Table Of Contents

Section Description Page Number Standard Form Standard Form 1 Volume 2 - Specifications Volume 2 - Specifications 4 Volume 4 - Other Attachments Volume 4 - Other Attachments 13

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

47PH0522R0035, Standard Form Page 1

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

47PH0522R0035, Standard Form Page 2

PAGE

GENERAL SERVICES ADMINISTRATION

OF

ITEM NO.

(a)

SUPPLIES OR SERVICES

(b)

QUANTITY

ORDERED

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

Place of Performance: AR0082RK LITTLE ROCK FOB/CTHS PARKING crack sealing with asphalt sealant in compliance with ASTM D

PoP: 07/22/2022 - 10/22/2023

Upgrade conditions for the parking lot located at 622 W 4th

(or better). Provide asphalt concrete pavement joint and

Arkansas

Contract Type: Firm Fixed Price

Department of Transportation (ARDOT) PG64-22 surface course

PSC: Z2LZ -- REPAIR OR ALTERATION OF PARKING FACILITIES

GSA Parking Lot Paving Repairs @ 622 W 4th St., Little Rock, replace all parking bumpers. Work will follow Arkansas

LOT 622 W 4TH ST LITTLE ROCK, AR 72201-2214

applying two seal coat, re-stripe the parking lot and

EA

Deliverable

6690 Type I, II or III

St., Little Rock, Arkansas. Work consists of minor leveling, 47PH0522R0035, Standard Form Page 3

U.S. General Services Administration Public Buildings Service Greater Southwest Region

1 SOW 3/2/2022

March 3, 2022

Scope of Work

1. Project Title: 70152 GSA Parking Lot Paving RAR10547

2. Project Location: AR AR0082RK Little Rock FOB/CTHS

622 W 4TH ST

Little Rock, AR 72201

3. Building Location Hours: Every attempt must be made to ensure normal building operations are not interrupted. All work affecting the parking lot shall be done after hours and or on weekends.

The project my be done in phases to make some parking available to employees.

4. Purpose: Purpose of this project is to repair the 4th street parking lot for the Little Rock Old Post Office/Courthouse Federal building by providing joint and crack cleaning and sealing, estimated at approximately 9100 linear feet. Provide new full depth hot mix asphalt concrete pavement patching in localized areas in compliance with Arkansas Department of Transportation (ARDOT) PG64-22 surface course (or better). Contractor will replace 11 curb stops and add about 20 new curb stops on parking row nearest old courthouse building. Contractor will restripe the parking lot of about 170 numbered spaces. Contractor will apply sealant coats on the parking lot. It is estimated at 50,530 SF.

5. Points of Contact:

5.1 Contracting Officer: Rod Blouin

819 Taylor Street Fort Worth, TX 76102 Phone #: 713-875-0632

5.2 Project Manager: John Knight

700 West Capitol Ave

Little Rock, AR 72201 Phone #: 501-258-0305

5.3 Supervisory Property Manager: Mark Freedle

700 West Capitol Ave

Little Rock, AR 72201

DocuSign Envelope ID: 3F443F3A-DA7A-4E1F-A0EB-B8B167951594 Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

Secured, But Unclassified

47PH0522R0035, Volume 2 - Specifications Page 4

2 SOW 3/2/2022

Phone #: 501-554-1467

5.4 Other: R7 Security Clearance Coordinators

r7clearance@gsa.gov

6. Notice to Proceed:

6.1 The Contracting Officer is the ONLY individual from the Government that can give the contractor a notice to proceed.

6.2 Before any of the work within the scope of the contract is started, the Contractor shall confer with the COR (Contracting Officer’s Representative) and agree on a sequence of procedure; means of access to premises and building; delivery of material and use of approaches; use of corridors, stairways, elevators, and similar means of communications;

and the location partitions, eating spaces for Contractor’s employees and the like.

6.3 After a Notice to Proceed is given the Contractor has 7 days to provide schedule.

7. Period of Performance: The total period of performance for this task order is 90 days which includes 45 calendar days for required security clearances, pre-work submittals, and material ordering. Actual construction period of performance is 45 calendar days.

8. Description of Work: Contractor shall provide all materials, labor, tools, equipment and daily supervision to accomplish tasks as outlined in contract documents. Contractor is also responsible for all necessary safety measures.

Provide asphalt hot mix asphalt concrete leveling course in depressed localized areas and joint and crack sealing of existing parking area. in compliance with Arkansas Department of Transportation (ARDOT) PG64-22 surface course (or better). Remove damaged / broken wheel stops and replace with new or anchor existing.

Dispose of refuse off site if needed.

Provide asphalt concrete pavement joint and crack sealing with asphalt sealant in compliance with ASTM D 6690 Type I, II or III. Provide joint and crack cleaning and sealing.

Cracks shall be routed and cleaned out at least 5/8”X5/8” wide and deep. Sealant shall be completed 1/8” to 1/4” below the surface. Excess sealant shall not be left on the surface.

Asphalt work shall comply with the guidelines in MS-16 Asphalt in Pavement Preservation and Maintenance, Asphalt Institute, 2009 unless otherwise specified herein.

DocuSign Envelope ID: 3F443F3A-DA7A-4E1F-A0EB-B8B167951594 Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

Secured, But Unclassified

47PH0522R0035, Volume 2 - Specifications Page 5 mailto:r7clearance@gsa.gov

3 SOW 3/2/2022

Protect from damage the adjacent concrete areas. Damage to these areas shall be repaired with no cost to the Government.

Apply sealant coats on parking lot.

Fix curb stops and install new curb stops.

Stripe parking lot.

Protect pedestrians and vehicles from flying debris and dust.

1.1 Division 1: General Requirements

1.1.1 Daily clean up - All workspace, staging areas, areas used for moving materials, trash, tools, etc. are to be always kept clean. All trash from the day’s work is to be removed and work site clean and orderly.

1.1.2 Protection - Contractor is responsible for protection of existing finishes, utilities, etc.

in the facility, and must maintain a separation of work area from adjacent spaces.

Site is to be secured at the end of day. Contactor shall be responsible for the security of the work site.

1.2 Division 2: Existing Conditions

1.2.1 All demolished material must be recycled/re-purposed to the maximum extent possible. If materials cannot be recycled/re-purposed, contractor is responsible for the proper disposal of the materials. No on-site dumpsters may be used.

1.3 Division 3: Concrete

1.3.1 Remove damaged / broken wheel stops and provide new replacement wheel stops and anchor them into the asphalt with two (2) new 18 inch long #4 deformed rebar.

1.3.1 Remove and replace wheel stops that have moved and anchor them into the asphalt with two (2) new 18 inch long #4 deformed rebar.

1.3.2 Contractor will replace 11 loose or cracked existing wheel stops and install approximately 17 new wheel stops on the front row near 4th street. It is noted estimated 11 curbs will be placed on spaces near the retaining wall on east side of the parking lot

1.4 Division 4: Masonry through Division 31: Earthwork

1.4.1 N/A

1.5 Division 32: Exterior Improvements

1.5.1 Clean and seal approximately 9100 LF of asphalt cracks in asphalt, VIF.

1.5.2 Provide hot mix asphalt concrete leveling course in depressed localized areas and joint and crack sealing of existing parking area.

1.5.3 Provide leveling course hot mix asphalt concrete pavement in localized areas in compliance with Arkansas Department of Transportation (ARDOT) PG64-22 surface course (or better). Tack coat leveling course in excavated square or rectangular

DocuSign Envelope ID: 3F443F3A-DA7A-4E1F-A0EB-B8B167951594 Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 6

4 SOW 3/2/2022

areas directed by the COR. It is estimated that 400 SF of asphalt requires leveling.

1.5.4 Provide asphalt concrete pavement joint and crack sealing with asphalt sealant in compliance with ASTM D 6690 Type I, II or III. Provide joint and crack cleaning and sealing. Cracks shall be routed and cleaned out at least 5/8”X5/8” wide and deep.

Sealant shall be completed 1/8” to 1/4” below the surface. Excess sealant shall not be left on the surface.

1.5.5 Asphalt work shall comply with the guidelines in MS-16 Asphalt in Pavement Preservation and Maintenance, Asphalt Institute, 2009, unless otherwise specified herein.

1.5.6 Contractor will provide asphalt seal coats for parking lot area (Asphalt Emulsion), 2 coats, resulting in a smooth black finish.

1.5.7 Provide proper application conditions exist and provide weather reports to include humidity levels for the time of application and for the drying period.

1.5.8 Provide ambient temperature and surface temperature at time of application.

1.5.9 Provide proper preparation on existing asphalt surface to receive the seal coats to include treating and priming oil spots with an acrylic emulsion-based primer that bonds tightly with oil-spotted asphalt surfaces and stops them from coming through seal coats.

1.5.10 Provide parking barricades to prevent traffic from driving on sealed parking lot areas until adequate curing time has passed, and a cure assessment is made to ensure traffic will not damage the surface.

1.5.11 Sealer shall not be applied to hot surfaces under the summer sun (over 90F°, ambient) without first cooling the surface with clean water. Water shall dampen the Provide surface without leaving puddles.

1.5.12 seal coats curing time of at least 24 hours before striping can be performed.

1.5.13 Provide parking spaces with 4" wide white striping lines and parking space numbers with water-based traffic paint.

1.5.14 Remove damaged / broken wheel stops and provide new replacement wheel stops and anchor them into the asphalt with two (2) new 18 inch long #4 deformed rebar.

1.5.15 Remove and replace wheel stops that have moved and anchor them into the asphalt with two (2) new 18 inch long #4 deformed rebar.

1.5.16 Contractor will replace 11 loose or cracked existing wheel stops and install approximately 17 new wheel stops on the row near 3rd street. Contractor will install 17 curb stops at the end parking stalls near 4th street.

1.5.17 Protect from damage the adjacent concrete areas. Damage to these areas shall be repaired with no cost to the Government.

1.5.18 Contractor will restripe the parking lot with the estimated 170 spaces. Contractor will number each space. Provide parking spaces with 4" wide white striping lines and parking space numbers with water-based traffic paint stripe.

1.5.19 Protect pedestrians and vehicles from flying debris and dust.

1.5.20 Dispose of the waste and refuse at contractor expense.

1.6 Division 33: Utilities

Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 7

5 SOW 3/2/2022

1.6.1 N/A

9. Options: N/A

10. Liquidated Damages: Liquidated damages shall be $64.00 per calendar day beginning at 12 mid night the date immediately following the scheduled completion date and will continue until all work is completed and accepted by GSA. Time for performance shall be determined upon notification to proceed. The ordering official will review all justifications and any extensions of time will be made based on their decision. No work shall begin until all necessary parts and materials are on-site and available.

11. Sustainability:

11.1 Green Purchasing: See attachment 1: green purchasing requirements

11.2 Waste Diversion Fourteen days from Notice to Proceed, the Contractor shall submit to the

Project Manager an updated Non-Hazardous Solid Waste Management Plan attachment 2:

Waste Diversion Plan, to include (not limited to):

a) List of materials Contractor will reuse

b) List of materials the Contractor will donate and name and address of donation recipient.

c) List of materials the Contractor will recycle and the name and address of the recycler. If Contractor receives recycling revenue, Contractor shall keep revenue and provide receipt for GSA for reference.

d) Name and location of solid waste landfill for non-diverted material.

12. Other Requirements:

12.1 Purchase of Equipment

12.2 Building Specific Requirements

13. Submittals:

13.1 Critical Path Method Schedule

13.2 Waste Diversion Submittal: Preconstruction

13.3 Waste Diversion Submittal: Post Construction

13.4 Green Purchasing items

13.5 Asphalt materials for repair of cracks.

13.6 Pavement Sealants. ( Asphalt Sealcoat Materials and Testing (shown as approved by

ARDOT, City of Little Rock or Little Rock School District)

13.7 Wheel Stops cut sheet.

14. Attachments:

14.1 Attachment 1: Green Purchasing

14.2 Attachment 2: Waste Diversion Plan

Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 8

6 SOW 3/2/2022

15. Closeout Plan:

15.1 Final Punch list complete

15.2 Customer Acceptance

15.3 Close Out Documents (O&M Manuals, Warranty, Certified payrolls and Release of Claims, Waste Diversion documentation)

15.4 Final inspection 220

15.5 Receiving report

15.6 Final Invoice

END OF SOW

Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 9

7 SOW 3/2/2022

Attachment 1: Green Purchasing

Sustainability:

● Green Purchasing:

o The contractor shall refer to the “Green Procurement Compilation” for all products being installed in federal facilities. The Green Procurement Compilation can be found at https://sftool.gov/greenprocurement. The standards found in this compilation shall guide all product purchasing decisions as they relate to federal facilities.

o The use of the following standards (“Key Sustainable Product” or “KSP” standards) is mandatory for all contracts and task orders. See https://sftool.gov/green-products/1037/key-sustainable-products for more details.

▪ Nylon Carpet: NSF-140 Platinum or Cradle to Cradle Bronze.

▪ Resilient Flooring (e.g. vinyl and linoleum): NSF-332 (any level) or Cradle to

Cradle (any level)

▪ Interior Latex Paint: Master Painters Institute (MPI) Extreme Green or Green

Seal 11.

▪ Acoustical Ceiling Tiles: > 15% post-consumer recycled content.

▪ Water-Consuming Equipment: WaterSense Certified.

A. For each KSP listed, the Contractor shall submit proof of compliance to the CO or his designee prior to the installation of the product or material. The CO’s designee shall verify compliance.

B. If the KSP materials listed above are 1) not reasonably available within a reasonable period of time; 2) fail to meet the performance standards set forth in the specification or fail to meet reasonable performance standards of GSA; or 3) are available only at an unreasonable price, only then can the Contractor use other types of products. In these cases the Contractor shall select products and materials, to the extent possible, which are the safest and most environmentally friendly. Exemptions must be submitted in writing and can only be approved by the CO.

Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 10

8 SOW 3/2/2022

Attachment 2: Waste Diversion Plan

1. Submittal Type: Pre-Construction or Final (Circle Appropriate Type)

2. ePMX Number: ___________________ (Should receive from GSA PM)

3. Field Office: Circle Appropriate Field Office: (Oklahoma City, Tulsa, New Mexico, Little Rock, Shreveport, Tyler, New Orleans, Baton Rouge, Dallas, Fort Worth, Lubbock, Houston, Austin, San Antonio, McAllen, El Paso)

4. GSA Project Manager: _________________

5. Contract Number: ______________________

6. Categories to Track:

6.1 Carpet: (rolled or tiled) Weight (lbs.):_____ Recover Method: ___________

6.2 Architectural :( doors, windows, frames, millwork) Weight (lbs.):_____ Recover Method:___________

6.3 Ferrous Metals: (structural steel, studs, rebar) Weight (lbs.): _____ Recover Method: ___________

6.4 Non-Ferrous: (wire, piping, duct) Weight (lbs.):_____ Recover Method:___________

6.5 Aggregate: (concrete, brick, blocks) Weight (lbs.):_____ Recover Method: ___________

6.6 Plumbing Fixtures: (sinks, toilets, urinals) Weight (lbs.):_____ Recover Method: ___________

6.7 Furniture: (Systems, casual, equip.) Weight (lbs.): _____ Recover Method: ___________

6.8 Ceiling/Wall: (gypsum, tiles) Weight (lbs.): _____ Recover Method: ___________

6.9 Roofing: (Shingles, Paper, membrane) Weight (lbs.):_____ Recover Method: ___________

7. Landfill Hauler: ___________________

8. Landfill Waste: ____________________

END OF SOW

Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 11

9 SOW 3/2/2022

Scope of Work Signature Page

Approvals

GSA Project Manager- John F. Knight

Signature Date

GSA Supervisory Property Manager- Mark Freedle

Signature Date

GSA Civil Engineer SME – Mark Woods

Signature Date

GSA Supervisory Project Manager- Jeff Chiavetta

Signature Date

DocuSign Envelope ID: 3F443F3A-DA7A-4E1F-A0EB-B8B167951594

3/7/2022

3/7/2022

3/7/2022

3/7/2022

Sensitive But Unclassified/Controlled Unclassified Information document security for sensitive See PBS Order 3490.1A

47PH0522R0035, Volume 2 - Specifications Page 12

47PH0522R0035 - Volume 4 - Other Attachments - List of Attachments Documents Table of Contents

Attachment Number Document Title ECF 1 ar145 10 - Solicitation and Amendments

47PH0522R0035, Volume 4 - Other Attachments Page 13

topmostSubform[0]:
Page2[0]:
USC10[0]:
TelephoneNo\:
[0]:
Date31c[0]:
CheckBox29[0]: Off
AmendmentNo4[0]:
AdministeredBy[0]:
FacilityCode[0]:
AmendmentDate4[0]:
AmendmentNo7[0]:
AuthorizedSignature[0]:
Date30c[0]:
Amounts[0]:
AmendmentNo5[0]:
AmendmentDate8[0]:
AmendmentNo1[0]:
AccountingData[0]:
AmendmentDate3[0]:
Amount[0]:
AmendmentNo10[0]:
AmendmentDate7[0]:
PaymentMadeBy[0]: PBS PAYMENTS BRANCH -https://finance.ocfo.gsa.gov/

P.O. BOX 17181

https://finance.ocfo.gsa.gov/

FORT WORTH, TX 76102-0181 USA

AmendmentNo8[0]:
NameofOfferor[0]:
NameContractingOfficer[0]: Roderick Blouin
Copies28[0]:
NameTitleSign[0]:
NameandTitle[0]:
OfferDate[0]:
Signature30b[0]:
AmendmentDate9[0]:
AmendmentNo6[0]:
ItemsAccepted[0]:
AmendmentDate2[0]:
AmendmentNo2[0]:
AmendmentDate6[0]:
RemittanceAddress[0]:
USC41[0]:
CalendarDays2[0]:
AmendmentNo9[0]:
CheckBox1[0]: Off
AmendmentDate10[0]:
CodeField[0]:
AmendmentNo3[0]:
AdministeredByCode[0]:
CheckBox28[0]: Off
Item[0]: 27
AmendmentDate1[0]:
AmendmentDate5[0]:
CheckBox2[0]: Off
Signature31b[0]:
Page1[0]:
Code[0]: 7PQCNO
Sealed[0]: Off
PurchaseRequestNo[0]: EQ7PACS-22-0070
Mandatory[0]: 1
AddressOfferTo[0]: 7PQCNO

ACQUISITION NON-PROSPECTUS

500 POYDRAS ST Room: 1010

NEW ORLEANS, LA 70113 USA

Is[0]: 1
Yes[0]: 1
NumberofCopies[0]:
Award[0]: Off
Pages[0]: 3
WorkDescribed[0]: GSA Parking Lot Paving, Project No. 70152, Scope of Work dated March 3rd, 2022.
PhoneNo[0]: 504-432-9239
Hour[0]: 4:00 PM (CST)
Proceed[0]: 1
See[0]:
SolicitationNo[0]: 47PH0522R0035
CalendarDays[0]: 7
CalendarDaysComplete[0]: 90
Name9a[0]: Mark Blanco
Page[0]: 1
Negotiated[0]: 1
By[0]:
Negotiable[0]: Off
IsNot[0]: Off
ProjectNo[0]: 70152
DateDue[0]: 7/8/2022
IssuedBy[0]: ACQUISITION NON-PROSPECTUS

500 POYDRAS ST Room: 1010

NEW ORLEANS, LA 70113 USA

ContractNo[0]:
No[0]: Off
CalendarDaysStart[0]: 10
LessCalendarDays[0]: 120
DateIssued[0]: 5/22/2022
2022-03-07T14:38:07-0800