GSA Solicitation No. 47PH0517R0003

Document: DB201A / DEC 2016 (The Solicitation) Pages 1 of 30

U.S. General Services Administration, Public Buildings Service, Acquisition Management Services Division, Non-Prospectus Projects Branch (7PQC) Greater Southwest Region 07

PROJECT: Design Build - Install Wet Pipe Fire Sprinkler System in the Monroe Federal Building and Courthouse, Building Number LA0029ZZ, 210

Jackson Street, Monroe, LA 71201

ISSUE DATE: July 20, 2017

Site Visit: August 1, 2017 @ 10:30 a.m. CST

PROPOSAL DUE: August 22, 2017 4:00 p.m. Central Standard Time

SOLICITATION NO.: 47PH0517R0003

U.S. General Services Administration

These documents are the property of the United States government.

Copying, dissemination, or distribution of these Drawings, Plans, or specifications to unauthorized persons is prohibited. Distribution to those with other than a need to know is strictly prohibited.

SPECIFICATIONS AND OFFER FORMS

GSA MISSION STATEMENT: The Mission of GSA is to deliver the best value in real estate, acquisition, and technology services to government and the American people.

(The Solicitation) Pages 2 of 30

Design Build Contract for Install Wet Pipe Fire Sprinkler System at the Monroe Federal Building and Courthouse, 210 Jackson Street, Monroe, LA 71201

The Solicitation

552.219-71 Notice to Offerors of Subcontracting Plan Requirements (MAR 2012)

The General Services Administration (GSA) is committed to assuring that maximum practicable opportunity is provided to small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran owned small business concerns to participate in the performance of this contract consistent with its efficient performance. GSA expects any subcontracting plan submitted pursuant to FAR 52.219-9, Small Business Subcontracting Plan, to reflect this commitment. Consequently, an offeror, other than a small business concern, before being awarded a contract exceeding $700,000 ($1,500,000 for construction), must demonstrate that its subcontracting plan represents a creative and innovative program for involving small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran owned small business concerns as subcontractors in the performance of this contract.

Notice of Equal Employment Opportunity (EEO) Compliance Plan GSA has partnered with the Department of Labor to ensure compliance with equal employment opportunity requirements that apply to this project. An EEO Compliance Plan is required after the award.

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit - Construction H. Receipt of Offers

II. Proposals A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to Submit with Proposal F. Requirements for Joint Venture Offerors

(The Solicitation) Pages 3 of 30

III. Solicitation Provisions A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding Documents Designated as Sensitive But Unclassified J. Additional Security Requirements

IV. FAR/GSAR Solicitation Provisions

A. FAR 52.215-1 Instructions to Offerors—Competitive Acquisition B. FAR 52.216-1 Type of Contract C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal

Employment Opportunity for Construction E. FAR 52.233-2 Service of Protest F. Buy American G. Buy American Exceptions H. Small Business Subcontracting Plan I. Project Labor Agreements J. GSAR 552.252-5 Authorized Deviations in Provisions K. FAR 52.252-1 Solicitation Provisions Incorporated by Reference L. GSAR 552.102 Incorporating Provisions and Clauses by Reference

V. Additional Solicitation Provisions and Instructions

A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29

B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions

C. Additional Solicitation Provisions D. Certified Cost or Pricing Data E. Additional Clauses F. FAR 52.222-62 Paid Sick Leave

VI. Method of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness / Price Realism D. Unbalanced Prices E. Total Evaluated Price F. Non-Price Factors G. Evaluation of Joint Venture Offerors

(The Solicitation) Pages 4 of 30

I. General Information

I.A. The Solicitation and Contract

(1) This Solicitation sets forth requirements for proposals for a Contract to design and construct the Project described in the Solicitation Documents. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3). The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer.

