This document is a solicitation for the USSS DAV Secure Parking Area project. The solicitation is for converting assigned parking spaces into a fully screened secure parking area at the Robert T. Matsui Federal Building located in Sacramento, CA. The scope of work includes providing all labor, supervision, materials, and equipment necessary to install two bi-parting sliding door systems, a pedestrian entrance, conduit and wiring for future CCTV and access control systems, additional lighting, electrical outlets, and water access. The solicitation number is 47PK0524R0066 and the solicitation closes on October 30, 2024 at 4:00 am (PST). A mandatory site walk is scheduled for October 9, 2023 at 10:00 am. The contract will be awarded on a firm fixed price basis. The work is to be completed within 180 days after the notice to proceed is issued.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date:

PROJECT TITLE: USSS DAV Secure Parking Area

SOLICITATION NUMBER: 47PK0524R0066

SOLICITATION CLOSES ON: Wednesday, October 30, 2024 at 04:00 am (PST).

Offers must be submitted by this date and time.

SUBMIT BIDS/OFFERS TO: David Furukawa

Contracting Officer david.furukawa@gsa.gov

619-892-1050

FOR INFORMATION ON THIS PROCUREMENT, CONTACT:

Timothy Day timothy.day@gsa.gov

(916) 212-7373

ITEMS OR SERVICES TO BE PURCHASED:

Provide all labor, supervision, materials, and equipment necessary to convert assigned parking spaces into a fully screened secure parking area. The space will have two bi-parting sliding door systems, a pedestrian entrance, and the conduit & wiring to provide infrastructure for a future CCTV & access control system. The project also includes additional lighting, electrical outlets, and water access. Work to be done at the Robert T. Matsui Federal

Building located at 501 I Street, Sacramento CA 95814.

Basis of Award: Price

SIGNIFICANT EVENTS/DATES:

SITE WALK IS MANDATORY FOR THIS CONTRACT; Wednesday, October 09, 2023 at 10:00 am. Please meet in Lobby of the Robert T. Matsui Federal Building located at 501 I Street, Sacramento CA 95814. Contact Timothy Day at timothy.day@gsa.gov to RSVP for the site walk and with questions about the project.

The site walk is mandatory in order to submit a proposal for this project.

SUBMISSION OF QUESTIONS/ RFIs: questions must be submitted by Friday, October 18, 2024. Submit all questions to: David Furukawa, david.furukawa@gsa.gov, Timothy Day, timothy.day@gsa.gov and Janette Bair, janette.bair@gsa.gov

Docusign Envelope ID: A94B0B29-C697-41B2-83C1-A02DED976170

9/25/2024

PROPOSALS: Proposals are due on Due Date at time. Proposals must include:

● Signed SF1442

● Detailed price breakout per scope of work (including subcontractor(s)’s quotes with proper material and labor breakdown)

● Sufficient drawings, specifications, or notes, and calculations shall be prepared by the contractor to show the extent of work being performed.

● Offeror Representations and Certifications (check all boxes) Signed

CONTRACT AWARD DATE: To be Determined.

Sincerely, David Furukawa, Contracting Officer

Docusign Envelope ID: A94B0B29-C697-41B2-83C1-A02DED976170

Table Of Contents

Section Description Page Number Section A Solicitation Form 1 Section B Schedule 15 Section C Clauses 61

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

47PK0524R0066

GSA, PBS R9, Acquisition Management Division Simplified Acquisitions Br, San Francisco Sect, 9PQAF 50 United Nations Plaza, Mailbox 9 San Francisco, CA 94102 USA

Scope of Work: USSS DAV Secure Parking Area dated 8/21/2024

9PQAF

GSA, PBS R9, Acquisition Management Division Simplified Acquisitions Br, San Francisco Sect, 9PQAF 50 United Nations Plaza, Mailbox 9 San Francisco, CA 94102 USA

EQ9PFN-24-0082

9PQAF

Janette Bair 619-610-4176

N3401787

1 39/24/2024

10/30/2024

1 4:00 PM (PST)

47PK0524R0066, Section A Page 1

JanetteLBair Typewritten Text

JanetteLBair Cross-Out

JanetteLBair Highlight

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

9PQAF

GSA, PBS R9, Acquisition Management Division Simplified Acquisitions Br, San Francisco Sect, 9PQAF 50 United Nations Plaza, Mailbox 9 San Francisco, CA 94102 USA

PBS PAYMENTS BRANCH

P.O. BOX 17181

https://finance.ocfo.gsa.gov/

FORT WORTH, TX 76102-0181 USA

David Furukawa

47PK0524R0066, Section A Page 2

JanetteLBair Highlight

JanetteLBair Highlight

JanetteLBair Highlight

JanetteLBair Highlight

JanetteLBair Highlight

JanetteLBair Highlight

PAGE

GENERAL SERVICES ADMINISTRATION

OF

ITEM NO.

