Post Award Schedule.docx
DOCX document 2 MB Posted
- Solicitation number
- 4NJ0314
About this file
This is a Post-Award Schedule document that establishes the timeline for design, construction, and acceptance of tenant improvements for a GSA lease of office space in Woodbury, New Jersey. The schedule commences within 5 working days of lease award and outlines the sequential phases required to complete the project, culminating in government acceptance of the finished space within 379 total working days.
The schedule is organized into four primary phases: (1) Lessor-Provided Design Intent Drawings (DIDs), requiring three submission iterations at 50%, 95%, and final approval, with GSA and Agency reviews and corrections totaling approximately 66 working days; (2) Construction Documents (CDs) preparation, submission, and review in three stages at 75%, 100%, with final corrections, spanning approximately 98 working days; (3) Tenant Improvement (TI) and Building Specific Amortized Capital (BSAC) pricing proposal preparation and government approval, requiring 60 combined working days; and (4) Construction execution and government inspection, requiring 90 working days. The Notice to Proceed with Construction is issued after government approval of pricing, followed by 80 working days for lessor completion of construction and 10 working days for government inspection and final acceptance. This schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to the management of the design and construction process for the 3,506 to 3,612 USF office space lease with a 10-year term and 5-year firm period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Delineated Area Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
| Activity |
| Working Days |
Lessor-Provided Design Intent Drawings
DIDs Provided by Lessor (50%) 20 days DIDs Reviewed by GSA / Agency 13 days Lessor Provides Corrected DID's 10 days DIDs Provided by Lessor (95%) 20 days DIDs Reviewed by GSA / Agency 13 days Lessor Provides Corrected DID's 10 days
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 10 Days
| Lessor Preparation and Submission of Construction Documents |
| CDs Provided by Lessor (75%) 20 days |
CDs Reviewed by GSA / Agency 13 days Lessor Provides Corrected CDs 10 days Lessor Provides 100% 20 days Government Review 15 days Final Corrections by Lessor 10 days Final Review Government Review 15 days
| Government Review of Construction Drawings |
| 15 Days |
| Lessor Preparation and Submission of the TI and BSAC Price Proposal |
| 30 Days |
| Government Reviews and Approves Pricing |
| 30 Days |
| Government Issues Notice to Proceed with Construction |
| 1 Day |
| Lessor Completes Construction of TIs and Completion of Other Required Construction Work |
| 80 Days |
| Government Inspects and Accepts Finished Space |
| 10 Days |
| Total Work Days from Lease Award to Government Acceptance |
| 379 Days |
| AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 | PSA VERSION - REV (04/26) |
| AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 | PSA VERSION - REV (10/22) |