About this file

This document is an AAAP Project Specific Advertisement (PSA) Attachment detailing the post-award schedule for a federal real estate lease project involving tenant improvements (TI) and building standard alterations and construction (BSAC). The schedule replaces the attachment referenced in section 1.05 of the Request for Lease Proposal (RLP/R100) and applies to section 4.01 of the Lease (L100).

The post-award schedule commences within 5 working days of lease award and establishes a total of 245 working days from lease award to final government acceptance of the space. The schedule breaks down nine sequential activities: Lessor-Provided Design Intent Drawings (30 days), Government review and approval of design drawings (45 days), Lessor preparation and submission of construction documents (20 days), Government review of construction drawings (20 days), Lessor submission of TI and BSAC pricing proposal (20 days), Government pricing review and approval (30 days), Government issuance of Notice to Proceed (10 days), Lessor construction completion (60 days), and Government inspection and acceptance of finished space (10 days). The schedule involves GSA and a client agency in the government review and approval processes.

View the file

Other files

File Type Posted
4TX1045 - Delineated Area (DA) Map.png PNG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (04/26)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 30

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 45

Lessor Preparation and Submission of Construction Documents 20

Government Review of Construction Drawings 20

Lessor Preparation and Submission of the TI and BSAC Price Proposal 20

Government Reviews and Approves Pricing 30

Government Issues Notice to Proceed with Construction 10

Lessor Completes Construction of TIs and Completion of Other Required Construction Work 60

Government Inspects and Accepts Finished Space 10

Total Work Days from Lease Award to Government Acceptance 245