USCG 49413 (BUSL 49)

SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS

FY2021

Developed By: Anthony M Dowd

(Rev-0, 19 August 2020)

USCG 49413 (BUSL-49) UNPLANNED AVAILABILITY FY2021

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: U/W Body, Preserve (100%) WORK ITEM 2: Hull Plating Freeboard, Preserve “100%” WORK ITEM 3: Stern Tube Interior Surfaces, Preserve 100% WORK ITEM 4: Rudder Tubes Interior Surfaces, Preserve 100% WORK ITEM 5: Decks – Exterior (Buoy), Preserve 100 Percent WORK ITEM 6: A-Frame, Preserve 100 Percent WORK ITEM 7: Work Shelter, Temporary, Provide WORK ITEM 8: Anchor Chain Hawse Pipe, Preserve WORK ITEM 9: Deck (Foredeck), Preserve 100% WORK ITEM 10: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) WORK ITEM 11: Superstructure, Preserve 100 Percent WORK ITEM 12: Deck Covering System, Pilothouse, Renew iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 49A BUSL 114-004, Rev G, Skeg & Shaft Tube Arrangement & Details

Coast Guard Drawing 49A BUSL 171-002, Rev D, Mast Construction and Details

Coast Guard Drawing 49A BUSL 243-001, Rev G, Propulsion Shafting & Bearing Arrangement

Coast Guard Drawing 49A BUSL 562-001, Rev C, Rudder & Steering Gear Arrangement & Details

Coast Guard Drawing 49A BUSL 573-005, Rev E, Stern A-Frame Construction & Details

Coast Guard Drawing 49A BUSL 573-006, Rev E, Removable Base for A-Frame

Coast Guard Drawing 49A BUSL 581-002, Rev D, Anchor Handling Details

Coast Guard Drawing 49A BUSL 601- 003, Rev D, Outboard Profile and Main Deck

Coast Guard Drawing 49A BUSL 601-003, Rev D, Outboard Profile & Main Deck Arrangement

Coast Guard Drawing 49A BUSL 601-003, Rev D, Outboard Profile and Main Deck Arrangement

Coast Guard Drawing 49A BUSL 631- 001, Rev F, Painting Schedule

Coast Guard Drawing 49A BUSL 634- 001, Rev C, Deck Covering Schedule

Coast Guard Drawing 49A-BUSL-634-001, Rev. C, Deck Covering Schedule

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Commandant Instruction (COMDTINST) M16114.22, October 2002, 49’ Buoy Utility Stern

Loading (BUSL) Boat Operators’ Handbook

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2018, Auxiliary

Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2018, Install Interior

Deck Covering Systems v (Rev-0)

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2018, Temporary

Services

OTHER REFERENCES

MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-DTL-15562G, May 1996, Matting or Sheet, Floor Covering, Insulating for High Voltage

Application

MIL-PRF-24647, Apr 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC), Surface Preparation Standard SSPC-SP 1, November 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by

Waterjetting Prior to Recoating

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel & Other Hard

Materials by High and Ultrahigh Pressure Water Jetting

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, July 2012, Near-White Blast Cleaning vi (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

This section is not applicable to this package.

vii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

1 U/W Body, Preserve (100%) viii (Rev-0)

PRINCIPAL CHARACTERISTICS

49’ BUSL

PHYSICAL

Length overall 49’ 7”

Depth (main deck at side to baseline) N/A

Maximum beam 16’ 10”

Height of highest projection (above

DWL)

15’

Frame spacing N/A

Full load draft 5’ 7”

Full load displacement 31.65 Long tons

Shore tie voltage requirements 120v

HULL

Hull material

MACHINERY

Number of propellers 2

Number of blades per propeller 4

Diameter of propeller 31”

Pitch 22” fixed

RPM 2300

Shaft diameter N/A

TANKS

1 (Rev-0)

00000_0220_FLT

REC_00000_FLT_Boats @ CG Facility (0914)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

(Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 07.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC

Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is CG Base Detroit.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3 (Rev-0)

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Hazardous Waste Manifest. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.7 Facilities Response Plans. Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33

CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy.