(a)

SUPPLIES OR SERVICES

(b)

QUANTITY

ORDERED

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

0001 __________

__________1

LSUSSS DAV Secure Parking Area

Provide all labor, supervision, materials, and equipment necessary to convert assigned parking spaces into a fully screened secure parking area. The space will have two bi-parting sliding door systems, a pedestrian entrance, and the conduit & wiring to provide infrastructure for a future CCTV & access control system. The project also includes additional lighting, electrical outlets, and water access. Work to be done at the Robert T. Matsui Federal Building located at 501 I Street, Sacramento CA 95814.

All work must be done in accordance with the scope of work titled "USSS

DAV Secure Parking Area" dated 8/21/2024

Construction wage rates are attached and apply to this contract. They will be updated at award if they change, and the latest rates are publicly available on SAM.gov.

Deliverable

PSC: Z2AA -- REPAIR OR ALTERATION OF OFFICE BUILDINGS

Contract Type: Firm Fixed Price

PoP: 11/12/2024 - 06/14/2025

Place of Performance:

CA0306ZZ ROBERT T MATSUI US COURTHOUSE 501 I ST

SACRAMENTO, CA 95814-7300

47PK0524R0066, Section A Page 3

JanetteLBair Highlight

3401787, DAV Secure Parking Area SF CA0306ZZ 8/21/2024

U.S. GENERAL SERVICES ADMINISTRATION

SAN FRANCISCO SERVICE CENTER

SACRAMENTO FIELD OFFICE

SPECIFICATIONS

For

United States Secret Service

USSS DAV Secure Parking Area

Robert T. Matsui Federal Courthouse 501 I St

Sacramento, CA 95814

Table of Contents

1.0 GENERAL

1.1 DESCRIPTION

1.2 POINTS OF CONTACT

1.3 USE OF SITE

1.4 QUALITY ASSURANCE

1.5 PROJECT COMPLETION PERIOD

2.0 PRODUCTS

2.1 SCHEDULE SUBMISSION

2.2 SECURITY CLEARANCE REQUIREMENTS AND INFORMATION

3.0 CODES AND STANDARDS

3.1 WORKING HOURS

3.2 CLEAN-UP OPERATIONS

4.0 GOVERNMENT OCCUPANCY

5.0 ROLES AND RESPONSIBILITIES

5.1 GOVERNMENT PARTICIPATION IN THE PROJECT PROCESS

6.0 SAFETY AND HEALTH

6.1 CONSTRUCTION PAYMENTS

7.0 WARRANTY

8.0 EXHIBITS

47PK0524R0066, Section A Page 4

U.S. GENERAL SERVICES ADMINISTRATION

SAN FRANCISCO SERVICE CENTER

SACRAMENTO FIELD OFFICE

SUMMARY OF WORK

1.0 GENERAL

1.1 DESCRIPTION

The location of this project is the Matsui Federal Courthouse at 501 I St, Sacramento, CA 95814.

The purpose of this project is to provide labor, materials, and equipment to convert assigned parking spaces into a fully screened secure parking area. The space will have two bi-parting sliding door systems, a pedestrian entrance, and the conduit & wiring to provide infrastructure for a future CCTV & access control system. The project also includes additional lighting, electrical outlets, and water access.

The building is owned by the Federal Government, and it is not subject to the requirements of the local Building Department. However, all local, state and federal codes need to be followed. The Contractor shall be responsible for the provision of design documents and calculations as required to illustrate and explain the proposed work. The contractor shall furnish adequate supervision, labor, materials, supplies and equipment necessary to perform all service required under this contract in an orderly, timely and efficient manner.

Unless otherwise indicated, items of work are inclusive of, but not limited to, all labor, materials, equipment, traffic control, safety measures, replacement of disrupted improvements, coordination, preparation and accommodation of project constraints (whether specifically identified in these specifications or encountered during the contract) necessary to complete the item in conformance with all applicable governing agency regulations and specifications to the satisfaction of the Government and inspecting agency. Items of work that are necessary to complete the project in accordance with the plans and specifications if any, but that are not specifically called out in the Schedule of Unit Prices, are considered incidental to the project and are not subject to separate compensation.

The project requirements include all engineering, programming, labor, testing, and cleanup.

Proposal The contractor's proposal should include pricing for all items listed below as well as any item the contractor believes will be needed to complete this project. The proposal will need to include a line item break out of pricing for each item listed below.

47PK0524R0066, Section A Page 5

Work Requirements – The contractor shall:

1. Provide detailed design drawings for the entire scope of work, including:

a. Layout and specifications for the secure fencing area.

b. Placement and specifications for the entrance & exit bi-parting door systems and pedestrian gate with striping designations.

c. Electrical and plumbing schematics.

d. Locations and specifications for the security features.

e. Submit design drawings for approval before commencing work. Provide design drawings in both PDF and DWG formats.

f. Provide as-built drawings following project completion.

