47PL0224A0005 Amend 001.pdf
PDF 1015 KB Posted
- Solicitation number
- 47PL0224Q0005a
About this file
This document is an Amendment 001 to a Request for Quote (RFQ) for interior signage at the Seattle and Tacoma courthouses. The amendment provides responses to pre-proposal inquiries, including clarification that the existing signs should be matched in material, font, and engraving, and that no removals are required. The signage quantities are specified as 110 plaque signs and 2 aluminum FCOs for Seattle, and 110 brass plaques, 2 brass letter FCOs, and 2 oak wood cabinets for Tacoma. The work is subject to prevailing wages, but no permits or bonds are required. Background checks will be conducted on the awardee. The contractor is responsible for developing the mounting method. The proposal due date remains 04/08/2024, 5pm EDT.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Scope of Work Interior Signage at CHs 21March2024.pdf | ||
| RFQ 47PL0224Q0005 dated 03252024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Quote (RFQ) 47PL0224Q0005
Interior Signage for Seattle and Tacoma Courthouses
AMENDMENT 001
This Amendment 001 is being issued to provide responses and photographs to pre-proposal inquiries (PPIs).
The proposal/quote due date of 04/08/2024, 5pm EDT is unchanged with this Amendment.
PPI responses and photos are provided below.
Pre-Proposal Inquiries for RFQ 47PL0224Q0005
Interior Signage at Courthouses (Seattle and Tacoma, WA)
Question 01: Are the photos of the name plates/signs (shown in SOW photos) “standard”? Please provide photos of existing nameplates.
Response 01: The signs and the plates need to be the same as is what is existing and in the photos, so yes, they are considered standard. The material, font, how their engraved, etc. must be the same. 3 photos provided below.
Question 02: Can you specify if Removal is in the Scope of Work? If yes, can existing sign pictures be provided?
Response 02: No removals are required.
Question 03: Is this subject to Prevailing Wages?
Response 03: Yes
Question 04: Is a permit required?
Response 04: No.
Question 05: Is there any kind of Bond required? (i.e. Bid Bond, Performance Bond)
Response 05: No.
Question 06: Will there be Background Checks be required after the award?
Response 06: Yes
Question 07: Please specify the Mounting methods of the signage required?
Response 07: The contractor will be responsible for developing the mounting method. It is expected that the signs will be mounted to cleats that are firmly attached to studs.
Question 08: Can you confirm the Counts of the signs required for Seattle Courthouse Signs and Tacoma Union Station Signs?
Response 08: ***Seattle Courthouse Signs
- Plaque Signs QTY:110
- Aluminum FCOs QTY: 2
***Tacoma Union Station Signs
- Brass Plaques QTY:110
- Brass Letter FCOs QTY: 2
- S/F Oak wood cabinet QTY:2
Question 09: Please specify which artwork to be followed for "Plaque Signs" and "Brass Plaques"?
There are two artworks provided for each sign.
Response 09: Refer to the scope of work and the photos provided.
Queston 10: Are there any license requirements for this RFQ?
Response 10: Yes, awardee shall be a licensed contractor.
End