3.6.1 Coast Guard facility usage and provisions. The Contractor shall be aware of the following:

3.6.1.1 Coast Guard personnel will haul and block the boat on a Coast Guard installation; consequently, the

Contractor shall not include the cost of lifting or re-floating the vessel in the bid price estimates

3.6.1.2 All work described herein is intended to be accomplished at this location.

4 (Rev-0)

3.6.1.3 The COR will submit to the Contractor a copy of the “Coast Guard Facility Survey”/”Landlord Survey” which contains utilities and/or equipment that the Coast Guard Facility will make available for use by the

Contractor.

3.6.2 Contractor equipment. The Contractor shall make arrangements to provide all other necessary equipment to accomplish the work described in this specification package including (as applicable) but not limited to generators, compressors, welding equipment, power tools, consumables, and storage containers.

3.6.2.1 The Contractor shall be responsible for storing own equipment.

3.6.2.2 Prior to setting up equipment and/or storage containers for long-term duration, the Contractor shall obtain approval from the COR at least 48 hours prior to placing the equipment in order to avoid conflict with other base activities.

3.6.3 Sewage Facilities. If the Coast Guard facility opts to provide sewage facilities (as listed on the Landlord

Survey) for use by the Contractor, the Contractor shall supply sanitary supplies such as toilet paper, paper towels, soap, etc. for use by contract personnel. Use of Government toilet paper, and other sanitary supplies shall not be authorized and the additional caveats apply as well.

3.6.3.1 The Contractor shall ensure the sanitary facilities (bathrooms) are left in a clean and neat condition as found.

3.6.3.2 The Contractor is NOT authorized to use any shower facilities which may or may not be located in the same room as the toilet facilities.

3.6.3.3 The Contractor shall adhere to any special requirements or regulations listed in the comments section of the Landlord survey forms, provided at the end of this document.

3.6.4 Coast Guard turn-over preparation. The Contractor shall be aware that, upon arrival, after haul out, and prior to departing the Contractor’s facility, the Coast Guard crew shall be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:

3.6.4.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.

3.6.4.2 The Contractor may commence/continue work during these time frames.

3.6.4.3 Coast Guard personnel will disconnect the Detroit Diesel Electronic Control (DDEC) System and any other electronic equipment, as required to avoid damage to systems arising from hotwork on the vessel during the availability.

3.6.4.4 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.

3.6.4.5 The Unit will contact the servicing ESD or ESU to setup removal/installation of the transducer if Unit personnel are unable to accomplish this task.

3.7 SFLC Standard Specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2018 Edition Standard Specifications and supersede published content:

5 (Rev-0)

None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

6 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

8 (Rev-0)

QA-3A - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

TIME

9 (Rev-0)

QA-3B - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

12 (Rev-0)

63130_0320_FLT

REC_63130_100Percent_FLT_49’ BUSL (0619)

WORK ITEM 1: U/W Body, Preserve (100%)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve U/W body surfaces.

NOTES

1. The purpose of the preservation tasks covered by this item is to completely remove all existing coatings and recoat the U/W body surfaces with a new coating system.

2. U/W body surfaces are as defined in 4.1 (Definitions) and exclude areas covered by docking blocks, unless the vessel is fleeted for the express purpose of preserving blocked areas.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 49A BUSL 601-003, Rev D, Outboard Profile and Main Deck

Arrangement

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

3. REQUIREMENTS

3.1 General.

13 (Rev-0)

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

3.2.3 Post-surface preparation cleaning and inspection

3.1.2 Tech Rep. The Contractor shall refer to SFLC Std Spec 0000, paragraphs 3.2.4.2.1 (Painting contractor certification program requirement) and 3.2.4.2.2 (Coating Tech Rep), for applicable requirements.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness. Specific areas/equipment/components to be protected include, but are not limited to:

All scuppers and overboard discharges.

Waterline area where U/W body coating system interfaces with freeboard coating system

(unless freeboard surfaces are also being preserved).

Fathometer transducer surfaces.

Sea valve openings.

Propeller shaft bearings and seals.

Rudder bearings.

Propellers.

Zinc anodes (unless anodes are being renewed).

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Sea chest grating.

3.1.5 Initial inspection. Prior to removing the existing coating system, the Contractor shall inspect and verify whether all draft marks have permanent markings (weld beads or impressions), showing their location on the hull. Submit a CFR.

3.1.6 Water used in preparation and washing procedures. The Contractor shall ensure that water used in all surface preparation tasks, including pre-surface preparation wash and water jetting, is of sufficient purity and quality that it does not prevent the surface being cleaned from achieving the required degree of surface cleanliness or non-visible contamination criteria.

3.1.6.1 Ensure that surface preparation water does not contain sediments or other impurities that are destructive to the proper functioning of the cleaning equipment.

3.1.6.2 Ensure that all water used in any surface preparation or cleaning procedures is captured, contained, and all spent water disposed of in accordance with all Federal, state and local regulations.

3.1.7 Surface preparation optional methods. The Contractor has the option of using either high/ultrahigh pressure water jetting or abrasive blasting to achieve the required surface preparation, prior to application

14 (Rev-0) of the coating system specified in 3.2 (Preservation requirements). The Contractor may add abrasives to the water jet stream, for one or both of the following reasons:

Achieving greater productivity.

Achieving the required surface profile.

NOTES

1. Existing coating system on the U/W body surfaces may have a nominal thickness in excess of that which was originally installed, because of “patch-coats” applied during past drydock availabilities.

2. Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.

3.2 Preservation requirements. The Contractor shall accomplish the following tasks:

3.2.1 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.

3.2.2 Surface preparation and coating application.

The Contractor shall accomplish the following tasks:

3.2.2.1 Prepare and coat the U/W hull surfaces with the system specified for “Underwater (U/W) Body and Boot-Top (U/W Body and Boot-Top, Icebreaker <235’, in Fresh Water (Excluding Sea Chest)” in

SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems).

3.2.2.2 Sea chest. Prepare and coat the sea chests with the system specified for “Underwater (U/W) Body and Boot-Top (U/W Body Sea Chest, Icebreaker in Fresh Water)”, in SFLC Std Spec 6310, Appendix A

(Cutter and Boat Exterior Painting Systems).

3.2.2.2 Ensure that the first AF coat is applied over the AC epoxy undercoating, while it is still tacky.

3.2.3 Post-surface preparation cleaning and inspection. After completion of surface preparation and prior to coating application, accomplish the following tasks and submit a CIR.

3.2.3.1 Perform a visual inspection of the prepared U/W body steel substrate.

3.2.3.2 Perform solvent cleaning of all prepared surfaces, in accordance with SSPC-SP 1. Capture, contain, and dispose of all wastes from solvent cleaning, in accordance with all Federal, state and local regulations..

NOTE

Lists of all authorized coating materials and suppliers are listed in SFLC Std

Spec 6310, Appendix C (Cutter and Boat Authorized Coatings).

3.2.3.2.

15 (Rev-0)

3.3 Draft mark painting. The Contractor shall paint all draft marks with two coats of a “Polysiloxane” or

“Silicone Alkyd Enamel” coating, at 2.0-3.0 mils DFT, white (17925).

3.4 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces). Surfaces being preserved are considered “critical-coated surfaces”.

4. NOTES

4.1 Definitions.

4.1.1 U/W Body. The underwater body is defined as the areas from the bottom of the keel to the waterline, as shown on Coast Guard Drawing 49A BUSL 601-003, including rudders, transducer hull rings, keel coolers, bilge keels, struts, skegs, gratings, and rope guards.

16 (Rev-0)

63140_0320_FLT

REC_63140_100Prcnt_FLT_49’ BUSL (ALL) (1215)

WORK ITEM 2: Hull Plating Freeboard, Preserve “100%”

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve 100% of the freeboard surfaces defined in 4.1 Definition of freeboard surfaces.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 49A BUSL 601-003, Rev D, Outboard Profile & Main Deck Arrangement

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

17 (Rev-0)

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.3.1 Apply protective measures as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection) to the following components, spaces and equipment:

Areas where underwater body coating system interfaces with freeboard coating system

(unless u/w body surfaces are also being preserved).

Adjacent deck surfaces and deck fittings.

Wood fenders.

Buoy Deck wood covering.

Port and starboard deck lockers.

Deck equipment.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec

0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

None.

3.2 Initial inspection. Prior to removing the existing coating system, the Contractor shall inspect and verify whether or not all hull identification numbers and letters have permanent markings (weld beads or impressions), showing their location on the hull. Submit a CFR.

3.3 Surface preparation optional methods. The Contractor shall have the option of using either high/ultrahigh pressure water Jetting or abrasive blasting to achieve the required surface preparation, prior to application of the coating system specified in 3.6 (Preservation requirements). The Contractor may add abrasives to the waterjet stream, for one or both of the following reasons:

Achieving greater productivity.

Achieving the required surface profile.

NOTE

Waterjetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.

3.4 Substrate inspection. After completing surface preparation and before coating application, the

Contractor shall perform a visual inspection of the prepared substrate, and submit a CFR.

3.5 Pre-surface preparation wash. The Contractor shall accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants.

Capture, contain, and dispose of wash water for proper disposal in accordance with all Federal, state and local regulations.

3.6 Preservation requirements. The Contractor shall accomplish the following tasks:

18 (Rev-0)

3.6.1 System particulars. Prepare and coat 100% of the freeboard surfaces as designated in paragraph 1.1

(Intent) with the system specified for “Freeboard/Superstructure/Mast (Freeboard/Superstructure)” in

SFLC Std Spec 6310. Select the following:

Select “Option II” system, for the applicable metal substrate.

Black (17038) as the top/finish coat color for all plating surfaces and stern rails and stanchions.

White (17925) for all port and starboard rails and stanchions..

3.6.2 Visual identification markings. The Contractor shall paint all distinctive visual safety and identification markings as follows:

3.6.2.1 Decals. Coast Guard Emblem decals may be substituted for painted emblems. Vinyl adhesive letters and numbers may also be substituted for painted letters and numbers - at the Contractor’s discretion.

3.6.2.2 Painted markings. Paint all distinctive visual identification markings, including the Coast Guard diagonal stripes, "U.S. COAST GUARD" legends, hull numbers, and draft marks in accordance with

SFLC Std Spec 6310, and Coast Guard Drawings FL 2804-12 and FL 2804-22 as applicable.

NOTES

Surfaces being preserved are considered “critical-coated surfaces”.

Although there may be several possible procurement sources for the Coast

Guard Emblem decals and vinyl adhesive letters and numbers, one known source is:

Brace Enterprises

10250 SE 138 Terrace

Dunnellon, FL 34431

352-489-4442 / Fax: 352-489-4476 www.braceenterprise.com

3.6.3 Tear drop. Not applicable.

3.7 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).

http://www.braceenterprise.com/

19 (Rev-0)

4.1 Definition of freeboard surfaces. For the purposes of this item the freeboard is defined as exterior steel hull surfaces from the waterline to the top of the gunwale; also included are the port, starboard, and stern steel rails and stanchions, shown on Coast Guard Drawing 49A BUSL 601-003.

20 (Rev-0)

63133_0620_FLT

REC_63133_FLT_49’ BUSL (ALL) (0819)

WORK ITEM 3: Stern Tube Interior Surfaces, Preserve 100%

WORK ITEM 1: SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve stern tube interior surfaces.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 49A BUSL 114-004, Rev G, Skeg & Shaft Tube Arrangement & Details

Coast Guard Drawing 49A BUSL 243-001, Rev G, Propulsion Shafting & Bearing Arrangement

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface

Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP

11), 2012, Power-Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface

Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of

Metals by Waterjetting Prior to Recoating

21 (Rev-0)

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.3.1 Apply protective measures as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection) to the following components, spaces and equipment:

Stern tube flange surfaces.

Engine Room.

Bearings and bearing housings.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Propellers.

Line cutters (if applicable).

Shaft zincs (if applicable).

Shaft seal assembly.

Drive-saver.

3.2 Preservation requirements. Using Coast Guard drawings 49A BUSL 114-004 and 49A BUSL 243-001 as guidance, the Contractor shall preserve 100% of the interior tube surfaces as follows:

3.2.1 The Contractor shall not prepare or coat waterborne bearing contact areas inside the stern tube. This includes bearing lands, areas in contact with bearing shell, areas in contact with Cutless type bearings, etc.

These areas shall remain uncoated to provide required fits.

3.2.2 Surface preparation. The Contractor shall prepare surfaces by waterjetting to a SSPC-SP 12/NACE

No. 5, WJ-2/L standard, or by one or a combination of the surface preparation methods described in Table

1:

TABLE 1 – SURFACE PREPARATION

ABRASIVE BLASTING MECHANICAL CLEANING

22 (Rev-0)

Abrasive-blasting to SSPC-SP10/NACE No. 2, using grit conforming to MIL-A-22262 (1.5 to 2.5 mil anchor profile).

Power tool cleaning to a SSPC-SP 11 (1.0 mil anchor profile).

3.2.3 Inspection. After surface preparation and before coating application, the Contractor shall perform a visual inspection of the prepared stern tube surfaces, and submit a CFR.

3.2.4 Surface coating. The Contractor shall prime and coat the prepared surfaces with two coats of a

“High Turbulence Coating”, at 5.0-6.0 mils DFT each.

NOTE

List of authorized suppliers for “High Turbulence Coatings” is provided in

SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.2.5 In-process quality control. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for

“critical-coated surfaces").

NOTE

Surfaces being preserved are considered “critical-coated surfaces”.

This section is not applicable to this work item.

23 (Rev-0)

56120_AKP_1119_49BUSL

WORK ITEM 4: Rudder Tubes Interior Surfaces, Preserve 100%

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve rudder tube interior surfaces.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 49A BUSL 562-001, Rev C, Rudder & Steering Gear Arrangement &

Details

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-PRF-24647, Apr 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface

Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP

11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface

Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of

Metals by Waterjetting Prior to Recoating

24 (Rev-0)

3.1.1 CIR.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness. Specific equipment/components include, but are not limited to:

Rudder flange surfaces.

Lazarette.

Bearings and bearing housings.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Preservation requirements. Using Coast Guard Drawing 49A BUSL 562-001, Rev C as guidance, the

Contractor shall preserve 100% of the interior tube surfaces as follows.

3.2.1 The Contractor shall not prepare or coat waterborne bearing contact areas inside the stern tube. This includes bearing lands, areas in contact with bearing shell, areas in contact with bearings, etc. These areas shall remain uncoated to provide required fits.

3.2.2 Surface preparation. The Contractor shall prepare surfaces by waterjetting to a SSPC-SP 12/NACE

No. 5, WJ-2/L standard, or by one or a combination of the following surface preparation methods:

TABLE 1 – SURFACE PREPARATION

ABRASIVE BLASTING MECHANICAL CLEANING

Abrasive-blasting to SSPC-SP10/NACE No. 2, using grit conforming to MIL-A-22262 (1.5 to 2.5 mil anchor profile).

Power tool cleaning to a SSPC-SP 11 (1.0 mil anchor profile).

3.2.3 Inspection. After surface preparation and before coating application, the Contractor shall perform a visual inspection of the prepared stern tube surfaces, and submit a CFR.

3.2.4 Surface coating. The Contractor shall prime and coat the prepared surfaces with two coats of a

“High Turbulence Coating”, at 5.0-6.0 mils DFT each.

NOTE

List of authorized suppliers for “High Turbulence Coatings” is provided in

SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

25 (Rev-0)

3.3 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).

NOTE

Surfaces being preserved are considered “critical-coated surfaces”.

26 (Rev-0)

63121_AKP_1119_49BUSL

WORK ITEM 5: Decks – Exterior (Buoy), Preserve 100 Percent

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve the Buoy Deck surfaces and apply slip resistant (non-skid) pads.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 49A BUSL 631- 001, Rev F, Painting Schedule

Coast Guard Drawing 49A BUSL 634- 001, Rev C, Deck Covering Schedule

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC), Surface Preparation Standard SSPC-SP 1, November 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface

Preparation Standard SSPC-SP 10/NACE No. 2, July 2012, Near-White Blast Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

27 (Rev-0)

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work.