No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) The Solicitation

(2) Offeror Representations and Certifications Form

(3) Standard Form (SF) 1442 – Solicitation Offer and Award

(4) The Agreement

(5) The Statement of Work, Specifications, Drawings, Exhibits, and other Attachments to the Agreement

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

(1) Contracting Officer

Name: Paul Shirlee Address: 819 Taylor Street, Room 12B, Fort Worth, TX 76102

Telephone: 817-978-3881 Email: Paul.shirlee@gsa.gov

(2) Alternate Point of Contact

Name: Stephan Harris

Telephone: 817- 978-0106 Email: Stephan.harris@gsa.gov

(The Solicitation) Pages 5 of 30

I.D. Pre-Proposal Conference [

(1) A pre-proposal conference regarding this Solicitation is scheduled as follows:

Date: August 1, 2017 Time: 10:30 AM CTS

Location: Monroe Federal Building and Courthouse, 210 Jackson Street, Monroe, LA 71201

(2) [ To request a reasonable accommodation due to a disability, contact the Contracting Officer.

I.E. Estimated Price Range or Budget Amount

The estimated price range for the Project is between $250,000 and $500,000.

I.F. FAR 52.228-1 Bid Guarantee (SEP 96)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.G. FAR 52.236-27 Site Visit - Construction (FEB 95)

(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.

http://www.acquisition.gov/far/current/html/52_233_240.html#wp1113365 http://www.acquisition.gov/far/current/html/52_233_240.html#wp1113375

(The Solicitation) Pages 6 of 30

(2) Site visits will be held at the following dates and times:

Date: [August 1, 2017 ] Time: [ 10:30 ]

(3) The Site Visit shall be limited to not more than four (4) representatives from each Offeror.

Offerors shall submit a Visit Authorization Request (VAR) identifying all attendees from their respective team. Participants must have a valid, Government issued picture identification, driver’s license preferred, to gain access for the pre-proposal Site Visit. Notification of the location of entry, where attendees are required to meet, and all other requirements for the Site Visit will be issued to the Offerors. Submit the VAR to the point of contact listed below.

For further information about the site visit or access requirements, please contact:

Name: [ Glen Keaton at glen.keaton@gsa.gov or Jerry Rash at jerry.rash@gsa.gov Address: [ 700 West Capitol, Suite 3423, Little Rock, AR 72201 ]

Telephone: [ Glen Keaton – 501-324-6371, Jerry Rash – 318-957-0256 ] Email: [Glen Keaton at glen.keaton@gsa.gov or Jerry Rash at jerry.rash@gsa.gov ]

I.H. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 4:00 pm local time on the following date and at the following address:

Date: August 22, 2017

(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.

(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the office designated for receipt of offers on or before the date established for receipt of offers.

II. Proposals

II.A. Proposal Contents

Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

(1) Price Proposal

(2) Technical Proposal

(3) Representations and Certifications (C301) mailto:glen.keaton@gsa.gov mailto:glen.keaton@gsa.gov

(The Solicitation) Pages 7 of 30

(4) Bid Guarantee, using Standard Form 24

(5) Subcontracting Plan

(6) Other Documents as Required

II.B. Proposal Format Two Copies of proposal

II.C. Price Proposal

(1) Contents The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

II.D. Technical Proposal The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.

(1) Experience

Description: This factor concerns the quality of the Offeror's experience in installing fire alarm systems. Considerations will be given to success in areas of technical quality, delivery, schedule conformance and completion within budget.

Evaluation Criteria: This factor evaluates the past performance and experience of the Offeror and will be evaluated as part of the responsibility determination. Past performance shall be evaluated in accordance with FAR 15.305, however the comparative assessment in 15.305(a)(2)(i) does not apply.

Acceptability Standard The Offeror shall provide samples of three (3) projects successfully completed within the last five (5) years from the date of issuance of this solicitation using the attached Past Performance Assessment Worksheet (to be completed by Offeror) and Past Performance Questionnaire (to be sent to and completed by references). References shall submit Past Performance Questionnaires directly to the Contract Specialist via email or to the address provided in Section I.C., Authorized Representatives. All references shall say they would contract with the firm again and rate them “acceptable” or better.

