW SPECIFICATIONS: 05 52 13, 08 06 71, 08 71

REISSUED SPECIFICATIONS: 00 01 10, 09 90 00,

11 53 00

REISSUED SHEETS: A2.1.1A, A2.2.1A,

A2.2A, A5.1.01, P3.1.1A, M2.2.1A, M2.3.1A, M3.1.01, M5.1.01, M6.1.01, E2.2.1A

ARCHITECT-ENGINEER GMB

616.796.0200

WWW.GMB.COM

CONSTRUCTION MANAGER GDK CONSTRUCTION

616.355.0300

CM WWW.GDKCONSTRUCTION.COM

5-6730 VBISD CTE IMPROVEMENTS MAY 28, 2026

A/E PROJECT 5-6730 PAGE 2 OF3

SPECIFICATION CLARIFICATIONS / REVISIONS

1.1 SECTION 00 01 10 TABLE OF CONTENTS (REISSUED)

A. Updated to reflect new specifications.

1.2 SECTION 05 52 13 PIPE AND TUBE RAILING (NEW)

A. Newly issued specification highlighting railing that is to be added to the mezzanine

1.3 SECTION 08 06 71 DOOR HARDWARE SCHEDULE (NEW)

A. Newly issued specification highlighting door hardware sets

1.4 SECTION 08 71 00 DOOR HARDWARE (NEW)

A. Newly issued specification covering overall door hardware requirements

1.5 SECTION 09 90 00 PAINTING AND COATING (REISSUED)

A. Re-issued specification to include paint stain system for bench

1.6 SECTION 11 53 00 LABORATORY EQUIPMENT (REISSUED)

A. Updated Section 1.1 for inclusion of owner furnished equipment B. Updated Section 1.2 for added abbreviation for owner furnished and contractor installed equipment C. Updated Section 2.1 to include shop equipment furnished by contractor and/or owner D. Added sections 2.6, 2.7, 2.8, 2.9, 2.10, 2.11, 2.12 for shop equipment

SHEET CLARIFICATIONS / REVISIONS

2.1 SHEET A2.1.1A - UNIT 'A' FIRST FLOOR DEMOLITION PLAN (REISSUED)

A. Added floor cutting keynotes throughout.

B. Added equipment to be removed and reinstalled.

C. Added locker demolition keynote in existing storage room.

D. Updated Demolition Notes for removal of key notes that were not used within the project.

E. Added P6 stain tag for benches in A105, A108 and A109.

2.2 SHEET A2.2.1A - UNIT 'A' FIRST FLOOR PLAN (REISSUED)

A. Added P6 stain tag for benches in A105, A108 and A109.

B. Added P6 stain to finish legend.

2.3 SHEET A2.2.2A - UNIT 'A' MEZZANINE PLAN (REISSUED)

A. Added protective railings to the edge of the mezzanine.

2.4 SHEET A5.1.01 - DOOR & FRAME SCHEDULE (REISSUED)

A. Added door A104A into the Door and Frame Schedule for Unit 'A'.

B. Added door hardware set numbers for all doors in Unit 'A' Door and Frame Schedule.

C. Updated Hollow Metal frame legend to match door frame numbering with Door and Frame

Schedule.

2.5 SHEET P3.1.1A - UNIT 'A' PLUMBING PLAN (REISSUED)

A. Added compressed air routing to dust collector.

B. Added notes for piping near air compressor and notes for railing to be coordinated with architecture.

5-6730 VBISD CTE IMPROVEMENTS MAY 28, 2026

A/E PROJECT 5-6730 PAGE 3 OF3

2.6 SHEET M2.2.1A - UNIT 'A' FIRST FLOOR HVAC PLAN (REISSUED)

A. Added details for supply and exhaust grilles.

B. Added additional keynotes and text notes for scope clarification.

C. Revised size of dust collector.

2.7 SHEET M2.3.1A - UNIT 'A' FIRST FLOOR HYDRONIC PLAN (REISSUED)

A. Added flows for finned tube elements. Added additional finned tube in A114 Storage.

B. Added additional sensor locations.

C. Added pumped coil callout.

2.8 SHEET M3.1.01 - MECHANICAL & CONTROL DIAGRAMS (REISSUED)

A. Removed note referencing backdraft dampers.

2.9 SHEET M5.1.01 - MECHANICAL SCHEDULES (REISSUED)

A. Revised equipment schedules to clarify equipment requirements.

2.10 SHEET M6.1.01 - MECHANICAL DETAILS (REISSUED)

A. Removed roof mounted exhaust fan detail.

B. Added high pressure round duct fitting detail.

2.11 SHEET E2.1.1A - UNIT 'A' FIRST FLOOR POWER & COMMUNICATIONS PLAN (REISSUED)

A. Added circuit number to homerun.

B. Added keynote clarifying clock requirements.

C. Removed duplicate ceiling data drop shown on incorrect level.

D. Added additional fire alarm pull station at door A101B.

END OF SECTION

File details come from the government source that posted it. Updated .