This is a Final Construction Report for the Net River Dam Channel Construction Project, jointly submitted to the Michigan Department of Natural Resources (MDNR) by GEI Consultants of Michigan, P.C. on January 18, 2023. The project involved constructing a temporary earth cofferdam, excavating a diversion channel through an existing dam embankment, and installing geotextile fabric, bedding stone, and riprap lining. Construction activities commenced October 3, 2022, with Terrazzo Creations and Renewal (TCR) mobilizing for concrete notch work and completed by November 15, 2022, with MD Contracting (MDC) executing the primary channel construction. The project required modification of the concrete intake structure by installing new stoplog slots and creating an 8-foot by 5-foot opening, while simultaneously constructing a temporary bypass channel to manage reservoir flows during spring runoff conditions. Critical construction activities included site preparation with erosion and sediment control measures, temporary cofferdam construction using heavy riprap and granular fill, channel excavation with protective lining systems, and cofferdam removal with subsequent site restoration and seeding.
The project encountered several minor deviations from original plans that were documented and approved through Request for Information (RFI) submittals. The stoplog slot protruded approximately 1 inch downstream of design specifications to maintain critical anchor clearances due to concrete wall thickness variations; 304 stainless steel was substituted for galvanized A36 steel for structural components; the channel alignment was shifted 15 feet west to prevent interference with the temporary bridge; and the channel outlet elevation was raised from 1528.5 feet to 1530.0 feet to avoid excavation within the river tailwater. Filter and bedding stone materials were approved as 3-inch minus material rather than specified MDOT 4AA, and compaction testing confirmed fill materials achieved 95 to 97.3 percent of maximum density standards. Quality control documentation included daily field reports, material testing results, construction photographs, contractor submittals, and as-constructed topographic surveys using GPS technology. The project was completed in substantial compliance with the design documents and applicable state regulations under the EGLE Joint Permit Application approval.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Net River Dam Channel Construction Project Final Construction Report Michigan Department of Natural Resources – MI Dam ID
Submitted to:
Mr. Bill Scullon Michigan Department of Natural Resources 520 West US Hwy 2 Norway, Michigan 49870
Submitted by:
GEI Consultants of Michigan, P.C.
109 W. Baraga Avenue Marquette, Michigan 49855
January 18, 2023 Project No. 2201765
Jacob Pieti, P.E.
Project Manager
Consulting
Engineers and
Scientists
Geoffrey L. Kruger, P.E.
E ngi neer of Record
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. i
Table of Contents
1. Introduction 1
1.1 Background 1
1.2 Project Description 1
1.3 Purpose 2
1.4 Project Team 2
1.4.1 Project Owner 3
1.4.2 Engineer of Record 3
1.4.3 Construction Contractor 3
1.4.4 Construction Observation and Documentation 3
1.4.5 Environmental Representative 4
1.5 Vertical and Horizontal Datum 4
2. Summary of Construction Activities 5
2.1 Overview 5
2.2 Construction Equipment 5
2.3 Concrete Intake Structure Notch 6
2.4 Site Preparation 6
2.5 Temporary Cofferdam Construction 7
2.6 Channel Construction 7
2.7 Cofferdam Removal 8
2.8 Restoration 8
2.9 Stoplog Installation 8
2.10 Demobilization 9
3. Summary of Deviations from Plans and Specifications 10
4. Quality Control 11
4.1 Construction Documentation 11
4.1.1 Daily Construction Reports 11
4.2 Materials Testing 11
5. Summary of Submittals and Construction Materials 12
6. General Qualifications and Certification 13
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. ii
Appendices A. Record Drawings B. Construction Photographs C. Contractor Technical Submittals D. Contractor RFIs E. Materials Testing Results F. Daily Field Reports G. Certification Letter
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 1
1. Introduction
1.1 Background
The Michigan Department of Natural Resources (MDNR) has completed the Net River Dam Channel Construction at the recreational Net River Dam Project near Covington, Michigan.
The construction activities consisted of the following major components:
• Mobilization
• Site Preparation
• Temporary Bridge Installation
• Concrete Intake Structure Notch Construction
• Site Clearing
• Cofferdam Construction
• Channel Excavation
• Cofferdam Removal
• Stoplog Installation
• Site Restoration
• Demobilization
The design improvements were provided in project plans and specifications prepared by GEI Consultants of Michigan, P.C. (GEI). The MDNR submitted the design report to the Michigan Department of Environment, Great Lakes, and Energy (EGLE) with the Joint Permit Application (JPA) dated October 14, 2022. The concrete notch drawings were issued for construction on September 12, 2022, with the stoplog slot drawing issued for construction on September 21, 2022. The channel drawings were issued for construction on October 14, 2022. The EGLE authorized construction with approval of the JPA dated September 29, 2022.
1.2 Project Description
The Net River Dam (MI Dam Inventory No. 131) is classified as a low hazard dam under Part 315 and located on the Net River in Baraga County, Michigan. The Net River Dam is owned and operated by the MDNR Wildlife Division. The dam provides environmental and recreational opportunities for the public by the creation of the reservoir impoundment, the Net River Flooding, and roadway access to the opposite side of the river. The dam was
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 2 originally constructed in 1953 but failed in 1985 when the embankment dam overtopped due to debris blockage of the intake structure. The dam was reconstructed in 1989 as part of a wetland mitigation project sponsored by the Tilden Magnetite Partnership.
The dam consists of a reinforced concrete intake structure transmitting flow via two six-foot diameter corrugated metal pipe (CMP) culverts through an earth embankment to a reinforced concrete outlet structure. The intake structure has a notch in the upstream face with steel stoplogs and is fully encased by steel trash racks. The embankment dam is approximately 435 feet long with a twenty-foot-wide (20) crest and 3:1 (horizontal to vertical) upstream and downstream slopes.
On April 28, 2022, a sinkhole on the embankment dam crest over the right (west) culvert was observed. The sinkhole revealed turbulent water above the crown of the barrel pipe. The water was gradually eroding the embankment crest causing progressive embankment loss through the barrel pipe. However, the embankment crest was not fully breached. The MDNR responded by working with local earthwork contractors to backfill the sinkhole.
The MDNR reached out to GEI on Monday, May 2, 2022, and GEI inspected the site on Thursday, May 5, 2022. Following the initial inspection, the MDNR worked to dewater the reservoir. GEI returned to the site on Wednesday, July 27, 2022, to conduct an internal dewatered inspection of the left (east) CMP culvert and intake structure. The July inspection identified severe corrosion and deterioration within the remaining open left culvert. The channel construction project was expedited as a result of the inspection findings as detailed in the field inspection report (detailing both inspections) dated August 11, 2022.
The primary goal of the Net River Dam Temporary Bypass Channel Project is to provide means of safely managing flows at the site, which are typically observed during spring runoff.
The bypass channel is intended to provide adequate means of safely managing site flows for one season pending future design of a permanent solution to mitigate dam safety issues at the site.
1.3 Purpose
The purpose of this final construction report is to summarize the equipment, materials, methods of installation and deviation from the plans and specifications during construction as required by the EGLE JPA. Record drawings that document the final construction details are included within Appendix A of this report.
1.4 Project Team
The primary parties engaged in the Net River Dam Channel Construction project are detailed in the following sections.