2. Install Secure Fencing Area

a. Fencing - Install a floor-to-deck secure fencing area made of welded plate square tubing. The fencing shall be fully screened with 100% opaque cloth or similar-type mesh to completely prevent visibility from outside the parking area. Screening must be pulled tight and secured with metal hardware.

b. Doors and Gates - All DAV garage doors and vehicle gates shall be rated for outdoor and heavy use.

i. Bi-parting Doors - Install two bi-parting sliding doors systems. Each bi-parting door system shall have two 8’ doors to provide full coverage of the entrance and exit space. Bi-parting doors shall be manually operated.

Gate locks shall contain cylinders to house Medeco M3 interchangeable cores. The agency is responsible to provide cores & keys. Bi-parting doors shall have a vertical cover plate to prevent visibility into the area between bi-parting doors. Install curbing for space 75A to prevent vehicle from parking too close to the open bi-parting gate.

ii. Pedestrian Gate - Install a pedestrian gate for access on the south side of gate enclosure. Cover the pedestrian gate with a vertical cover plate to prevent visibility into the area. Install an outlet box for a card reader/keypad. Install a Yale 8800 Series electric door mortise; exact model TBD by the agency. Location and box size of the security features to be determined by the agency.

c. Electrical

i. Control Wiring Conduit - Install conduit and control wiring to support 8 exterior cameras, access control equipment at pedestrian gate, and 3 PIRs. Provide octagonal back boxes to support camera mounting locations. Utilize metal conduit for control wire for cameras and access control equipment to safeguard the integrity and functionality of the systems transmission reliability and protection against direct access.

Wiring requirements to be determined by the agency. Ensure proper sealing and protection of conduit against environmental factors. Control wiring shall be run within conduit from the secure storage area, across parking garage, up the applicable data closet into the agency space. Final termination location TBD by agency POC.

ii. Electrical Power – Provide 4 dedicated 20A circuits with lockout at the Sub-Level 1 Electrical Panel and run cable within conduit from panel to Sub-Level 2 vehicle storage area. Terminate power in local panel box mounted to ESS Wall.

iii. Electronic Security System (ESS) Wall - This wall will be used to mount all ESS equipment and be the central termination point for all ESS related wiring and conduit for the secure storage Access Control System (ACS), Intrusion Detection System (IDS) and Video Management System (VMS)

47PK0524R0066, Section A Page 6 equipment. This wall will be the location for the fiber cable enclosure and connection from the garage to the agency space.

1. Install fire resistant ¾” plywood to garage structure for the ESS wall; to fit equipment.

2. Provide and install three outdoor rated Hoffman model A- 242410LP boxes and one AL600ULXPD16CB power supply to the ESS equipment wall.

3. Provide and install 3 fourplex wall 5-20R outlets on ESS wall, exact location TBD by agency.

4. Provide and install a 12 strands fiber cable from the ESS wall to the agency ESS wall; in compliance with USSS CIO specifications. The fiber cable between the DAV garage area and the agency will facilitate data transfer for the ACS, IDS and VMS and terminate in an outdoor rated fiber cable. All fiber optic cables shall be either armor jacketed or protected in “inner duct”.

iv. Install electrical outlets - Install four 20A 110V duplex outlets with housings within the secure parking area for vehicle use tied into the storage area panel on the ESS wall.

v. Lighting - Relocate two existing building parking lights to outside the fenced area. Existing lighting shall remain connected to building lighting system. Install three new LED ceiling lights suitable for parking space illumination within the fenced area with two switches to control all interior lighting.

d. Plumbing - Water Line Extension - Tie into the existing water line and extend it to provide a hose bib within the secure parking area.

e. Parking Lot Striping - Re-stripe the parking lot within the cage. Coordinate with the agency to determine the exact layout and dimensions of the new parking stalls.

Provide striping outside the bi-parting doors delineate No Parking.

Full compensation for providing all labor, materials, tools and equipment necessary to meet the above requirements shall be considered included in the contract price and no additional compensation shall be allowed therefore.

1.2 POINTS OF CONTACT

Name Role Building/Agency Office Cell Tim Day Project Manager 650 Capitol Mall/GSA (916) 498-5366 (916) 212-7373 Alisha Decena Building Manager 501 I St./GSA (916) 498-5360 (916) 216-7858

1.3 USE OF SITE

Limit use of the premises to the immediate work area. Do not disturb portions of the Federal Building beyond the immediate work area. The contractor must repair or replace damage to existing site features caused by construction. Protect the building during the construction period. Keep driveways, loading docks, elevators, elevator entrances, and building entrances clear. These areas are not authorized for parking or material storage without permission. Contractor will schedule deliveries to minimize on-site storage of materials and equipment. The contractor shall designate a representative to receive building materials. Government personnel are not authorized to receive shipments or deliveries upon behalf of a construction contractor.

47PK0524R0066, Section A Page 7

Work in the Federal Office Buildings will require coordination with a GSA representative. Please contact him/her to coordinate arrangements upon behalf of the project.

1.4 QUALITY ASSURANCE

The contractor shall designate a specific individual as a project/contract manager. The project manager or approved designate will be on site during the time work is performed on this contract.

1.5 PROJECT COMPLETION PERIOD

The work of the project must be completed within 180 days after the notice to proceed (NTP) is issued by the Contracting Officer. The NTP will not be issued until all bonds and insurance has been collected and all security clearances have been processed.

Completion of work is herein defined as follows: All work specified shall be fully completed per the plans and specification and accepted by the governing agencies, all certifications, as-built plans, and guarantees are submitted to the Government.

The working days specified shall be inclusive of all construction windows, utility energizing, punch list buy-off and final acceptance of all facilities.

The project work shall not be considered complete until these items have been addressed. They are:

a. Published punch-list work items must be corrected in a manner acceptable to the Government.

b. As-built drawings (both CAD and PDF) and operations manuals must be made available to the Government.

c. The final payment request accompanied by a release of claims form must be made available to the Government.

2.0 PRODUCTS

The work of this project shall be constructed of new products delivered to the job site in their original unopened, undamaged containers. Provide only products manufactured or specifically recommended to match existing installed components.

Whenever available, products, equipment and materials utilized and installed under this statement of work shall comply with the following energy efficient and eco-friendly standards:

a. Energy-efficient (ENERGY STAR® or Federal Energy Management Program (FEMP)-designated);

b. Water-efficient;

c. Biobased;

d. Environmentally preferable (e.g., EPEAT-registered, or non-toxic or less toxic alternatives);

47PK0524R0066, Section A Page 8

e. Non-ozone depleting; and/or

f. Made with recovered materials.

GSA purchases for products and services must meet sustainable product requirements. Every contractor shall comply with these sustainable product requirements by using products that meet the criteria and standards listed in the PBS Sustainable Product Requirements document at the time of contract award, and or exercise of option modification. The contractor is also responsible for providing sufficient documentation to confirm that the products provided have the required sustainable criteria, upon the Government's request. See attached PBS Sustainable Products Requirements List.

2.1 SCHEDULE SUBMISSION

The contractor shall submit a schedule regarding the work of this project to the Government for review and approval before the work of this project shall begin and shall provide updated schedules due to any changes.

2.2 SECURITY CLEARANCE REQIREMENTS AND INFORMATION

The agency requires all contractors to be US Citizens. The contractor shall submit a completed Contractor Information Worksheet (CIW) for each employee working on the project to the Zone-D Credentialing Office. In addition, a Requesting Official worksheet must be filled out with each employee working on the contract and sent to the Project Manager for verification. The forms will be provided by the Project Manager, along with further guidance on submittal procedures.

It is the contractor’s responsibility to verify the forms are completed correctly, properly endorsed and dated, and they contain the necessary fingerprint forms. Please note recent history suggests the evaluation of the forms by the Defense Homeland Security Agency (DHS) requires a minimum of nine working days. The actual evaluation time is a function of DHS’s workload. Submit the forms a suitable period in advance of the actual start of work in order to maintain the projected construction schedule. Only those individuals who receive a favorable security response from a DHS will be allowed to work on the project. The submitted security clearance information is maintained in the strictest confidence, and once a favorable report is provided it is valid for a five-year period.

3.0 CODES AND STANDARDS

The contractor shall be responsible for the delivery of a completed project that is operational for its intended use by the building tenants and visitors, fits with its building context and its systems, and its surrounding environment.

The work of this project shall conform to the following codes. They are:

P-100 Facility Standards for the Public Building Service (GSA) UBC Uniform Building Code UL Underwriter’s Laboratory NEC National Electrical Code UMC Uniform Mechanical Code NFPA National Fire Protection Association Title-24 Accessibility Standards, State of California ASHRAE American Society of Heating, Refrigerating and Air Conditioning ADA American Disabilities Act

47PK0524R0066, Section A Page 9

3.1 WORKING HOURS

The normal hours of operation of this Federal Building are 7:00 AM to 5:00 PM, Monday through Friday, unless stated otherwise. A majority of the work requirements of the project may be scheduled during the building’s normal hours of operation. Work necessitating loud noise, hot work, or power outages will be performed outside of normal working hours. The parking lot may be available for contractor use and staging during that time period but must be scheduled with the Project Manager in advance.

3.2 CLEAN-UP OPERATIONS

The project site must be left in a clean condition at the conclusion of each work shift to the satisfaction of the tenant and\or Governing Agencies, whichever is more stringent. Once the project has been completed and accepted by the Government, the project site must be thoroughly cleaned and ready for occupancy or use. Contractor shall employee green cleaning practices whenever possible. Payment for final cleanup shall be considered as included in the various contract items and no additional compensation will be allowed therefore.

4.0 GOVERNMENT OCCUPANCY

Please note the Government will occupy the Federal Building throughout the entire period of construction.

Cooperate fully with the Government representatives during construction operations to minimize conflicts with normal building operations. Circulation within corridors and access to elevators, stairwells, use of occupancy of office suites, and access to the parking lots shall be maintained. Provide necessary barricades, construction tape, and temporary signage as required to define the project site and redirect circulation flow as conditions require.

5.0 ROLES AND RESPONSIBILITIES

The contractor shall be required to coordinate the current project with other ongoing construction activities at the site.

Coordinate with property manager construction work that may generate noise, airborne debris, and odors within adjacent occupied areas. Do not proceed with such work until the project representatives grant approval for such operations. Disruptive construction operations must be conducted before or after standard business hours.

Coordinate seventy-two hours in advance with the project representatives’ disruption of building systems and utilities. Disruptions to these building elements shall be accomplished before or after normal business hours, and restoration of service must be made not later than two hours before the resumption of the next business day.

Contractor shall submit a list of subcontractors to be used for this project.

Supervision: Contractor shall supervise and direct the efficient performance of the Work in accordance with Contractor's best skill, attention and judgment. Contractor shall be solely responsible for the means, methods, techniques, sequences and procedures of construction and shall be responsible to see that the finished Work complies fully and completely with the Contract Documents.

Labor and Workmanship: Where the Contract Documents refer to particular construction means, methods, techniques, sequences or procedures, or indicate or imply that such are to be used on the Work, such mention is intended only to indicate that the operations of Contractor shall be such as to produce the quality of work implied by the operations described, but that the actual determination of whether the

47PK0524R0066, Section A Page 10 described operations may be safely or suitably employed on the Work shall be the responsibility of Contractor, who shall notify the Government in writing of the actual means, methods, techniques, sequences or procedures which will be employed on the Work, if they differ from those mentioned in the Contract Documents. All loss, damage or liability, or cost of correcting defective work arising from the employment of any construction means, methods, techniques, sequences or procedures, shall be borne by Contractor, notwithstanding that such construction means, methods, techniques, sequences or procedures are referred to, indicated in or implied by the Contract Documents. Contractor shall at all times enforce strict discipline and good order among its employees and shall not employ on the Work any unfit person or anyone not skilled in the task assigned to him.

Materials and Equipment: All materials and equipment incorporated into the Work shall be new, unless otherwise specifically provided in the Contract Documents. Materials and equipment not otherwise designated by detailed specifications shall be of the best commercial quality and shall be suitable for the purpose intended. If required by the Government Contractor shall furnish evidence satisfactory to Government as to the kind and quality of materials and equipment. Any material specified by reference to the number, symbol or title of a specific standard such as that of the American Society for Testing Materials (ASTM), a Product or Commercial Standard, Federal Specification or other similar standards, shall comply with the requirements of the dated revisions stated in the Specifications, or where the Specifications contain no revision date, shall comply with the requirements of the latest revision thereof and any supplement or amendment thereto in effect on the date of receipt of bids. The standards referred to, except as specifically modified in the Specifications, shall have the same force as if they were printed in full context within the Specifications.

Manufacturers' Instructions: All materials and equipment shall be applied, installed, connected, erected, used, conditioned and cleaned in accordance with the instructions of the respective manufacturer, fabricator or processor, unless otherwise expressly provided in the Contract Documents.

Substitute Materials or Equipment: In the event the Specifications or applicable law, ordinances, rules or regulations permit Contractor to furnish or use a substitute equal in quality to any material or equipment specified, and in the event Contractor wishes to furnish or use any such substitute, Contractor shall, prior to the commencement of construction of the Work, make written application to the Government for approval of such a substitute:

a. Certifying in writing that the proposed substitute will perform adequately all functions called for by the general design, will be similar and of equal substance to that specified and will be suited to the same use and capable of performing the same function as that specified;

b. Stating whether its incorporation in or use in connection with the Project is subject to the payment of any license fee or royalties; and

c. Identifying all variations of the proposed substitute from that specified and indicating available maintenance service. No substitute whatsoever shall be ordered or installed without the prior written approval of the Government, which approval the Government may give or withhold in its sole discretion and which approval the Government may condition upon Contractor's furnishing such other data about the proposed substitute as the Government may consider pertinent and such performance guaranties and bonds as the Government may require, all at Contractor's sole cost and expense.

Provide protection for existing items to remain within work areas.

47PK0524R0066, Section A Page 11

Properly dispose of all solid, liquid, and gaseous contaminants in accordance with all local codes and regulations. Comply with all applicable local and state laws, ordinances, and regulation regarding noise control.

5.1 GOVERNMENT PARTICIPATION IN THE PROJECT PROCESS

The Government will participate in the project process in these respects. They are:

a. Review materials submitted by the contractor.

b. Inspect work in progress and convey notice of deficient work items to the Contractor in writing.

c. Provide a final inspection and a final acceptance of the work.

d. Process construction progress (when applicable) and final payments in accordance with contract requirements.

6.0 SAFETY AND HEALTH

All work shall comply with the applicable requirements of 29 CFR 1910/1926 and 40 CFR 761. All work shall comply with applicable local building codes and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.

The contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work and shall hold the Government harmless for any action on its part or that of its employees or subcontractors that result in illness or death.

The contractor shall provide all necessary safety equipment and ensure that such equipment and all relevant safety procedures are adequate for contract performance.

6.1 PROJECT PAYMENT

Typically, one payment is made at completion of the project. If this is not adequate, please request progress payments from the contracting officer during the proposal phase of the solicitation. Progress payments will be approved on a case-by-case basis.

7.0 WARRANTY

The contractor warrants materials supplied and work provided under this contract are free from defects.

The contractor shall remedy at his expense any failure to conform to the specifications, defects in material, and unacceptable workmanship. This warranty shall continue for a period of 1 year from the date of final project acceptance.

8.0 EXHIBITS

1. Work Area Diagram

End of Document

47PK0524R0066, Section A Page 12

Scope of work provided by:

Austin Schneider / GSA Project Manager

Signature

Date

Scope of work approved by:

Steven Robin / USSS Administrative Operations Division (AOD)

Signature

Date

47PK0524R0066, Section A Page 13

8.0 WORK SITE PLAN

8/20/2024

USSS SECURE FENCE PARKING

3401787

MATSUI FEDERAL COURTHOUSE

501 I ST, SACRAMENTO, CA

Bi-Parting

Doors

Pedestrian

Gate

Bi-Parting

Doors Space 75A

Curbing

ESS

Wall

Bi-Parting

Door H/H

Rail Spt Post

Legend

Approx

Enclosure

47PK0524R0066, Section A Page 14

PAGE

GENERAL SERVICES ADMINISTRATION

OF

ITEM NO.

(a)

SUPPLIES OR SERVICES

(b)

QUANTITY

ORDERED

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f) publicly available on SAM.gov.

Work to be done at the Robert T. Matsui Federal Building updated at award if they change, and the latest rates are necessary to convert assigned parking spaces into a fully additional lighting, electrical outlets, and water access.

PoP: 11/12/2024 - 06/14/2025

Provide all labor, supervision, materials, and equipment

Contract Type: Firm Fixed Price rates are attached and apply to this contract. They will be

CCTV & access control system. The project also includes

DAV Secure Parking Area dated 8/21/2024 Construction wage

USSS DAV Secure Parking Area the conduit & wiring to provide infrastructure for a future

PSC: Z2AA -- REPAIR OR ALTERATION OF OFFICE BUILDINGS

Deliverable bi-parting sliding door systems, a pedestrian entrance, and

LS

be done in accordance with the scope of work titled "USSS located at 501 I Street, Sacramento CA 95814. All work must screened secure parking area. The space will have two

47PK0524R0066, Section B Page 15

"General Decision Number: CA20240007 09/13/2024

Superseded General Decision Number: CA20230007

State: California

Construction Types: Building, Heavy (Heavy and Dredging) and Highway

Counties: Alpine, Amador, Butte, Colusa, El Dorado, Glenn, Lassen, Marin, Modoc, Napa, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Solano, Sonoma, Sutter, Tehama, Trinity, Yolo and Yuba Counties in California.

BUILDING CONSTRUCTION PROJECTS (excluding Amador County only);

DREDGING CONSTRUCTION PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); AND HIGHWAY CONSTRUCTION PROJECTS

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 1/45

47PK0524R0066, Section B Page 16

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2024 1 01/12/2024 2 01/19/2024 3 02/09/2024 4 02/16/2024 5 03/01/2024 6 03/08/2024 7 04/12/2024 8 05/24/2024 9 06/14/2024 10 07/05/2024 11 07/12/2024 12 07/26/2024 13 08/23/2024 14 09/06/2024 15 09/13/2024

ASBE0016-001 01/01/2024

AREA 1: MARIN, NAPA, SAN BENITO, SAN FRANCISCO, SOLANO, &

SONOMA COUNTIES

AREA 2: ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,

MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA,

SISKIYOU, SUTTER, TEHEMA, TRINITY, YOLO, & YUBA COUNTIES

Rates Fringes

Asbestos Workers/Insulator (Includes the application of all insulating materials, Protective Coverings, Coatings, and Finishes to all types of mechanical systems) Area 1......................$ 84.76 25.07 Area 2......................$ 64.56 25.07

ASBE0016-007 01/01/2021

AREA 1 : ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,

LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA,

SIERRA, SISKIYOU, SOLANO, SONOMA, SUTTER, TEHAMA, TRINITY, YOLO

& YUBA COUNTIES

AREA 2: MARIN & NAPA COUNTIES

Rates Fringes

Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 2/45

47PK0524R0066, Section B Page 17 they contain asbestos or not)

AREA 1......................$ 30.45 10.60

AREA 2......................$ 36.53 9.27

BOIL0549-002 01/01/2021

Rates Fringes

BOILERMAKER

(1) Marin & Solano Counties.$ 49.62 41.27

(2) Remaining Counties......$ 45.60 38.99

BRCA0003-001 08/01/2023

Rates Fringes

MARBLE FINISHER..................$ 41.18 18.58

BRCA0003-004 05/01/2024

AREA 1: ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,

LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA,

SIERRA, SUTTER, TEHAMA, YOLO AND YUBA COUNTIES

AREA 2: MARIN, NAPA, SISKIYOU, SOLANO, SONOMA AND TRINITY

COUNTIES

Rates Fringes

BRICKLAYER

AREA 1......................$ 52.76 25.01

AREA 2......................$ 57.02 28.50

SPECIALTY PAY:

(A) Underground work such as tunnel work, sewer work, manholes, catch basins, sewer pipes and telephone conduit shall be paid $1.25 per hour above the regular rate. Work in direct contact with raw sewage shall receive $1.25 per hour in addition to the above.

(B) Operating a saw or grinder shall receive $1.25 per hour above the regular rate.

(C) Gunite nozzle person shall receive $1.25 per hour above the regular rate.

BRCA0003-008 07/01/2023

Rates Fringes

TERRAZZO FINISHER................$ 43.90 19.51

TERRAZZO WORKER/SETTER...........$ 59.06 28.31

BRCA0003-010 04/01/2024

Rates Fringes

TILE FINISHER

Area 1......................$ 35.00 17.44 Area 2......................$ 34.76 19.22 Area 3......................$ 37.75 19.28 Area 4......................$ 35.78 19.23 Tile Layer Area 1......................$ 55.55 21.08 Area 2......................$ 55.17 22.52

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 3/45

47PK0524R0066, Section B Page 18

Area 3......................$ 59.92 22.62 Area 4......................$ 56.79 22.54

AREA 1: Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Sutter, Tehema, Yolo, Yuba AREA 2: Alpine, Amador AREA 3: Marin, Napa, Solano, Siskiyou AREA 4: Sonoma

BRCA0003-014 08/01/2023

Rates Fringes

MARBLE MASON.....................$ 60.20 28.82

CARP0034-001 07/01/2021

Rates Fringes

Diver Assistant Tender, ROV Tender/Technician...........$ 54.10 34.69 Diver standby...............$ 60.51 34.69 Diver Tender................$ 59.51 34.69 Diver wet...................$ 103.62 34.69 Manifold Operator (mixed gas)........................$ 64.51 34.69 Manifold Operator (Standby).$ 59.51 34.69

DEPTH PAY (Surface Diving):

050 to 100 ft $2.00 per foot 101 to 150 ft $3.00 per foot 151 to 220 ft $4.00 per foot 221 ft.-deeper $5.00 per foot

SATURATION DIVING:

The standby rate shall apply until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. The diver rate shall be paid for all saturation hours.

DIVING IN ENCLOSURES:

Where it is necessary for Divers to enter pipes or tunnels, or other enclosures where there is no vertical ascent, the following premium shall be paid: Distance traveled from entrance 26 feet to 300 feet: $1.00 per foot. When it is necessary for a diver to enter any pipe, tunnel or other enclosure less than 48"" in height, the premium will be $1.00 per foot.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

CARP0034-003 07/01/2021

Rates Fringes

Piledriver.......................$ 54.10 34.69

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 4/45

47PK0524R0066, Section B Page 19

CARP0035-001 08/01/2020

AREA 1: MARIN, NAPA, SOLANO & SONOMA

AREA 3: SACRAMENTO, WESTERN EL DORADO (Territory west of an including highway 49 and the territory inside the city limits of Placerville), WESTERN PLACER (Territory west of and including highway 49), & YOLO

AREA 4: ALPINE, BUTTE, COLUSA, EASTERN EL DORADO, GLENN,

LASSEN, MODOC, NEVADA, EASTERN PLACER, PLUMAS, SHASTA, SIERRA,

SISKIYOU, SUTTER, TEHAMA, TRINITY, & YUBA

Rates Fringes

Drywall Installers/Lathers:

Area 1......................$ 52.65 31.26 Area 3......................$ 47.27 31.26 Area 4......................$ 45.92 31.26 Drywall Stocker/Scrapper Area 1......................$ 26.33 18.22 Area 3......................$ 23.64 18.22 Area 4......................$ 22.97 18.22

CARP0035-009 07/01/2020

Marin County

Rates Fringes

CARPENTER

Bridge Builder/Highway Carpenter...................$ 52.65 30.82 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 52.80 30.82 Journeyman Carpenter........$ 52.65 30.82 Millwright..................$ 52.75 32.41

CARP0035-010 07/01/2020

AREA 1: Marin, Napa, Solano & Sonoma Counties

AREA 2: Monterey, San Benito and Santa Cruz

AREA 3: Alpine, Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Sutter, Tehama, Trinity, Yolo & Yuba counties

Rates Fringes

Modular Furniture Installer Area 1 Installer..................$ 28.76 22.53 Lead Installer.............$ 32.21 23.03 Master Installer...........$ 36.43 23.03 Area 2 Installer..................$ 26.11 22.53 Lead Installer.............$ 29.08 23.03 Master Installer...........$ 32.71 23.03

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 5/45

47PK0524R0066, Section B Page 20

Area 3 Installer..................$ 25.16 22.53 Lead Installer.............$ 27.96 23.03 Master Installer...........$ 31.38 23.03

CARP0046-001 07/01/2023

El Dorado (West), Placer (West), Sacramento and Yolo Counties

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 60.39 33.52 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 54.66 33.52 Journeyman Carpenter........$ 54.51 33.52 Millwright..................$ 57.01 35.11

Footnote: Placer County (West) includes territory West of and including Highway 49 and El Dorado County (West) includes territory West of and including Highway 49 and territory inside the city limits of Placerville.

CARP0046-002 07/01/2023

Alpine, Colusa, El Dorado (East), Nevada, Placer (East), Sierra, Sutter and Yuba Counties

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 60.39 33.52 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 53.31 33.52 Journeyman Carpenter........$ 53.16 33.52 Millwright..................$ 55.66 35.11

CARP0152-003 07/01/2020

Amador County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 52.65 30.82 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 45.57 30.82 Journeyman Carpenter........$ 45.42 30.82 Millwright..................$ 47.92 32.41

CARP0180-001 07/01/2021

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 6/45

47PK0524R0066, Section B Page 21

Solano County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 54.85 31.49 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 55.00 31.49 Journeyman Carpenter........$ 54.85 31.49 Millwright..................$ 54.95 33.08

CARP0751-001 07/01/2021

Napa and Sonoma Counties

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 54.85 31.49 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 55.00 31.49 Journeyman Carpenter........$ 54.85 31.49 Millwright..................$ 54.95 33.08

CARP1599-001 07/01/2020

Butte, Glenn, Lassen, Modoc, Plumas, Shasta, Siskiyou, Tehama and Trinity Counties

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 52.65 30.82 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 45.57 30.82 Journeyman Carpenter........$ 45.42 30.82 Millwright..................$ 47.92 32.41

ELEC0180-001 06/01/2024

NAPA AND SOLANO COUNTIES

Rates Fringes

CABLE SPLICER....................$ 66.44 3%+27.84

ELECTRICIAN......................$ 59.06 3%+27.83

ELEC0180-003 12/01/2023

NAPA AND SOLANO COUNTIES

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 7/45

47PK0524R0066, Section B Page 22

Rates Fringes

Sound & Communications Installer...................$ 48.44 27.60 Technician..................$ 55.71 27.82

SCOPE OF WORK INCLUDES-

SOUND & VOICE TRANSMISSION (Music, Intercom, Nurse Call, Telephone); FIRE ALARM SYSTEMS [excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs], TELEVISION & VIDEO SYSTEMS, SECURITY SYSTEMS, COMMUNICATIONS

SYSTEMS that transmit or receive information and/or control systems that are intrinsic to the above.

EXCLUDES-

Excludes all other data systems or multiple systems which include control function or power supply; excludes installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access); excludes energy management systems.

ELEC0340-002 02/01/2018

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN,

NEVADA, PLACER, PLUMAS, SACRAMENTO, TRINITY, YOLO, YUBA COUNTIES

Rates Fringes

Communications System Sound & Communications Installer...................$ 29.35 3%+15.35 Sound & Communications Technician..................$ 33.75 3%+15.35

SCOPE OF WORK

Includes the installation testing, service and maintenance, of the following systems which utilize the transmission and/or transference of voice, sound, vision and digital for commercial, education, security and entertainment purposes for the following TV monitoring and surveillance, background-foreground music, intercom and telephone interconnect, inventory control systems, microwave transmission, multi-media, multiplex, nurse call system, radio page, school intercom and sound, burglar alarms, and low voltage master clock systems.

A. SOUND AND VOICE TRANSMISSION/TRANSFERENCE SYSTEMS

Background foreground music Intercom and telephone interconnect systems, Telephone systems, Nurse call systems, Radio page systems, School intercom and sound systems, Burglar alarm systems, Low voltage master clock systems, Multi-media/multiplex systems, Sound and musical entertainment systems, RF systems, Antennas and Wave Guide.

B. FIRE ALARM SYSTEMS

Installation, wire pulling and testing

C. TELEVISION AND VIDEO SYSTEMS Television monitoring and

9/24/24, 9:48 AM SAM.gov https://sam.gov/wage-determination/CA20240007/15 8/45

47PK0524R0066, Section B Page 23 surveillance systems, Video security systems, Video entertainment systems, Video educational systems, Microwave transmission systems, CATV and CCTV

D. SECURITY SYSTEMS Perimeter security systems Vibration sensor systems Card access systems Access control systems Sonar/infrared monitoring equipment

E. COMMUNICATIONS SYSTEMS THAT TRANSMIT OR RECEIVE

INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO

THE ABOVE LISTED SYSTEMS SCADA (Supervisory Control and Data Acquisition) PCM (Pulse Code Modulation) Inventory Control Systems Digital Data Systems Broadband and Baseband and Carriers Point of Sale Systems VSAT Data Systems Data Communication Systems RF and Remote Control Systems Fiber Optic Data Systems WORK EXCLUDED Raceway systems are not covered (excluding Ladder-Rack for the purpose of the above listed systems). Chases and/or nipples (not to exceed 10 feet) may be installed on open wiring systems. Energy management systems. SCADA (Supervisory Control and Data Acquisition) when not intrinsic to the above listed systems (in the scope).