(The Solicitation) Pages 8 of 30

The three (3) projects submitted should meet the definition of both “similar size” and “similar scope” to the project.

The definition of "similar size” for evaluation purposes is a project involving successful design and construction valued at a minimum of $400,000.00 in a high-rise building.

The definition of “similar scope” for evaluation purposes is a project consisting:

Installation of a fire sprinkler system in an occupied building.

Any proposal submitted by the offeror which does not demonstrate satisfactory performance on three (3) similar projects substantially completed within the last five (5) years will not be considered technically acceptable.

The Government reserves the right to use other government data available in its assessment of the offeror. The quality of the reference information supplied will be considered. In accordance with FAR 15.306, the offeror will be given the opportunity to respond to adverse past performance information.

Standard for Evaluation:

The standard is met when:

The Offeror submits three (3) projects performed within the last five (5) years and the projects meet both the definition of “similar size” and “similar scope” to the project using the Past Performance worksheets. All references shall say they would contract with the firm again and rate them “acceptable” or better. A narrative of these projects shall be provided and include the following information:

o Project Name and address o Project size in square footage of the building.

o Contract amount o New Construction or retrofit o Contact information of customer – Company, Contact Name, Phone # o Project duration (time to complete) o Narrative describing overall scope of project

(2) Experience of Key Personnel

Description: This factor considers the education, knowledge, experience, and expertise of the Offeror’s key personnel proposed to be assigned directly to the contract.

Evaluation Criteria: This factor evaluates the Offeror’s demonstrated qualifications of proposed key personnel.

Acceptability Standard The Offeror must provide a staffing plan for the following positions:

Project Manager Project Foreman (Installation) Project Designer/Engineer

The Offeror must provide a Resume for the individuals that will be assigned to these

(The Solicitation) Pages 9 of 30 positions on this project. If it is unknown which individual will be assigned to these positions at this time, the offeror shall submit a resume for each individual that may be assigned to the above position. Resumes shall include the following information:

● Job Title

● Education / Training, certifications, licenses

● Employment History (Company name, dates employed, Job Title) within Fire Alarm Trade

● Project History – include a total of three (3) projects of similar size and scope completed within the last 5 years.

Standard for Evaluation:

The standard is met when:

● Project personnel demonstrate they meet installer qualifications outlined in specification 283111 Section 1.6.

● The Offeror submits a staffing plan for the following positions: Project Manager, Project Foreman (Installation) and Project Designer/Engineer.

● The Offeror submits a resume or curriculum vitae for individuals that will or may be assigned to the aforementioned positions and includes all information as required above.

Project History shall include three projects of similar size and scope with the following information:

o Project Name and address o Project size in square footage of the building.

o Contract amount o New Construction or retrofit o Narrative describing overall scope of project.

The Offeror must demonstrate successful experience as a Design Build (DB) Contractor responsible for the construction of three (3) similar projects substantially completed within the past five (5) years as defined below. One similar project is defined as a project that is comparable in nature, type, and complexity as defined by the all of the following characteristics:

(a) The project involved a modernization and/or renovations to an existing building that included work on architectural, structural, electrical, mechanical, plumbing, fire protection systems, high security blast and ballistic windows.

(b) The total project construction cost at award of the construction contract(s) was not less than $50 million.

(c) Project involved work on a historic site and/or building

(d) Project involved phase construction in a partially occupied building.

The Offeror may also present not more than 3 additional comparable projects substantially completed within the last eight (8) years. Comparable projects are projects with a total project cost at award of not less than $50 million and contain any 3 of the following characteristics:

(a) The project involved a modernization and/or renovations to an existing building that included work on architectural, structural, electrical, mechanical, plumbing, fire protection systems, high security blast and ballistic windows.