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 3
1.4.1 Project Owner
The Project site is owned by MDNR and operates the project as a recreational impoundment.
The following personnel contributed to the project:
• Michelle Crook – MDNR Senior Project Manager
• Bill Scullon – MDNR Project Manager
• John DePue – MDNR Wildlife Biologist
• Brad Johnson – MDNR Wildlife Biologist
1.4.2 Engineer of Record
The Engineer of Record is GEI Consultants of Michigan, P.C., and the following personnel contributed to the project:
• Jacob Pieti, P.E., – Project Manager
• Geffrey L. Kruger, P.E. – Engineer of Record (Channel Construction)
• Richard Price, P.E., – Engineer of Record (Concrete Intake Structure Notch)
1.4.3 Construction Contractor
The General Contractor for this project was MD Contracting (MDC) with assistance from construction surveying subcontractor TriMedia Environmental Engineering (TMEE). The concrete notch cutting was performed by Terrazzo Creations and Renewal (TCR). The following personnel contributed to the project:
• Dan Robillard – Project Manager (MDC)
• Mike Delene – Owner/Site Supervisor (MDC)
• Mike Begres – Owner/Foreman (TCR)
• Stacey Bluse – Project Manager (TMEE)
1.4.4 Construction Observation and Documentation
Construction observation, GEI performed documentation, material testing, and as-constructed survey. The following personnel executed the field work:
• Jacob Pieti, P.E. – Project Manager (GEI)
• Bruce Peterson, E.I.T. – Senior Field Engineer (GEI)
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 4
• Patrick Dowling, E.I.T. – Project Engineer (GEI)
• Jacob Burch, E.I.T – Project Engineer (GEI)
1.4.5 Environmental Representative
The following environmental representative for this project was:
• Mike Delene –Environmental Representative (MDC)
• Mike Begres –Environmental Representative (TCR)
1.5 Vertical and Horizontal Datum
Elevations listed herein are referenced to the North American Vertical Datum of 1988 (NAVD88). Horizontal spatial datum referenced to the North American Datum of 1983
(NAD83).
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 5
2. Summary of Construction Activities
2.1 Overview
The EGLE Dam Safety accepted the design documents and authorized the construction of the channel. The channel project was directly managed by MDNR staff with GEI providing construction oversight. The work was performed by MDC and TCR. TCR mobilized to the site on October 3, 2022 and completed the concrete notch construction on October 6, 2022.
MDC mobilized to commence the channel work on October 24, 2022 and was substantially complete by November 15, 2022.
The following subsections provide a general summary of the work conducted for this project.
Construction photographs of the control structure modification and channel construction projects are included in Appendix B. Additional supporting construction documentation is included within the following appendices.
• Appendix A – Record Drawings
• Appendix B – Construction Photographs
• Appendix C – Contractor Technical Submittals
• Appendix D – Contractor RFIs
• Appendix E – Material Testing Results
• Appendix F – Daily Field Reports
• Appendix G – Certification Letters
2.2 Construction Equipment
The work completed by MDC and TCR was conducted primarily with the equipment listed below. The construction equipment can be seen in many of the photographs included in Appendix B.
• 3 – Excavators – Caterpillar 349F, 336F, 323F
• 1 – Loader – Caterpillar 950 M
• 2 – Dozers – John Deere 700K, Caterpillar D6N
• 1 – Broderson Mobile Crane
• 3 – Off Road Dump Trucks – 1 – Volvo A25F and 2 – John Deere 250D
• Truck with Grapple Loader
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 6
2.3 Concrete Intake Structure Notch
TCR mobilized to the site on October 3, 2022, set up erosion control measures and a submersible pump to dewater the right inlet to the control structure. The pump was discharged into a filter bag, installed to the right of the concrete structure. The work area was contained with sandbag cofferdams in the invert of the concrete intake structure, lined with geotextile fabric. TCR cored 2 holes in the existing concrete wall to aid in saw cutting activities. The cores were retained and the location, size, and spacing of reinforcement steel was documented by GEI. The existing concrete was removed in 2 sections. The upper 3.5’ of concrete was sawcut and removed. A temporary wood bulkhead was constructed upstream of the structure and the remaining 1.5’ of the 5’ below the top of the structure was cut and removed, as depicted on the drawings. The location, size, and spacing of the existing reinforcement steel was documented by GEI. TCR installed the steel channel stop log slots by drilling and epoxying anchors into the concrete with Hilti Hit 200 HY. The interface of the concrete and steel stoplog channel were sealed using Aquabond Aquaflex AFW 8000-400 underwater sealant.
The steel channel stoplog slots were adjusted approximately 1” downstream from the design drawing due to the existing wall concrete variation in thickness to maintain a clear distance a minimum of 3 ½” between the anchors and the upstream face of the concrete. The temporary wood bulkhead was removed, and the notch utilized. The concrete intake structure managed all reservoir flows during construction of the channel through both the pre-existing notch and new notch until the channel was commissioned.
2.4 Site Preparation
Prior to mobilizing to the site, MDC obtained the Baraga County SESC Permit and the MDNR obtained the EGLE JPA. The MDNR permitted use of the Net River Boat Launch area as a construction staging area. MDC installed a temporary steel bridge on wood timber mat cribbing to span over the existing culverts to provide access to the right embankment and areas to the west of the project. SESC measures including turbidity curtains and silt fence were installed. Areas were cleared to the southwest and northwest of the dam right abutment for stockpiling materials deemed to be unsuitable for re-use. Access roads were cleared for construction equipment access. Clearing also occurred to the southeast of the existing gravel parking lot for stockpiling excavated material to be possibly used for future construction.
MDC removed existing rip rap and armor stone from the upstream slope of the embankment and stockpiled them at the cleared southeast area for future reuse for the construction of the cofferdam. A temporary access road of wood timber mats was constructed to provide equipment access upstream and downstream of the existing dam.
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 7
Construction staking was performed by TMEE on October 24, 2022. TMEE provided survey control points, elevation benchmarks, and staked proposed alignments of the cofferdam and channel. After review of the slope stakes for the channel, it was determined that excavation of the left slope of the channel would interfere with the temporary bridge and prohibit construction vehicle access. The upstream end of the proposed alignment at station 0+00 and the point of intersection (PI) point at station 1+21.7 were shifted approximately 15’ to the west and the outlet point of the channel remained as per the design drawings. After discussion and approval from the Engineer the new alignment was staked by TMEE. The change was documented with RFI 001 included in Appendix D.
2.5 Temporary Cofferdam Construction
A temporary earthen cofferdam was constructed in general accordance with the design plans and specifications. MDC removed approximately one foot of unsuitable materials from the footprint of the cofferdam, placing in offroad trucks and hauling to stockpile areas prior to placing cofferdam fill. Heavy rip rap was placed as the core and downstream portion of the cofferdam, overlain with plain rip rap and filter stone (~3” minus rockfill), and covered with geotextile and salvaged granular fill. Fill was salvaged from the existing right embankment at the location shown on the design drawings.
A sample (Sample S-4) of the 3” minus filter/bedding stone was submitted for gradation analysis as a substitute by MDC for the specified MDOT 4AA. The Engineer took no exception to the 3” minus filter/bedding stone. Gradation results are included in Appendix E.
GEI obtained a sample of the salvaged granular fill materials (Sample S-5) and conducted nuclear density testing of the granular fill placed on the crest of the cofferdam. All density tests achieved greater than 95% of the maximum density as determined by the Michigan Cone Method. One test did not initially achieve 95% of the maximum density; however, MDC recompacted the area with the excavator bucket and loader and a retest of the area resulted in a compaction of 97.3% of the maximum density. Density test results are included in Appendix E.
GEI obtained two additional samples (Samples S-6 and S-7) of the stockpiled granular fill materials excavated from the right embankment for gradation analysis for assessment of suitability of use for future construction. Results are included in Appendix E.
2.6 Channel Construction
The horizontal alignment of the channel was adjusted approximately 15’ west as discussed in section 2.4 above. To limit the necessity for excavation within the river tailwater, the specified elevation of the channel outlet was raised from the proposed elevation of 1528.5’ to 1530.0’ resulting in an overall slope of the channel to change from 4.2% to 2.9%. The inlet of the channel was maintained at elevation of 1534.8.’ MDC submitted and GEI reviewed
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 8 and took no exception to RFI 002 to address this issue. RFI 002 is provided in Appendix D.
Excavation for the channel began at the downstream outlet end of the alignment at approximate station 1+75 to approximately 4’ below final grade as depicted on the design drawings. Elevations of the excavation and final grades were checked with MDC’s Topcon laser level and a grade rod. Geotextile fabric was placed, covered with approximately one foot of bedding stone and three feet of heavy rip rap choked with plain rip rap.
Approximately 12’ wide sections were completed prior to progressing upstream. Heavy rip rap was placed on the slopes of the existing dam embankments to a height of at least 8’ above the bottom of the channel. The remaining exposed cut slopes were lined with geotextile and plain rip rap per the design drawings.
The inlet area between 0+00 of the alignment and the cofferdam was approximately fifteen to thirty feet wide and was excavated to approximately three feet below final grade. A one-foot layer of bedding stone was placed over the geotextile fabric and covered with two feet of heavy rip rap choked with plain rip rap. The staging and stockpile areas on the west side of the site were restored with seed, fertilizer, and mulch prior to completing the upstream end of the channel and removal of the temporary cofferdam.
2.7 Cofferdam Removal
Removal of the temporary cofferdam occurred on November 14, 2022. Material removed was hauled to the stockpile area southeast of the gravel parking lot with the offroad dump trucks. Heavy rip rap from the cofferdam was placed to armor the remaining cofferdam end and upstream slope of the portion left in place to be used in future construction. Some of the heavy rip rap was used to armor the left slope of the channel to 8’ above the final grade of the bottom of the channel as called for on the design plans. The removal was performed to elevations as shown on the drawings. The reservoir elevation was at 1533.04’ at time of cofferdam removal which did not allow for immediate flow from the reservoir into the channel.
2.8 Restoration
Seed, fertilizer, and mulch was placed by hand casting the seed and blowing the mulch in areas disturbed by construction and not covered with rip rap. Seed placed included MDOT Roadside Mix as called for in the specifications, and a mixture of winter wheat, annual and perennial rye, and oats.
2.9 Stoplog Installation
With the cofferdam removed, MDC finalized all construction measures including rip rap placement, restoration efforts, and began demobilizing from the site. The DNR-provided timber stoplogs were modified according to the project drawings and installed. Several steel
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 9 logs were salvaged and reused in the left side with timber logs supplementing the previously lost steel logs. The installed stoplogs allowed the reservoir to rise slightly, allowing flow to enter the channel. Only some leakage flow through the stoplogs was observed through the stoplogs and concrete intake structure. The top of the stoplogs were at approximate elevation 1536.4’.
2.10 Demobilization
After completion of the left rip rap slope of the channel and seeding and mulch, MDC began the demobilization process. MDC removed turbidity curtains, wood timber mats, and all equipment, from the site by November 15, 2021.
GEI conducted an as-constructed topographic survey using a Trimble R10 GPS unit to document the actual construction of the channel and slopes. The topographic survey is included on the As-Constructed drawings included in Appendix A.
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 10
3. Summary of Deviations from Plans and Specifications
The work was conducted in general accordance with the plans and specifications and the designs dated September 12, 2022, for the concrete intake structure notch and October 14, 2022, for the channel construction. However, there were a few minor changes to the scope of work as discussed in Section 2. The changes are summarized in the bulleted list below:
• The steel stoplog slots for the new notch were observed to protrude as much as 1” downstream, contrary to the design drawings indication of 1/2” due to thickness variation in the existing concrete wall in order to maintain the critical clear distance of at least 3 ½” between the anchors and the upstream face of the concrete.
• The structural steel slots for the new notch were procured in 304 Stainless Steel in lieu of hot dipped galvanized A36 steel as approved in submittal TCR002.
• The proposed channel design alignment the excavation of the left slope of the channel would interfere with the temporary bridge. The upstream end of the proposed alignment at station 0+00 and the point of intersection (PI) point at station 1+21.7 were shifted approximately 15’ to the west and the outlet point of the channel remained as per the design drawings, after discussion and approval from the Engineer. MDC addressed this change by submitting RFI 001 which is provided in Appendix D.
• The outlet of the channel was raised to prevent excavation within the tailwater, from the proposed elevation of 1528.5’ to 1530.0’ resulting in an overall slope of the channel to change from 4.2% to 2.9% and the inlet of the channel to remain at elevation of 1534.8. To address this issue, MDC submitted RFI 002 which is provided in Appendix D.
• The filter stone and bedding stone was a 3” Minus material, submitted as a replacement for the specified MDOT 4AA material as approved in submittal MDC009. Gradation results are included in Appendix E.
The above modifications were reviewed by the Engineer and Owner and considered to not negatively impact the original design intent of the project.
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 11
4. Quality Control
4.1 Construction Documentation
The Field Engineer was responsible for observation, monitoring, and documentation of the construction work, performing quality control inspections, communicating progress to the Owner and Engineer, and evaluating compliance of the work with the Contract Drawings, and Technical Specifications. Construction documentation was performed by Mr. Bruce Peterson, E.I.T., Mr. Jacob Pieti, P.E., Mr. Patrick Dowling, E.I.T, and Mr. Jacob Burch, E.I.T.
4.1.1 Daily Construction Reports
The Field Engineer prepared a daily construction report for each day of construction when onsite. The reports summarized information of the days’ events and provided documentation for critical construction, existing conditions, and construction progress. The daily field reports provided and prepared by GEI, are included in chronological order in Appendix F.
4.2 Materials Testing
Nuclear density testing, sampling, and laboratory gradation analysis testing of existing soil and submitted filter/bedding stone material completed by GEI. Heavy rip rap and plain rip rap was visually inspected and graded as delivered on site. Complete results of the field and laboratory testing are summarized in Appendix E.
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 12
5. Summary of Submittals and Construction Materials
Prior to mobilizing, TCR provided submittals to GEI, detailing the means, methods, and materials proposed for construction. Approved technical submittals are included in Appendix C. The following submittal list summarizes the primary means, methods, materials, and suppliers utilized by TCR for this project.
• TCR001 – Contractor Work Plan
• TCR002 – Structural Steel Shop Drawings
Prior to mobilizing, MDC provided submittals to GEI, detailing the means, methods, and materials proposed for construction. Approved technical submittals are included in Appendix C. The following submittal list summarizes the primary means, methods, materials, and suppliers utilized by MDC for this project.
• MDC001a – Heavy Rip Rap (RH Huhtala – Old M28 Pit)
• MDC001a – Heavy Rip Rap (MDC – Michigamme Pit)
• MDC002 – Site Safety Program
• MDC003 – Mutual Industries Inc. Silt Fence
• MDC004 – Rhino Erosion King Straw Blanket
• MDC005 – Carthage Mills FX-105HS Geotextile
• MDC006 – Contractor Work Plan
• MDC007 – Curlex Sediment Log
• MDC008 – Plain Rip Rap (MDC – US141 Pit)
• MDC009 – 3” Minus Filter Gravel/Bedding Stone
• MDC010 – AER-FLO Environmental Turbidity Curtain
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C. 13
6. General Qualifications and Certification
The test results submitted in this report represent specific areas tested as indicated in the attached test records. Our field engineering services were performed in general accordance with accepted dam construction engineering practices and procedures as defined in the project plans and specifications dated September 12, 2022, and October 14, 2022. No other warranties or representations, either expressed or implied, are made. A certification letter from GEI (as the Design Engineer) is provided in Appendix G.
Observations of the channel, and stoplog slot remediation, appear to be effective.
The undersigned, a Registered Professional Engineer in Michigan, does hereby certify that he was designated as being in responsible charge of the project Quality Control and that the work was completed in partial accordance with the plans and specifications with exceptions as noted in this report.
GEI Consultants of Michigan, P.C.
Jacob E. Pieti, P.E.
Project Engineer
Michigan Department of Natural Resources January 18, 2023
GEI Consultants of Michigan, P.C.
Appendix A
Record Drawings
PIETI, JAKE B:\Working\DTMB\2201765 Net River Engineering Support Services\00_CAD\Design\Working\01_G-1.0_COVER SHEET.dwg - 12/21/2022
NET RIVER DAM CHANNEL CONSTRUCTION
STATE DAM I.D. NO 131
MICHIGAN DEPARTMENT OF NATURAL RESOURCES
BARAGA COUNTY
COVINGTON, MICHIGAN
THIS DOCUMENT, AND THE IDEAS AND DESIGNS INCORPORATED
HEREIN, IS AN INSTRUMENT OF PROFESSIONAL SERVICE, IS THE
PROPERTY OF GEI CONSULTANTS AND IS NOT TO BE USED, IN WHOLE
OR IN PART, FOR ANY OTHER PROJECT WITHOUT THE WRITTEN
AUTHORIZATION OF GEI CONSULTANTS.
STATE MAP
(NOT TO SCALE)
SITE LOCATION MAP
(NOT TO SCALE)
GEI PROJECT NO. 2201765
SITE
SOURCE:
GOOGLE EARTH IMAGE
NO. DATE ISSUE/REVISION APP
0 10/14/2022 ISSUE FOR CONSTRUCTION GLK
1 12/23/2022 RECORD DRAWINGS GLK
Consultants
PREPARED BY:
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
DWG. NO.
SHEET NO.
G-1.0
SITE
PREPARED FOR:
MICHIGAN DEPARTMENT OF NATURAL
RESOURCES
427 US-41 NORTH
BARAGA, MI 49908
(906) 353-6651
SHEET INDEX
SHEET NO. DRAWING NO. SHEET TITLE
G-1.0 1 OF 15 COVER SHEET
G-2.0 2 OF 15 GENERAL NOTES AND LEGEND
C-1.0 3 OF 15 EXISTING CONDITIONS
C-2.0 4 OF 15 SESC PLAN
C-3.0 5 OF 15 COFFERDAM PLAN
C-4.0 6 OF 15 COFFERDAM PROFILE
C-5.0 7 OF 15 EXCAVATION PLAN
C-6.0 8 OF 15 CHANNEL PLAN
C-7.0 9 OF 15 CHANNEL PROFILE
C-8.0 10 OF 15 COFFERDAM REMOVAL AND SITE
STABILIZATION PLAN
C-9.0 11 OF 15 COFFERDAM REMOVAL PROFILE
T-1.0 12 OF 15 TECHNICAL SPECIFICATIONS 1 OF 2
T-2.0 13 OF 15 TECHNICAL SPECIFICATIONS 2 OF 2
D-01 14 OF 15 CONCRETE NOTCH AT NORTH WALL -
DEMOLITION
S-01 15 OF 15 STOP LOG DETAILS
AS-CONSTRUCTED NOTES:
1. REFERENCE THE FINAL CONSTRUCTION REPORT FOR FULL
DESCRIPTION OF ACTIVITIES PERFORMED AND ALL RECORD
DOCUMENTS.
PI
ET
I, JA
KE
B
:\W or ki ng
\D
TM
B\
N et R iv er
E ng in ee rin g
Su pp or t S er vi ce s\
_C
AD
\D es ig n\ W or ki ng \0
2_ G
-2 .0
_G
EN
ER
AL
N O
TE
S
AN
D
L
EG
EN
D
.d w g
2/
/2
MICHIGAN
DEPARTMENT OF
NATURAL
RESOURCES
427 US-41 NORTH
BARAGA, MI 49908
(906) 353-6651
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
NO DATE ISSUE/REVISION APP
0 10/14/2022 ISSUE FOR CONSTRUCTION GLK
1 12/23/2022 RECORD DRAWINGS GLK
SHEET NAME DWG. NO.
NET RIVER DAM
CHANNEL CONSTRUCTION
BARAGA COUNTY, MI
SHEET NO.
GENERAL NOTES AND
LEGEND
G-2.0
If this scale bar does not measure 1" then drawing is not original scale.
Attention:
0 1"
DRAFT
Designed:
Checked:
Drawn:
P.E. No:
GEI Project
JEP
KAR
AKG
Approved: GLK
48098
2201765
STRUCTURAL
CONCRETE
APPROX = APPROXIMATE
BIT = BITUMINOUS
BOT = BOTTOM
CIP = CAST IN PLACE
CL = CENTERLINE
CLR = CLEAR
CMP = CORRUGATED METAL PIPE
CNTR = CENTER
CONC = CONCRETE
DIA, Ø = DIAMETER
DIM = DIMENSION(S)
D/S = DOWNSTREAM
DWG, DWGS = DRAWING OR DRAWINGS
EA = EACH
EL., ELEV = ELEVATION
EW = EACH WAY
FT = FEET OR FOOT
GALV = GALVANIZED
GR = GRADE
HSS = HOLLOW STRUCTURAL STEEL
LOC = LIMITS OF CONSTRUCTION
MAX = MAXIMUM
MDOT = MICHIGAN DEPARTMENT OF
TRANSPORTATION
MIN = MINIMUM
NO = NUMBER
NTS = NOT TO SCALE
O.C. = ON CENTER
O.D. = OUTSIDE DIAMETER
PL = PLATE
RA = RADIUS
REINF = REINFORCEMENT
REQ'D = REQUIRED
SPEC = SPECIFICATION(S)
TYP = TYPICAL
U.N.O. = UNLESS NOTED OTHERWISE
U/S = UPSTREAM
VERT = VERTICAL
VIF = VERIFY IN FIELD
ABBREVIATIONS:
HATCH LEGEND:
GENERAL LEGEND:
A S-01
A S-01
SECTION LOCATION. THE LETTER "A" REFERS TO THE SECTION
DESIGNATION. THE NUMBER "S-01" REFERS TO THE DRAWING NUMBER
WHERE THE SECTION IS SHOWN.
S-01
DETAIL LOCATION. THE NUMBER "1" REFERS TO THE DETAIL
DESIGNATION. THE NUMBER "S-01" REFERS TO THE DRAWING NUMBER
WHERE THE DETAIL IS SHOWN.
SCALE: N.T.S.
DETAIL - XXXX1
S-01
SCALE: N.T.S.
SECTION - XXXXA
S-01
DETAIL TITLE. THE NUMBER "1" REFERS TO THE DETAIL DESIGNATION.
THE NUMBER "S-01" REFERS TO THE DRAWING NUMBER WHERE THE
DETAIL IS CALLED OUT.
SECTION TITLE. THE LETTER "A" REFERS TO THE DETAIL
DESIGNATION. THE NUMBER "S-01" REFERS TO THE DRAWING
NUMBER WHERE THE DETAIL IS CALLED OUT.
EXISTING GROUND
SURFACE
VERTICAL DATUM:
NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88)
HORIZONTAL DATUM:
NORTH AMERICAN DATUM 1983 (NAD83), MICHIGAN SOUTH ZONE, INTERNATIONAL FOOT
GENERAL NOTES:
1. THESE NOTES SUPPLEMENT THE PROJECT SPECIFICATIONS. BEFORE BEGINNING CONSTRUCTION, THE CONTRACTOR SHALL VERIFY ALL CRITICAL DIMENSIONS, LOCATIONS, AND ELEVATIONS
BEFORE PROCEEDING WITH WORK. ANY DISCREPANCY FOUND AMONG THE DRAWINGS,
SPECIFICATIONS, THESE NOTES, AND THE SITE CONDITIONS SHALL BE REPORTED TO THE
OWNER'S REPRESENTATIVE (GEI), WHO SHALL CORRECT SUCH DISCREPANCY IN WRITING. ANY
WORK DONE BY THE CONTRACTOR AFTER DISCOVERY OF SUCH DISCREPANCY SHALL BE DONE AT
CONTRACTOR'S RISK.
2. CONSTRUCTION IS SUBJECT TO THE RULES AND REGULATIONS OF THE MICHIGAN DEPARTMENT OF
THE ENVIRONMENT, GREAT LAKES, AND ENERGY (EGLE). SUBSTANTIVE CHANGES TO THE
APPROVED DRAWINGS AND SPECIFICATIONS MAY REQUIRE EGLE APPROVAL.
3. THE SUBSURFACE UTILITY INFORMATION IN THESE DRAWINGS SHALL BE ASSUMED TO BE
APPROXIMATE. THE CONTRACTOR SHALL MAKE ANY NECESSARY INVESTIGATIONS AND
COORDINATION WITH THE 811 MISS-DIG ONE CALL PRIOR TO COMMENCEMENT OF ANY WORK
ACTIVITIES.
4. TEMPORARY STAGING, STORAGE, STOCKPILE AND ACCESS AREAS SHALL BE WITHIN WORK LIMITS
AND RESTORED BY THE CONTRACTOR TO ORIGINAL CONDITION. ALL RESTORATION OF GRASSED
AREAS SHALL BE WITH SEED AND MULCH.
5. THE EXISTING TOPOGRAPHY HEREIN IS FOR INFORMATIONAL PURPOSES ONLY. THE ENGINEER
AND OWNER IS NOT RESPONSIBLE FOR ANY MISCHARTED OR UNCHARTED UTILITIES, OR OTHER
ERRORS DETECTED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY ALL SITE
CONDITIONS.
6. EXISTING CONDITIONS SHOWN ON THE DRAWINGS ARE APPROXIMATE, ACTUAL FIELD CONDITIONS
MAY VARY. REFER TO REFERENCE DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL
INFORMATION REGARDING EXISTING CONDITIONS.
7. RESERVOIR LEVEL VARIES. INDICATIONS OF WATER LEVELS SHOWN ON THE DRAWINGS MAY NOT
BE REPRESENTATIVE OF ACTUAL WATER LEVELS THAT MAY BE ENCOUNTERED DURING
PERFORMANCE OF WORK BY THE CONTRACTOR.
8. CONTRACTOR SHALL PROVIDE APPLICABLE SIGNAGE AND TEMPORARY RESTRICT PUBLIC ACCESS
TO THE WORK AREAS.
COORDINATION:
1. SCHEDULE, COORDINATE, AND PERFORM THE WORK TO MEET THE OVERALL PROJECT SCHEDULE
CONSTRAINTS.
2. COORDINATE WITH THE OWNER FOR DESIGNATION OF SPECIFIC WORK AREAS FOR RESTRICTED
ACCESS DURING PARTICULAR PERIODS OF THE WORK, AS WELL AS NEED FOR FENCING, SIGNAGE, AND OTHER MEASURES NECESSARY TO PROTECT THE PUBLIC, COMPLETED WORK, WORK IN
PROGRESS, AND CONTRACTOR'S EQUIPMENT AND PROPERTY ON SITE.
3. MAINTAIN FULL AND COMPLETE ACCESS TO WORK TO OWNER, ENGINEER, AND REGULATORY
PERSONNEL.
PERMITTING AND ENVIRONMENTAL:
COMPLY WITH ALL REQUIREMENTS OF OWNER-OBTAINED PROJECT PERMITS. CONTRACTOR SHALL
OBTAIN THE PART 91 SESC PERMIT FROM BARAGA COUNTY.
PROJECT WORKS AUTHORIZED UNDER REQUIREMENTS OF EGLE JPA WRP035090
STEWARDSHIP / ARTIFACT NOTE:
IF ANY ARTIFACTS ARE DISCOVERED DURING THE CONSTRUCTION PROCESS, ALL WORK IS TO
STOP AND THE OWNER'S REPRESENTATIVE / PROJECT MANAGER SHALL BE NOTIFIED.
ARTIFACTS OR ARCHEOLOGICAL MATERIALS ARE DEFINED AS : ABORIGINAL ANTIQUITIES AND
OTHER RECORDS ON ANTIQUITY, INCLUDING MOUNDS, MINES, EARTHWORKS, VILLAGE SITES,
CAMP SITES, BURIALS, HUMAN OR OTHER BONES, SHELLS, STONE IMPLEMENTS, BONE OR
COPPER IMPLEMENTS, POTTERY OR SHARD OF POTTER, OR OTHER OBJECTS RELATING TO
NATIVE AMERICAN OCCUPATION; AND MODERN ARTIFACTS, SUCH AS FORTS, RELICS, AND
OTHER ARTIFACTS RELATING TO THE HISTORIC, COLONIAL, TERRITORIAL AND EARLY
STATEHOOD PERIODS.
EXISTING DATA SOURCES:
1. EXISTING BASEMAP COMPILED FROM AERIAL IMAGERY OBTAINED FROM GOOGLE EARTH
(2022) AND OVERLAID BY THE RESULTS OF A SITE SURVEY CONDUCTED JULY 27, 2022 BY
GEI CONSULTANTS. A TRIMBLE R6 GNSS SYSTEM GPS WAS USED FOR THE DATA
COLLECTION. THIS WAS OVERLAIN BY THE RESULTS OF A BATHYMETRIC SURVEY
PERFORMED BY TRIMEDIA ENVIRONMENTAL & ENGINEERING ON SEPTEMBER 1, 2022.
2. GEOTECHNICAL EXPLORATION CONDUCTED BY GEI IN JULY, 2022. LABORATORY TEST
RESULTS ARE AVAILABLE UPON REQUEST.
WETLAND
EXCAVATION
GRANULAR
FILL
MDOT HEAVY
RIP RAP
LINETYPE LEGEND:
ALIGNMENTS
EXISTING GROUND
TOPO (MAJOR)
TOPO (MINOR)
TREELINE
DESIGN GRADE
WATERLINE
MDOT PLAIN
RIP RAP
HISTORICAL REFERENCE DRAWINGS
SHEET NO. SHEET TITLE SHEET DATE
16286-1 COVER SHEET 9/16/1988
16286-2 EXISTING SITE CONDITIONS 9/16/1988
16286-3 PROPOSED DAM CONTOURS 11/2/1988
16286-4 TYPICAL DESIGN CROSS-SECTIONS 11/2/1988
16286-5 EARTHWORK CROSS-SECTIONS 11/2/1988
16286-6 SPILLWAY TRASH RACK DESIGN 7/6/1989
16286-7 TRASH RACK DETAILS 7/18/1989
16286-8 OVERLAND FLOW CENTERLINE
PROFILE 5/8/1989
16286-9 OVERLAND PLAN SITE TOPOGRAPHY 5/8/1989
16286-10 OVERLAND FLOW CROSS-SECTIONS 11/21/1988
16286-11 DOWNSTREAM CROSS-SECTIONS 11/21/1988
16286-12 DAM CROSS-SECTIONS 12/2/1988
1 OF 3 WETLAND MITIGATION PLAN AND
CONSTRUCTION SEQUENCE 3/2/1990
2 OF 3 ENLARGEMENT I: EAST BAY AREA AND
DETAILS 3/2/1990
3 OF 3 ENLARGEMENT II: SOUTH BAY AREA
AND DETAILS 3/2/1990
FILTER
GRAVEL
BEDDING STONE
TIMBER MATTING
OH
W
OHW
OHW
OHW
OH
W
OHW
OHW OHW OHW
OHW
OH
W
OHW
OHW
OHW
OHW
OH
W
OHW
CP-1
CP-2
CP-3
CONTROL POINT
LOCATION DATA
POINT #
CP-1
CP-2
CP-3
NORTHING
603699.4880
603705.4260
603712.6310
EASTING
25864922.4000
25864638.6600
25865135.3200
ELEVATION
1546.37
1545.88
1547.67
IEWET
WET
WET
W
ET
WET
WET
WET
WET
W
ET
WET
WET
W
ET
WET W
ET
WETWET
W
ET
W
ET
W
ET
W
ET
WET
WET
WET
WET
WET
WET
W
ET
WET
W
ET
WET
WET
WET
WET
WET
WET
WET
WET
WET
W
ET
W
ET
WET
WET
WET
WET
WET
WET
153015
301530
PI
ET
I, JA
KE
B
:\W or ki ng
\D
TM
B\
N et R iv er
E ng in ee rin g
Su pp or t S er vi ce s\
_C
AD
\D es ig n\ W or ki ng \0
3_ C
-1 .0
_E
XI
ST
IN
G C
O N
D
IT
IO
N
S.
dw g
2/
/2
MICHIGAN
DEPARTMENT OF
NATURAL
RESOURCES
427 US-41 NORTH
BARAGA, MI 49908
(906) 353-6651
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
NO DATE ISSUE/REVISION APP
0 10/14/2022 ISSUE FOR CONSTRUCTION GLK
1 12/23/2022 RECORD DRAWINGS GLK
SHEET NAME DWG. NO.
NET RIVER DAM
CHANNEL CONSTRUCTION
BARAGA COUNTY, MI
SHEET NO.
EXISTING CONDITIONS
C-1.0
EXISTING CONDITIONS
PLAN
SCALE, FEET
40 80
If this scale bar does not measure 1" then drawing is not original scale.
Attention:
0 1"
DRAFT
Designed:
Checked:
Drawn:
P.E. No:
GEI Project
JEP
KAR
AKG
Approved: GLK
48098
2201765
APPROXIMATE WATERLINE
ELEV. 1536.0 SURVEYED
7/27/2022
CONCRETE BOAT
LAUNCH RAMP
TREE LINE
APPROXIMATE WATERLINE
ELEV. 1530.0 SURVEYED
7/27/2022
NET RIVER FLOODING
N
ET R
IVER
NET RIVER DAM ROAD
GRAVEL PARKING LOT
RESTROOM
CONCRETE INTAKE
STRUCTURE
PARTIALLY
CRUSHED 72" Ø
CMP CULVERT
72" Ø CMP
CULVERT
CONCRETE OUTLET
STRUCTURE
APPROXIMATE WATERLINE
ELEV. 1533.5 SURVEYED
9/1/2022
(0.9 M
ILES TO US 141)
HISTORICAL OHWM
ELEV. 1543.2
FL
O
W
NOTES:
1. CONTROL POINTS CONSIST OF DRIVEN REBAR
POINT WITH CAP.
2. CONTRACTOR SHALL RELOCATE CONTROL
POINTS CP-2 AND CP-3 TO AREA OUTSIDE
DISTURBANCE TO FACILITATE PROJECT WORK.
SURVEY RELOCATED LOCATIONS AND PROVIDE
TO ENGINEER.
AS-CONSTRUCTED NOTES:
1. CP-2 AND CP-3 WERE REMOVED AND REPLACED
WITH CP-105 AND CP-106.
4"Ø PVC DRAIN OUTLET
CP-105
CP-106
CP-105 603662.400
0 25864955.2000 1546.5000
CP-106 603691.800
0 25864799.4000 1544.6000
OHW
OHW
OHW
OH
W
OHW
OHW OHW OHW
OHW
OH
W
OHW
OHW
OHW
CP-1
CP-2
CP-3
IEWET
WET
WET
W
ET
WET
WET
WET
WET
W
ET
WET
WET
W
ET
WET W
ET
WETWET
W
ET
W
ET
W
ET
W
ET
WET
WET
WET
WET
WET
WET
W
ET
WET
W
ET
WET
WET
WET
WET
WET
WET
WET
WET
WET
W
ET
W
ET
WET
WET
WET
WET
WET
WET
TC
TC
TC
SF SF
SF
SF
SF
SF SF SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
NOTES:
1. MAINTAIN AT LEAST 12" OF CLEARANCE BETWEEN BOTTOM
OF CURTAIN AND SEDIMENT.
2. REEFING LINES ARE REQUIRED TO BE INSTALLED AND
USED TO SHORTEN CURTAIN DURING PERIODS OF LOW
WATER LEVELS.
FLOTATION SEGMENT ATTACH LINES TO SHACKLE
BOTTOM OF
WATER BODY
FLOTATION DEVICES (BUOY).
LIGHTED BOUYS REQUIRED
AT 100' INTERVALS.
FILTER CLOTH SKIRT
(DEPTH VARIES)
STREAM ANCHOR
UNIVERSAL CONNECTOR
TOP TENSION CABLE
FLOATATION SEGMENT FOLD JOINT
FOR STORAGE
TOP LOAD LINE
SKIRT CONNECT GROMMETS
PROFILE
ANCHOR LINES
TURBID WATER CLEAR WATER
SECTION
DISTURBED GROUND/
WORK ZONE
SHORE ANCHOR (TYP) SHORELINE
TURBIDITY CURTAIN
50'-100'
(TYP)
INSTALLATION
CHANNEL ANCHOR
TURBIDITY CURTAIN
SCALE: NTS
INSTALLATION WITH TRENCHING
NOTES:
1. SILT FENCE SHALL BE PLACED ON SLOPE CONTOURS TO MAXIMIZE PONDING EFFICIENCY.
2. INSPECT AND REPAIR FENCE AFTER EACH STORM EVENT AND REMOVE SEDIMENT WHEN
NECESSARY. 9" (225mm) MAXIMUM RECOMMENDED STORAGE HEIGHT.
3. REMOVED SEDIMENT SHALL BE DEPOSITED TO AN AREA THAT WILL NOT CONTRIBUTE
SEDIMENT OFF-SITE AND CAN BE PERMANENTLY STABILIZED.
EXTRA STRENGTH FILTER
FABRIC NEEDED WITHOUT
WIRE MESH SUPPORT
STEEL OR WOOD POST
ATTACH FILTER FABRIC
SECURELY TO UPSTREAM
SIDE OF POST
10' (3m) MAXIMUM SPACING WITH WIRE SUPPORT FENCE 6' (1.8m)
MAXIMUM SPACING WITHOUT
WIRE SUPPORT FENCE
FLOW
PONDING HEIGHT
8" (200 mm)
3/4" (20mm) MIN
DRAIN ROCK
FLOW
12" MIN
(300 MM)
9" MAX
(225 mm)
STORAGE HT
PONDING HEIGHT
FLOW
INSTALLATION WITHOUT TRENCHING
STEEL OR WOOD
POST
36" (1M) HIGH MAX
12" MIN
(300 mm)
4"x6" (100x150mm)
TRENCH WITH
COMPACTED BACKFILL
SILT FENCE
SCALE: NTS
1"x1"x24"
WOOD STAKE
COMPACT EXCAVATED
SOIL ON BERM
CREST SIDE
SET WATTLE ROLL IN
2" - 3" DEEP TRENCH
12" (MIN)
INSTALL STAKE
PERPENDICULAR
TO SLOPE FACE
2" -3
STRAW WATTLE STAKE
SCALE: NTS
PI
ET
I, JA
KE
B
:\W or ki ng
\D
TM
B\
N et R iv er
E ng in ee rin g
Su pp or t S er vi ce s\
_C
AD
\D es ig n\ W or ki ng \0
4_ C
-2 .0
_S
ES
C P
LA
N
.d w g
2/
/2
MICHIGAN
DEPARTMENT OF
NATURAL
RESOURCES
427 US-41 NORTH
BARAGA, MI 49908
(906) 353-6651
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
NO DATE ISSUE/REVISION APP
0 10/14/2022 ISSUE FOR CONSTRUCTION GLK
1 12/23/2022 RECORD DRAWINGS GLK
SHEET NAME DWG. NO.
NET RIVER DAM
CHANNEL CONSTRUCTION
BARAGA COUNTY, MI
SHEET NO.
SESC PLAN
C-2.0
If this scale bar does not measure 1" then drawing is not original scale.
Attention:
0 1"
Designed:
Checked:
Drawn:
P.E. No:
GEI Project
JEP
KAR
AKG
Approved: GLK
48098
2201765
TURBIDITY CURTAIN (TYP)
NET RIVER FLOODING
N
ET R
IVER
SESC
PLAN
SCALE, FEET
40 80
NOTES:
1. INSTALL BALES AS SHOWN. IF ADDITIONAL STORAGE VOLUME IS NECESSARY, SECURE
ADDITIONAL BALES ON TOP OF INITIAL BOTTOM LAYER AND/OR BY INCREASING THE
NUMBER BALES IN BOTTOM LAYER.
2. SECURE EACH BALE & EACH LAYER OF BALES USING EITHER TWO REBARS OR TWO
WOODEN STAKES PER BALE.
3. LINE TRAP WITH GEOTEXTILE FABRIC AND SECURE OVER HAY BALES USING STAKES.
4. THE SEDIMENT TRAP WILL NOT BE GREATER THAN TWO BALES IN HEIGHT FOR SIX-BALE
BOTTOM CONSTRUCTION WITHOUT ADDITIONAL REINFORCEMENT OF TRAP WALLS.
5. CONSTRUCT DEWATERING STRUCTURE TO ACCOMODATE ANTICIPATED PUMPING RATES:
EXAMPLE PUMPING RATE = 200 G.P.M.
STORAGE VOLUME (C.F.) = 16 x 200 G.P.M. = 3,200 C.F.
HEIGHT OF STRAW BALES STRUCTURE = 3 FEET (2 BALES STACKED)
INSIDE DIMENSIONS OF STRUCTURE = 33 x 33 FEET SQUARE
6. SEDIMENT TRAP DEWATERING DEVICE CANNOT BE USED IN A WETLAND.
6 INCH MIN.
PLAN VIEW
SECTION A-A
LINE TRAP WITH
GEOTEXTILE
FABRIC, SEE
NOTE 4
CLAMPS
FILTER BAG
WELL VEGETATED, GRASSY AREA
WELL VEGETATED, GRASSY AREA
FILTER BAG
HEAVY DUTY LIFTING STRAPS
(RECOMMENDED)
PLAN VIEW
ELEVATION VIEW
NOTES:
1. LOW VOLUME FILTER BAGS SHALL BE MADE FROM NON-WOVEN GEOTEXTILE MATERIAL SEWN WITH HIGH STRENGTH, DOUBLE STITCHED "J" TYPE SEAMS. THEY SHALL BE CAPABLE OF TRAPPING PARTICLES LARGER THAN 150 MICRONS.
FILTER BAGS SHALL BE PROPERLY SIZED; REFER TO THE MANUFACTURER SPECIFICATIONS TO DETERMINE APPROPRIATE
SIZE.
2. A SUITABLE MEANS OF ACCESSING THE BAG WITH MACHINERY REQUIRED FOR DISPOSAL PURPOSES SHALL BE PROVIDED.
FILTER BAGS SHALL BE REPLACED WHEN THEY BECOME 1/2 FULL OF SEDIMENT. SPARE BAGS SHALL BE KEPT AVAILABLE FOR REPLACEMENT OF THOSE THAT HAVE FAILED OR ARE FILLED. BAGS SHALL BE PLACED ON STRAPS TO FACILITATE
REMOVAL UNLESS BAGS COME WITH LIFTING STRAPS ALREADY ATTACHED.
3. BAGS SHALL BE LOCATED IN WELL-VEGETATED (GRASSY) AREA, AND DISCHARGE ONTO STABLE, EROSION RESISTANT AREAS. WHERE THIS IS NOT POSSIBLE, A GEOTEXTILE UNDERLAYMENT AND FLOW PATH OR SECONDARY CONTAINMENT SHALL BE PROVIDED. BAGS MAY BE PLACED ON FILTER STONE TO INCREASE DISCHARGE CAPACITY. BAGS SHALL NOT BE PLACED ON SLOPES GREATER THAN 5%. FOR SLOPES EXCEEDING 5%, CLEAN ROCK OR OTHER NON-ERODIBLE AND
NON-POLLUTING MATERIAL MAY BE PLACED UNDER THE BAG TO REDUCE SLOPE STEEPNESS.
4. NO DOWNSLOPE SEDIMENT BARRIER IS REQUIRED FOR MOST INSTALLATIONS. COMPOST BERM OR COMPOST FILTER SOCK SHALL BE INSTALLED BELOW BAGS LOCATED IN HQ OR EV WATERSHEDS, WITHIN 50 FEET OF ANY RECEIVING
SURFACE WATER OR WHERE GRASSY AREA IS NOT AVAILABLE.
5. THE PUMP DISCHARGE HOSE SHALL BE INSERTED INTO THE BAGS IN THE MANNER SPECIFIED BY THE MANUFACTURER
AND SECURELY CLAMPED. A PIECE OF PVC PIPE IS RECOMMENDED FOR THIS PURPOSE.
6. THE PUMPING RATE SHALL BE NO GREATER THAN 750 GPM OR 1/2 THE MAXIMUM SPECIFIED BY THE MANUFACTURER, WHICHEVER IS LESS. PUMP INTAKES SHALL BE FLOATING AND SCREENED.
7. FILTER BAGS SHALL BE INSPECTED DAILY. IF ANY PROBLEM IS DETECTED, PUMPING SHALL CEASE IMMEDIATELY AND NOT
RESUME UNTIL THE PROBLEM IS CORRECTED.
8. FILTER BAGS MAY BE PLACED IN WETLANDS IF UPLAND DISCHARGE LOCATIONS ARE NOT LOCATED WITHIN A SUITABLE
DISTANCE
DISCHARGE HOSE
INTAKE HOSEPUMP
CLAMPS
PUMP
INTAKE HOSE
DISCHARGE HOSE
POTENTIAL STOCKPILE AREA
SILT FENCE (TYP)
AS-CONSTRUCTED NOTES:
1. TURBIDITY CURTAIN REMOVED AT CONSTRUCTION COMPLETION ON 11/15/22. SILT FENCE
REMAINED IN PLACE TO PROTECT SLOPES UNTIL VEGETATION IS REESTABLISHED.
OHW
OHW
OH
W
OHW
OHW
OHW
OHW OHW
OHW
OHW OHW OHW
OHW
CP-2
IE
WET
WET
WET
WET
W
ET
WET
W
ET
W
ET
WET WET
WET
WET
WET
WET
WET
WET
W
ET
WET
WET
WET W
ET
WET
WET WET
W
ET
WET
WET
WET
WET
WET
W
ET
W
ET
WET
W
ET
W
ET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
WET
W
ET
W
ET
W
ET
W
ET
WET
WET
WET
WET
WET
TC TC TC
TC
TC
TC
TC
TC
SF
SF
SF
SF
SFSF
SF
SF
SF
SF
SF
SF
SF
SF
SF SF
SFSF
1+00
PC: 0+88.55
PT: 1+83.70
0+00
1+96.56
APPROXIMATE CREST
REMOVAL LIMITS
(SEE NOTE 1)
X X
X
PI
ET
I, JA
KE
B
:\W or ki ng
\D
TM
B\
N et R iv er
E ng in ee rin g
Su pp or t S er vi ce s\
_C
AD
\D es ig n\ W or ki ng \0
5_ C
-3 .0
_C O
FF
ER
D
AM
P
LA
N .d w g
2/
/2
MICHIGAN
DEPARTMENT OF
NATURAL
RESOURCES
427 US-41 NORTH
BARAGA, MI 49908
(906) 353-6651
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
NO DATE ISSUE/REVISION APP
0 10/14/2022 ISSUE FOR CONSTRUCTION GLK
1 12/23/2022 RECORD DRAWINGS GLK
SHEET NAME DWG. NO.
NET RIVER DAM
CHANNEL CONSTRUCTION
BARAGA COUNTY, MI
SHEET NO.
COFFERDAM PLAN
C-3.0
If this scale bar does not measure 1" then drawing is not original scale.
Attention:
0 1"
DRAFT
Designed:
Checked:
Drawn:
P.E. No:
GEI Project
JEP
KAR
AKG
Approved: GLK
48098
2201765
COFFERDAM
PLAN
SCALE, FEET
20 40
COFFERDAM
TEMPORARY BRIDGE
C-3.0
TEMPORARY BRIDGE
TYPICAL PLAN
SCALE: 1" = 10'
C-3.0
TEMPORARY BRIDGE
TYPICAL SECTION
SCALE: 1" = 10'
B
C-3.0
40' MIN
TEMPORARY BRIDGE
TIMBER MATTING
PARTIALLY CRUSHED
72" Ø CMP CULVERT
72" Ø CMP CULVERT
TEMPORARY
BRIDGE
TIMBER MATTING
BRIDGE SHALL NOT CONTACT
GROUND SURFACE
EMBANKMENT CREST
COFFERDAM
TYPICAL ROCK CORE SECTION
SCALE: 1" = 10'
A
C-3.0
6'
3H 1V
GRANULAR FILL
EXISTING
SURFACE
VARIES
COFFERDAM CREST
EL 1538.0'
FILTER GRAVEL 12"
THICK MIN
HEAVY RIP RAP
10'
TOP OF HEAVY RIP RAP
EL 1536.0'
ANTICIPATED CONSTRUCTION SEQUENCE:
1. INSTALL SESC MEASURES
2. INSTALL TEMPORARY BRIDGE
3. CLEAR RIGHT ABUTMENT AND CONSTRUCT
TEMPORARY ACCESS ROAD
4. BEGIN CONSTRUCTING COFFERDAM
2H
1V2-YEAR FLOOD ELEV. 1536.4'
9/1/22 WATER ELEV. 1533.5'
B C-3.0
B C-3.0
A C-3.0
A C-3.0
GEOTEXTILE FABRIC
NOTES:
1. EXISTING EMBANKMENT CREST WITHIN LIMITS OF
PROPOSED CHANNEL CUT MAY BE EXCAVATED TO NO
LOWER THAN ELEVATION 1539.0 FT PRIOR TO
COMPLETION OF COFFERDAM. THIS IS INTENDED TO
ALLOW FOR PLACEMENT OF GRANULAR FILL SOURCED
FROM EXISTING EMBANKMENT MATERIALS.
1. VERTICAL PROFILE SHOWN ON SHEET C-4.0.
6' C
O
FF
ER
D
AM
AL
IG
N
M
EN
T
COFFERDAM CREST ALIGNMENT1
STATION NORTHING (FT) EASTING (FT) ELEVATION (FT)
0+00 603794.05 25864536.45 1538.00
0+88.55 603794.05 25864625.00 1538.00
CURVE DESIGN DATA: R = 61.63 FT, L = 95.15 FT
1+83.70 603734.07 25864686.61 1538.00 1+96.56 603721.22 25864686.96 1538.00
AS-CONSTRUCTED NOTES:
1. COFFERDAM REMOVED PER C-8.0 AND C-9.0.
CL LEFT CMP CULVERT
CL TEMPORARY BRIDGE
2.4' file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .