This document provides a summary scope of work for a design-build project to upgrade the building envelope at the Pacific Highway Land Port of Entry located in Blaine, Washington. The General Services Administration intends to utilize a two-phase design-build selection procedure with a best value tradeoff source selection method considering technical factors and price. Interested small businesses, 8(a), HUBZone, service-disabled veteran-owned, or women-owned small businesses are invited to respond with relevant project experience, business size and socio-economic status, and bonding capacity by March 11, 2020. If the project proceeds, the solicitation is estimated to award a firm-fixed price contract between $14-18 million in November 2020 to replace exterior walls and roofs, install waterproofing, improve insulation, and handle any biological growth at the port of entry's two buildings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IndustryOutreachSourcesSought QuestionnairePacHwy Envelope.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: Design Build Pacific Highway LPOE Envelope Upgrade, Blaine WA
Summary of Scope:
The Pacific Highway (Hwy) Land Port of Entry (LPOE), located in Blaine WA, sits on an
11.8 acre site and consists of two buildings – the Auto/Bus and the Commercial/Warehouse buildings.
The Port, which was expanded and renovated in 1999, is the main commercial port of entry between the State of Washington and British Columbia, Canada, and is operated by US Customs and Border Protection (CBP). The LPOE facilities house several different Federal agencies responsible for protecting the border and facilitating border crossings. The LPOE operates 24/7/365.
The Auto/Bus building is a single-story automotive and bus processing building with 30,418 gross square feet (GSF). The Commercial/Warehouse building is a three-story commercial inspection and administration/head-house building, with an attached single- story Warehouse wing/building. The Commercial/head-house building and the Warehouse were originally constructed as separate buildings in 1999; however, a subsequent project, completed in approximately 2005, connected the two structures via a multi-story breezeway. The Commercial/Head-house building totals 67,013 GSF, and the Warehouse is estimated at 19,700 GSF.
Almost immediately after construction completion and initial occupancy back in 1999, the facilities started exhibiting signs of moisture infiltration and resultant water damage to varying degrees through the exterior envelopes of each of the Port’s buildings. As a result, GSA Region 10 has conducted several successive investigations and studies, along with some limited/spot repairs, over the ensuing years to document the infiltration and to determine possible root causes. The culmination of these efforts was a Project Development Study (PDS) that was completed in early 2016, the end result of which is this PacHwy Envelope Upgrade project.
Previous studies and investigations have revealed the presence of biological growth at the LPOE buildings, including, but not necessarily limited to, within the exterior envelope cavities, windows and doors, and interior surfaces.
The Design Build Project intent is to install a new exterior wall system and roof, and improve energy performance, at the LPOE’s two existing buildings; the Auto/Bus and Commercial/Warehouse buildings.
The exterior envelope (walls and roof) is to be replaced to stop water intrusion, and the scope involves the deconstruction and reconstruction of exterior walls and roofs, installation of waterproof materials, and improvements to the underlying insulation. While the exterior envelope is repaired, any biological growth encountered is to be handled according to appropriate removal and disposal procedures. This project may, as a result of the envelope repairs, also impact multiple building systems, including but not limited to: electrical; mechanical; plumbing; fire protection; HVAC, adjacent interior walls and finishes;
and security (IDS) systems. After envelope repairs are complete, the HVAC system will be tested and re-balanced to reflect the effects of the repaired envelope and provide efficient operations as a result.