(b) Project involved work on a historic site and/or building

(c) Site was located in a Major metropolitan downtown area.

(d) Project required close coordination with occupants

(The Solicitation) Pages 10 of 30

(e) Project involved phase construction in a partially occupied building.

(f) Project involved abatement of hazardous material.

For each project presented in relation to this factor, the Offeror must explain how the characteristics of the project relate to the characteristics of this project. The similarity to this project is more important than the quantity of projects presented. For each project presented the Offeror shall submit the following data/information:

(a) Project Title

(b) Owner and/or Occupants(s)/Tenant(s)

(c) Location

(d) Description including GSF and/or OSF

(e) Special Features (Security System, Historical Consideration, Blast & Ballistic

Windows)

(f) Contract Award Date

(g) Contract Type and Contractor's Responsibilities (Scope of Work)

(h) Date of Substantial Completion

(i) Date of Final Completion

(j) Contract Cost at Award

(k) Contract Cost at Completion

(l) Original Schedule Completion Time at Contract Award (Calendar Days)

(m) Actual Completion Time (Calendar Days)

(n) Number of Change Orders

This factor will be evaluated based upon the written response to the RFP by the Offeror and the past experience demonstrated by the presented projects. Attachment # 2, titled “Experience Checklist”, will be used for each presented project just to record which listed characteristics apply to the respective project example.

(3) Management Approach

Description: This factor is comprised of the Offeror's management capability and ability for planning, organizing and controlling the execution and coordination of installing fire sprinkler activities, including meeting schedules, coordination of subcontractors, minimization of delays and compliance with tenants’ needs. It includes: the coordination to assure compliance with contract requirements; a safety plan, technique for dealing with issues, problems, questions, emergencies and other areas of concern.

● Offerors shall describe their approach to managing and delivering a project of the magnitude and complexity of THIS project under budgetary and time constraints. The description shall include a discussion of offeror’s approach to managing the project to meet or exceed performance criteria, on schedule, and within budget. Offerors should include discussions of how the schedule for the project will be met while, at the same time, managing any changes that may occur. Offerors previous experience in managing to achieve LEEDS certification shall also be presented.

Submittal Requirement:

The Offeror shall submit a narrative describing their:

Plan for organizing and coordinating activities

(The Solicitation) Pages 11 of 30

Plan to manage sub-contractors Safety Plan Quality Control Plan

The Offeror submits all narratives required above.

Plans demonstrate the foresight of the Offeror’s team for solving the future challenges that will be present in the coordination of design and construction activities

Plan demonstrates an effective approach to dealing and managing design team members and sub-contractors

Plan demonstrates a sound Safety Plan Quality controls are in place

Specialized experience and technical competence

(b) Design Team Qualifications

Demonstrate that the proposed TEAM has the relevant key individual professional qualifications including professional registrations and experience necessary for this project.

II.E. Other Information to Submit with Proposal

(1) Representations and Certifications

Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in the System for Award Management accessed via https://www.sam.gov. Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301).

(2) Qualifications of Offerors

Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract. Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.

II.F. Requirements for Joint Venture Offerors

(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.

(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.

https://www.sam.gov/

(The Solicitation) Pages 12 of 30

(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.

(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.

III. General Provisions

III.A. Availability of Funds

Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the Contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of Contract award.

III.B. Requests for Clarification or Interpretation

The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but will not warrant that all such requests will be answered within 15 calendar days. Therefore, prospective Offerors should make such requests not less than 15 calendar days prior to the date set for receipt of offers.

III.C. Notice to Small Business Firms

A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (www.sba.gov). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.

III.D. Information Concerning the Disclosure of Solicitation Results

This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will made available until after award except as provided by FAR 15.503.

III.E. Affirmative Procurement Program

GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to clauses FAR 52.204-4 requiring double sided printing on recycled paper for all reports and FAR 52.223-10 encouraging vendors to practice waste reduction.

III.F. Notice Concerning Preparation of Proposals

(The Solicitation) Pages 13 of 30

Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.

III.G. Bond Requirements

If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.

III.H. Contractor Performance Information

(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process.

CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is http://www.cpars.gov

Completed CPARS evaluations are sent to the Past Performance Information Retrieval System (PPIRS) which may then be used by Federal acquisition community for use in making source selection decisions. PPIRS assists acquisition officials by serving as the single source for contractor past performance data.

(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS.

The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.

(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (http://www.cpars.gov/allapps/cpcbtdlf.htm) and updated as needed.

(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.

Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.

GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.

http://www.cpars.gov/ http://www.cpars.gov/allapps/cpcbtdlf.htm

(The Solicitation) Pages 14 of 30

Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.

III.I. Safeguarding Documents Designated as Sensitive But Unclassified

Certain information contained in the Solicitation Documents may have been designated as Sensitive but Unclassified (SBU) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.

III.J. Additional Security Requirements

(1) FAR 52.204-9, Personal Identity Verification of Contractor Personnel, January 2011

(Insert clause when contract performance requires contractors to have routine physical access to a Federally-controlled facility and/or routine access to a Federally-controlled information system. Shall not be used when contractors require only intermittent Federally-controlled facilities).

(2) FAR 52.224-2, Privacy Act, April 1984 (Insert clause when design, development, or operation of a system of records on individuals is required to accomplish an agency function).

(3) GSAR Clause 552.204-9, Personal Identity Verification Requirements, October 2012 (Insert clause when it is determined that contractor employees will require access to federally controlled facilities or information systems to perform contract requirements).

This project is classified as Sensitive but Unclassified

IV. FAR/GSAR Solicitation Provisions

IV.A. FAR 52.215-1 Instructions to Offerors—Competitive Acquisition (JAN 04)

(a) Definitions. As used in this provision— “Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.

“In writing,” “writing,” or “written” means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the

(The Solicitation) Pages 15 of 30 last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Submission, modification, revision, and withdrawal of proposals.

(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and

(ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show—

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal.

Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

(3) Submission, modification, revision, and withdrawal of proposals.

(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—

(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or

(3) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(The Solicitation) Pages 16 of 30

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225- 17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.

(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.

(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.

(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).

(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall—

(1) Mark the title page with the following legend:

This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and

(2) Mark each sheet of data it wishes to restrict with the following legend:

Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.

(The Solicitation) Pages 17 of 30

(f) Contract award.

(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

(2) The Government may reject any or all proposals if such action is in the Government’s interest.

(3) The Government may waive informalities and minor irregularities in proposals received.

(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.

(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.

(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government. (f)(4) The Government intends to evaluate proposals and award a contract after conducting discussions with offerors whose proposals have been determined to be within the competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the offeror's initial proposal should contain the offeror's best terms from a price and technical standpoint.

(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.

(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.

(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:

(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.

(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.

(The Solicitation) Pages 18 of 30

(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.

(iv) A summary of the rationale for award.

(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.

(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.

IV.B. FAR 52.216-1 Type of Contract (APR 84)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

IV.C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work

(MAY 14)

(a) (1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b) (1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

IV.D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)

(Applicable to solicitations resulting in construction contracts in excess of $10,000.)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative

Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for Minority Participation for Each Trade

Goals for Female Participation for Each Trade

22.8%

6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located

(The Solicitation) Pages 19 of 30 outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for

Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the

"covered area" is:

Ouachia County in Louisiana

IV.E. FAR 52.233-2 Service of Protest (SEP 06)

(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

IV. F. Buy American

FAR 52.225--9 Buy American Act—Construction Materials.

(The Solicitation) Pages 20 of 30

As prescribed in 25.1102(a), insert the following clause:

Buy American Act—Construction Materials (Sep 2010)

(a) Definitions. As used in this clause—

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 ( 46 U.S.C. App. 1702), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic…