Post Award Schedule.docx

DOCX document 2 MB Posted

Attached to
Lease of Office Space within Woodbury, NJ. Request for Lease Proposals (RLP) #26NAT02
Solicitation number
4NJ0314
Issued by

About this file

This is a Post-Award Schedule document that establishes the timeline for design, construction, and acceptance of tenant improvements for a GSA lease of office space in Woodbury, New Jersey. The schedule commences within 5 working days of lease award and outlines the sequential phases required to complete the project, culminating in government acceptance of the finished space within 379 total working days.

The schedule is organized into four primary phases: (1) Lessor-Provided Design Intent Drawings (DIDs), requiring three submission iterations at 50%, 95%, and final approval, with GSA and Agency reviews and corrections totaling approximately 66 working days; (2) Construction Documents (CDs) preparation, submission, and review in three stages at 75%, 100%, with final corrections, spanning approximately 98 working days; (3) Tenant Improvement (TI) and Building Specific Amortized Capital (BSAC) pricing proposal preparation and government approval, requiring 60 combined working days; and (4) Construction execution and government inspection, requiring 90 working days. The Notice to Proceed with Construction is issued after government approval of pricing, followed by 80 working days for lessor completion of construction and 10 working days for government inspection and final acceptance. This schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to the management of the design and construction process for the 3,506 to 3,612 USF office space lease with a 10-year term and 5-year firm period.

View the file

Other files

File Type Posted
Delineated Area Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity
Working Days

Lessor-Provided Design Intent Drawings

DIDs Provided by Lessor (50%) 20 days DIDs Reviewed by GSA / Agency 13 days Lessor Provides Corrected DID's 10 days DIDs Provided by Lessor (95%) 20 days DIDs Reviewed by GSA / Agency 13 days Lessor Provides Corrected DID's 10 days

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 10 Days

Lessor Preparation and Submission of Construction Documents
CDs Provided by Lessor (75%) 20 days

CDs Reviewed by GSA / Agency 13 days Lessor Provides Corrected CDs 10 days Lessor Provides 100% 20 days Government Review 15 days Final Corrections by Lessor 10 days Final Review Government Review 15 days

Government Review of Construction Drawings
15 Days
Lessor Preparation and Submission of the TI and BSAC Price Proposal
30 Days
Government Reviews and Approves Pricing
30 Days
Government Issues Notice to Proceed with Construction
1 Day
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
80 Days
Government Inspects and Accepts Finished Space
10 Days
Total Work Days from Lease Award to Government Acceptance
379 Days
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1PSA VERSION - REV (04/26)