This document is a Statement of Work (SOW) for a Building Automation Systems (BAS) Blanket Purchase Agreement (BPA) in GSA Region 6. The SOW outlines requirements to replace existing building automation controllers with JACE 8000 or JACE 9000 network controllers, install service maintenance agreements, replace end-of-life air handler and VAV controllers with Niagara Edge controllers, and migrate the system to a new GSA-provided virtual server. Key requirements include creating new permissions, categories, and navigation files; programming new graphics, sequences of operation, and optimization strategies; and conducting system testing, verification, and training. The SOW also details open-source protocol requirements, software features, and deliverables. This SOW supports a larger federal contract opportunity, Solicitation Number 47PG1024Q0002, for a Region 6 GSA BAS BPA with a 5-year period of performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Region 6 BAS BPA for 5 Years
June 14, 2024
BACKGROUND
The intended purpose of this SOW is to perform the following:
JACE 8000 or JACE 9000:
Replace all Johnson Controls Metasys NAE/NCE’s or similar network controllers with Niagara JACE 8000 or JACE 9000 network controllers. Replicate all existing programming that is currently being used. Provide Niagara drivers to Metasys drivers to the existing N2 bus for communications to field controllers and add a newly configured Niagara server to provide better control and functionality of the existing HVAC control system. The only approved replacement device for the existing NAE/NCE style devices will be a JACE 8000 running the latest approved version GSA approved version. The installed JACE 8000 or JACE 9000 must have an open NIC in its license.
Service Maintenance Agreements:
Install Service Maintenance Agreements (SMA) for the existing Niagara JACE 8000’s and JACE 9000’s located in Region 6. Service maintenance agreements play an important role in maintaining up to date versions of the building automation software to ensure all security measures are kept current. The contractor will install the 3 Year SMA Renewal agreements for the following JACEs and Soft JACE. These are set at 3-year renewals to bring them back up to date.
Niagara Edge Air Handler and VAV Controllers:
Replace the existing EOL Network air handler and vav controllers with Non-preparatory Niagara Edge10 air handler controllers and Non-preparatory Niagara vav controllers for trimming of ventilation programming per ASHRAE 36. This will provide standardized sequences of operation for heating, ventilating, and air-conditioning (HVAC) systems which will maximize HVAC system energy efficiency and performance, provide control stability, and allow for real-time fault detection and diagnostics. The trimming of ventilation programming reset strategy is applied for control of the static air pressure and air temperature setpoints.
Standardized advanced control sequences provide benefits including reduced programming time, reduced energy consumption, system downtime and improved indoor air quality.
JOB LOCATION
· Region 6
JOB REQUIREMENTS
The contractor shall provide all materials, labor, and equipment necessary for the completion of the following:
1. Installation of JACE 8000’s and JACE 9000’s within Region 6 locations.
2. Creation of new Niagara NAV files
3. Creation of new categories under permissions to signify facility personnel navigation
4. Creation of new User Roles to control system privileges
5. Recreation of all programming currently residing in NAE into new JACE 8000’s and JACE 9000’s
6. Creation of all new Histories and Alarms in new JACE 8000’s and JACE 9000’s
7. Redirection of all JACEs to new Primary Server
8. Building automation verification for the building automation system replacement
9. Testing and verification of all building automation systems after the migration or retrofit
10. Technical training with the staff regarding the operation of the new building automation system
11. The removal of existing EOL air handler controllers and VAV controller
12. The installation of Non-preparatory Niagara Edge-10 air handler controllers with an attached I/O module
13. Provide wiring diagrams of all new Non-preparatory Niagara Edge-10 air handler controllers
14. Provide BAS vav programming to reflect any new sequence of operation changes to the new Non-preparatory Niagara Edge-10 air handler controllers.
15. Create new BAS air handler graphics.
16. Verify air handler operation and functionality.
17. Provide updated network diagrams.
18. Provide updated sequence of operations.
19. The removal of existing EOL vav controllers
20. The installation of Non-preoperatory Niagara Edge vav controllers and supporting I/O modules
21. Provide wiring diagrams of all new Non-preoperatory Niagara Edge vav controllers
22. Provide BAS vav programming to reflect any new sequence of operation changes to the Non-preoperatory Niagara Edge controllers.
23. Create new BAS graphics for vav’s and air handlers.
24. Verify vav operation and functionality.
25. Provide updated network diagrams.
26. Verify air handler operation and functionality.
27. Provide updated network diagrams.
28. Initial 18 month SMA for JACE 8000’s and JACE 9000’s for new JACE installations
29. Contractor to look up the host IDs and provide the correct license and SMA.
30. Any and all new wiring and network connections MUST be added by the contractor.
31. The Contractor shall dispose of all removed hardware and unused construction materials. **Any hardware with a USENAME and PASSWORD must be given to R6 Smart Building Team**
STATEMENT OF WORK
JACE 8000 and JACE 9000 The contractor shall provide all management, supervision, manpower, equipment and supplies necessary for the following: Replace BAS Platform and Install JACE 8000’s and JACE 9000’s
1. Building Automation System Replacement Verification
a. Conduct a verification of all onsite network controllers to determine suitable GSA acceptable open platform replacements to the proposed version.
i. The awarded contractor shall provide a list of all hardware devices that require replacement under this contract
ii. A schedule of affected areas shall be provided to the Government for review and approval, as to minimize zone down times and service disruptions
iii. NOTE: Continuity of service in the facility during building occupied hours is mandated throughout the duration of this project
2. Building Automation System Backup – Pre-Deployment
a. Conduct a backup of the building automation system which includes the following:
i. Historical data/trends
ii. Points
iii. Programs
iv. Graphics
v. Other related data to the BAS
b. Provide two copies of existing backup data to the Government
i. Distribution of copies shall be the responsibility of the Government (COR) to the following:
1. GSA Building Manager
2. Region 6 Smart Buildings Team
c. Backup media to be provided via CD or DVD media
d. Labeling of the media shall include the date of the backup, location, project number and the BAS version
i. Labeling shall also include the term “SBU”
3. Installation of Building Automation System Related Equipment
a. Install JACE 8000 or JACE 9000 network controllers and Niagara drivers to N2 bus drivers for field level controller communications that use open-source protocol that will connect to the new Niagara N4 BAS Platform
i. Building automation system shall encompass the following equipment where applicable to the building:
1. Entire Central Chiller Plant operations such as chillers, towers, pumps, and other related equipment
2. Heating System/Boilers
3. Heat Exchangers
4. Air Handlers
5. VAV Boxes
6. Cabinet Heaters
7. Unit Heaters
8. Fan Coil Units
9. Exhaust Fan Systems
10. Lighting Control
11. ION Metering
12. Generators
13. Any other equipment currently connected to the existing building automation system.
14. NOTE: Additional open-source protocol information provided below
b. All JACE installations shall have WiFi capability disabled with antennas removed and turned in to GSA for disposition.
c. Configurations for all JACE 8000s or JACE 9000’s, including already existing JACEs, shall be configured to have username and passwords networked to the Supervisor. This is a new change to be incorporated as part of the consolidations.
i. NOTE: The only exception to this is the admin account. The admin account shall be exempt from network settings.
ii. Timing of the networked JACEs shall be coordinated with GSA Region 6 Smart Buildings Team to prevent access disruption to the facilities.
iii. All platform usernames and passwords shall be provided by GSA Region 6 Smart Buildings Team ONLY. Contractor is not permitted to furnish their own platform password.
d. NOTE: The installation of any new JACE 8000 or JACE 9000 controllers and related equipment shall include all materials necessary for installation
i. Materials may include, but are not limited to wiring, connections, electrical components, cabinets, network cabling, and other related items
e. NOTE: Where installation of JACE8000 or JACE 9000 controllers occurs, disruption to tenants must be taken into consideration and scheduled with the Building Manager and may be required to be performed outside of normal building operating hours
f. All JACE installations both existing and new shall have the webstart feature disabled on the JACEs to prevent HTML connections to the JACE. All connections shall only allow connectivity via Workbench.
i. This process also allows GSA to only handle one SSL certification per consolidated server as opposed to several for each JACE at each of the locations.
g. It is GSA’s intent to purchase an open system capable of being serviced and expanded by any acceptable system integrator that has and maintains certification (TCP) to work on
Niagara Framework systems. The Niagara Compatibility Statement (NICS) for all Niagara
Software/Hardware shall allow open access and be set as follows: accept.station.in="*" accept.station.out="*" accept.wb.out="*" accept.wb.in="*”. In any case, <GSA Region 6> shall maintain the right to direct contractor to modify any software license, regardless of supplier, as desired by <GSA Region 6>. The Contractor shall not install any “brand specific” software, applications or utilities on Niagara Framework based devices.
h. NOTE: The specific version of Niagara N4 shall be provided prior to the installation of the software. At the draft of this SOW, only version 4.10u1 is approved by GSA IT Security for installation on the GSA Network. Since testing is consistently taking place, a newer approved version may be available prior to installation and GSA will exercise the right to install a more current that is approved by GSA IT Security. No other versions are approved for use on the GSA IT network other than approved. The GSA Region 6 Smart Buildings Team shall provide all of the details on approved versions.
i. Verify the integrity of the controllers after applying the configuration settings
j. NOTE: A separate password to communicate between the Niagara N4 Supervisor and
JACE8000s or JACE 9000’s shall be used for this project. The username shall be “datapasser”. GSA Region 6 Smart Buildings Team to provide the password for the datapasser account as part of this project. Contractor is not permitted to furnish their own password.
k. Provide a list of field level devices attached to each controller
i. List to be provided to the GSA project management team
4. Apply BAS Application Tools to GSA Provided Virtual Server and Workstations
a. Utilize on-site GFE for publishing of BAS controller configuration and system configuration application tools to GSA shared drive
b. Utilize on-site GFE for publishing of BAS logic application tools to GSA shared drive
c. Install and configure all application tools onto GSA provided virtual server
ii. This includes but is not limited to the following examples as applicable to the installed BAS platform:
1. Workbench
a. GSA to furnish a DEMO license after installation of the Niagara
Workbench onto the laptops
2. Licensing
5. Migrate Data Points to the New GSA Provided Virtual Server
a. Migrate existing data points to the existing GSA provided virtual server
i. Ensure proper creation/mapping of end nodes to P04TCM-PW06BAXX
ii. Ensure proper end device configurations to the new server
1. IP Addresses
2. Gateway
iii. Incorporate controllers, gateways, and field devices to the new server
1. Migrated data must include all new JACE8000 or JACE 9000 controllers and incorporated field devices as they are created in the system
2. Migration of devices to occur in stages as programming is completed and points are verified to ensure easy transition to the new server
3. Proper programming shall consist of the following:
a. Relevant data points
b. Device logic
c. Incorporated graphics
i. Graphics shall be migrated and formatted to meet the “Region 6 BAS Graphic Guideline”
ii. Additional graphics related information found below in a separate section
4. NOTE: No new station will be created. The facility will be added to the server and combined with the exiting station. All graphic files will reside on a new folder placed in the Niagara folder.
6. Create New Permissions, Categories, and Navigation Files
a. NOTE: With the consolidation of server and sites, it is vital to maintain proper security between sites. Setup each section as noted below to ensure overall site security is maintained.
b. EXAMPLE Setup/Create Navigation files for each of the following:
i. Eagleton – Existing navigation files to remain the same
1. Navigation file to be named “EAG”
ii. RAY – Existing navigation file to be transferred to primary server and to remain the same
1. Navigation file to be named “RAY”
c. . EXAMPLE Setup/Create Permission Categories as Follows:
i. Permission categories shall be broken down into the categories applicable to the
Central plant, AHUs, and each floor. This breakdown shall be completed for each facility as well. This will effectively create several new categories.
ii. Similar to Navigation files, each location shall be named as follows:
1. EAGLETON = EAG
2. RAY = RAY
iii. Categories shall be broken down and named as follows:
1. (Facility) Plant = Facility Central Plant (all chillers, boilers, pumps, cooling towers and valves associated with the central plant)
2. (Facility) AHUs = Facility Air Handling Units that are feed by chilled water loop and/or hot water loop. Does NOT include DX AHUs that service a small area
3. (Facility) Base = Facility levels with all other BAS connected devices related to the basement levels
4. (Facility) 1Flr = Facility 1st Floor with all other BAS connected devices related to the 1st floor.
5. (Facility) (Floor) = Continue the same process for each floor of each of the facilities.
6. (Facility) Pent = Facility Penthouse and Roof levels with all other BAS connected devices related to those levels.
iv. NOTE: An example of a named category shall be as follows:
1. EAG Plant
2. RAY 1Flr
3. EAG 3Flr
4. RAY Pent
v. After categories are created, associate the related equipment to each of the categories above for each of the facilities. This will allow the ability to fine tune permissions for users and restrict access as needed by specific areas of each facility
d. EXAMPLE Setup/Create Permission Roles as Follows:
i. Permission Roles shall be broken down into separate Read or Write capabilities for each location as well as a couple of dual location roles. This shall allow another level of security measures to protect our facilities.
ii. Similar to Navigation files, each location shall be named as follows:
1. EAGLETON = EAG
2. RAY = RAY
iii. Create the roles as follows:
1. EAGLETON Read Only = EAG Read (Shall Apply to all Categories for the
EAGLETON Building)
2. EAGLETON Read/Write = EAG Write (Shall Apply to all Categories for the
EAGLETON Building)
3. RAY Read Only = RAY Read (Shall Apply to all Categories for the RAY
Building)
4. RAY Read/Write = RAY Write (Shall Apply to all Categories for the RAY
Building)
e. NOTE: For any questions related to permissions, roles, and categories please seek clarification from GSA Region 6 Smart Buildings Team prior to moving forward. It is very important that these security measures are put in place as designed.
7. Programming Requirements for the Building Automation System
a. Graphics
i. Graphics shall incorporate at minimum the information requirements from the “Region 6 BAS Graphic Guideline”
ii. Additional graphics and graphic information may be provided by the building manager and/or the project management staff
iii. Graphics shall be saved at the Niagara N4 Supervisor level
1. Controllers shall be sized properly to store all the requested graphic requirements found in the guideline and based on the amount of field level devices connecting to the controller
b. Programming
i. Provide new programming for air handlers
ii. Provide new programming for variable air volume boxes
iii. Provide new programming for central chiller plant
iv. Provide new programming for heating system and heat exchangers
v. Convert existing metric values to standard values
c. Setpoints
i. Existing setpoints from the previous Metasys system should be recorded and duplicated as part of the new building automation system
ii. Additional set points and set point information may be provided by the building manager and/or the project management staff
iii. Temperature set points shall incorporate, but are not limited to the following:
1. Individual zone set points both occupied and unoccupied
2. Supply air temperatures and resets
3. Supply air static pressure set point and resets
4. CO2 resets
5. VAV Min CFM
6. Chilled water supply resets
7. HX hot water reset
d. Operating Schedules
i. Existing operating schedules from the previous Metasys system should be recorded and duplicated as part of the new building automation system
ii. Additional operating schedules information may be provided by the building manager and/or the project management staff
iii. Schedules shall also utilize the building automation systems and sequencing logic that will be provided by the GSA
1. GSA building automation startup guideline to be provided prior to the start of the implantation process
iv. Existing energy optimization measures shall also be implemented as part of this project
v. GSA provided unoccupied temperature setbacks to be programmed as part of the schedules
vi. NOTE: Schedules should reside on both the Niagara N4 Supervisor and JACE
8000’s or JACE 9000’s and should be synced so that any changes on the Supervisor shall pass down to the schedules on the JACE 8000’s or JACE 9000’s. This is a requirement for disaster recovery.
vii. In the event a disconnection from the server occurs, program the ability to override the schedule at the controller level to allow unoccupied mode to be overridden in order to allow normal building functions.
1. Programming details to be approved by GSA prior to implementation
e. Building startup sequencing
i. Startup sequencing shall include programming for optimal start/stop
f. Naming conventions
i. Naming conventions shall be formatted to meet the “Region 6 Naming Conventions Guideline”
g. Trend data
i. Existing trends from the previous Metasys system should be recorded and duplicated as part of the new building automation system
1. Controllers shall maintain a minimum of 2 weeks’ worth of trend data and backed up to server
2. Servers to maintain trend data for a minimum of 2 years
3. All points currently trended as part of the previous Metasys system
h. Alarm Notifications
i. Existing alarm notifications from the previous Metasys system should be recorded and duplicated as part of the new building automation system
1. This includes the use of alarm notification systems in which emails, texts, or other forms of external communication is used to notify individuals of alarm conditions
ii. Similar to Navigation files, Example for each location shall be named as follows:
1. EAGLETON = EAG
2. RAY = RAY
iii. Example of new alarms:
1. EAG Level 1
2. RAY Critical
3. (Bldg) (Existing Alarm Name)
iv. NOTE: No other changes to take place on alarms other thank renaming to designate which facility they belong to
i. Optimization
i. Existing energy related monitoring information and pertinent point data from the previous Metasys system should be recorded and duplicated as part of the new building automation system
j. If applicable: migration of existing lighting control functionalities
i. Existing lighting controls and pertinent point data from the previous Eagleton system should be recorded and duplicated as part of the new building automation system
k. Migration of miscellaneous building automation functionality
i. Any other miscellaneous building automation functionality that existed in the previous Metasys system should be recorded and duplicated as part of the new building automation system
1. Specific automation functionality shall include the following previous functions as noted in the current Metasys system:
a. AHU button override
b. ION meter integration with alarm and control valves
c. Lighting control
d. Generator
e. Power meter monitoring
2. Additional systems can include but is not limited to:
a. Personal access control systems
b. Fire alarms system functions
c. Elevator/escalator systems
d. Plumbing and water systems
e. Close circuit video systems
l. GSAlink (SkySpark Technology through SkyFoundry)
i. GSA utilizes a tailored SkySpark product produced by SkyFoundary known as
GSAlink. The analytics software program has several points mapped from the existing BAS as a function of the analytics. In order to meet continuation of service requirements, point mapping information will need to be provided as a deliverable.
1. Create a point mapping list of all the equipment to provide as part of the required deliverables
a. Must be a complete list of points and relevant mapping data
b. List to be provided to GSA project management staff and the GSA
Region BAS SME
8. Building Automation System Testing and Verification
a. Validation and testing of overall building automation system for functionality
i. Validation includes verification that all network controllers field level devices are online, and no alarms are present
b. Validation of proper creation/mapping of end nodes
c. Validation and testing of proper accessibility to the logic application tools
d. Validation of proper end device configurations
e. Validation of proper creation of ALL existing historical trends and trend data
f. Validation of proper creation of ALL existing graphic pages and pertinent point data
g. Validation of proper creation of ALL schedules and pertinent start/stop and temperature references
h. Validation of proper creation of ALL energy related monitoring pages and pertinent point data
i. Validation of proper migration of ALL optimization strategies as noted in the previous
Eagleton building automation system
9. Building Automation System Backup
a. Conduct a backup of both the previous Metasys and the new replacement building automation systems which includes the following:
i. Points
ii. Programs
iii. Graphics
iv. Other related data to the BAS
b. Provide a copy of the existing backup data to the following:
i. Eagleton GSA Building Manager
ii. Region 6 Smart Buildings Team
c. Backup media to be provided via CD or DVD media
d. Labeling of the media shall include the date of the backup, location, project number and the software version
10. Conduct Training of Local Staff
a. Provide 40 hours of BAS training to review the system and its operation of the new building automation system
Service Maintenance Agreements:
for the following: Install Service Maintenance Agreements for JACE 8000’s and JACE 9000’s.
1. Contractor to look up the host IDs and provide the correct license and SMA
a. The Region 6 Smart Buildings Team shall be the managers of the VSI and shall use the demo licensing as needed for the region.
i. Should a name be required, Tino Long, the Smart Buildings Program Manager shall be used.
2. It is GSA’s intent to purchase an open system capable of being serviced and expanded by any acceptable system integrator that has and maintains certification (TCP) to work on Niagara Framework systems. The Niagara Compatibility Statement (NICS) for all Niagara Software/Hardware shall allow open access and be set as follows: accept.station.in="*" accept.station.out="*" accept.wb.out="*" accept.wb.in="*”. In any case, <GSA Region 6> shall maintain the right to direct contractor to modify any software license, regardless of supplier, as desired by <GSA Region 6>. The Contractor shall not install any “brand specific” software, applications or utilities on Niagara Framework based devices.
3. Installation of Service Maintenance Agreements
a. Contact GSA R6 Smart Buildings Team by emailing 6pme-bsn@gsa.gov to let the group know the license agreements have been installed.
b. NOTE: Installation of SMAs will be accomplished by the awarded contractor
c. It is GSA’s intent to purchase an open system capable of being serviced and expanded by any acceptable system integrator that has and maintains certification (TCP) to work on Niagara Framework systems. The Niagara Compatibility Statement (NICS) for all Niagara Software/Hardware shall allow open access and be set as follows: accept.station.in="*" accept.station.out="*" accept.wb.out="*" accept.wb.in="*”. In any case, <GSA Region 6> shall maintain the right to direct contractor to modify any software license, regardless of supplier, as desired by <GSA Region 6>. The Contractor shall not install any “brand specific” software, applications or utilities on Niagara Framework based devices.
Installation/Removal of EOL Air Handler Controllers for the following:
1) May include Building Automation System Replacement Verification
a. Conduct a verification of all the controllers and field level devices to determine compatibility of replacing the building automation system from all existing versions to the proposed version.
i. The awarded contractor shall provide a list of all hardware devices that will require installation under this bid
ii. A schedule of affected areas shall be provided to the Government for review and approval, to minimize zone down times and service disruptions
iii. NOTE: Continuity of service in the facility during building occupied hours is mandated throughout the duration of this project
2) Network Diagrams and Sequence of Operations
a. Design network diagrams as related to the design of the new building automation system
i. Network diagrams are a required submittal as part of this project
ii. Approval of network diagrams are required prior to installation of any devices
b. Create sequence of operations (SOO) as related to the design of the new building automation system
i. Building sequence of operations are a required submittal as part of this project
ii. Approval of building sequence of operations are required prior to installation of any devices
iii. Reference existing SOO documentation for the creation of the new SOO document.
Deviation from existing SOO shall be permitted whereas improved functionality will occur resulting in energy reduction and/or improved building automation system control
1. Deviations must be approved through submittal process
iv. Review of proposed SOO shall be conducted through the submittal process and shall include GSA facility management staff, GSA project management staff, and GSA Region 6 Smart Buildings Team
v. NOTE: SOO must be provided for approval prior to any work being performed as part of an initial submittal
vi. Sequence of Operations is a required submittal as part of this project
c. With all Smart Building Projects as with all technology in general, the benefits of the systems are reliant on their use and maintenance. It is critical to consider the lifespan and end user of every system when designing and implementing and building system. Coordination with facility managers, operation and maintenance engineers and other parties invested in the technology should be considered early and often during design stages. Goals of the system use should be agreed upon by the project team in order for the building operators to have targets for building metrics
3) Installation of Air Handler Controllers
a. This applies to all air handler controllers found throughout the facility as it relates to the building automation system
b. Configure TCP/IP information for new Non-preparatory Niagara Edge-10 controllers.
c. This shall include coordination of MAC addresses with Region 6 Smart Building Team.
d. Utilize the most current GSA approved Niagara version.
e. Any and all new wiring and network connections MUST be added by the contractor
f. As applicable: Install new field level controllers on all units to accommodate the additional
DDC outputs
i. Includes new field level controllers on all air handlers
NOTE: The installation of any new DDC devices, sensors, controllers, and related equipment shall include all materials necessary for installation. Materials may include, but are not limited to wiring, connections, electrical components, cabinets, network cabling, and other related items
4) Programming Additions
a. Programming of the DDC controllers shall be incorporated as part of this project
b. GSAlink (SkySpark Technology through SkyFoundry)
i. GSA utilizes a tailored SkySpark product produced by SkyFoundary known as GSAlink. The analytics software program has several points mapped from the existing BAS as a function of the analytics. In order to meet continuation of service requirements, point mapping information will need to be provided as a deliverable.
1. Create a point mapping list of all the equipment to provide as part of the required deliverables
a. Must be a complete list of points and relevant mapping data
ii. List to be provided to GSA project management staff and the GSA Region 6 Smart Buildings Team
5) Conduct Training of Local Staff Provide 40 hours of onsite training to review the system and its operation of the new building automation system.
Removal/Replacement of Preparatory Network VAV Controllers for the following: Replace Preparatory Network VAV controllers.
1) Building Automation System Replacement Verification
a. Conduct a verification of all the controllers and field level devices to determine compatibility of replacing the building automation system from all existing versions to the proposed version.
i. The awarded contractor shall provide a list of all hardware devices that will require installation under this bid
ii. A schedule of affected areas shall be provided to the Government for review and approval, to minimize zone down times and service disruptions
iii. NOTE: Continuity of service in the facility during building occupied hours is mandated throughout the duration of this project
2) Network Diagrams and Sequence of Operations
a. Design network diagrams as related to the design of the new building automation system
i. Network diagrams are a required submittal as part of this project
ii. Approval of network diagrams are required prior to installation of any devices
b. Create sequence of operations as related to the design of the new building automation system.
i. Building sequence of operations are a required submittal as part of this project.
ii. Approval of building sequence of operations are required prior to installation of any devices
iii. Reference existing sequence of operation documentation for the creation of the new sequence of operation document. Deviation from existing sequence of operation shall be permitted whereas improved functionality will occur resulting in energy reduction and/or improved building automation system control.
1. Deviations must be approved through submittal process
iv. Review of proposed sequence of operation shall be conducted through the submittal process and shall include GSA facility management staff, GSA project management staff, and GSA Region 6 Smart Buildings Team
v. NOTE: Sequence of operation must be provided for approval prior to any work being performed as part of an initial submittal
vi. Sequence of Operations is a required submittal as part of this project.
c. With all Smart Building Projects as with all technology in general, the benefits of the systems are reliant on their use and maintenance. It is critical to consider the lifespan and end user of every system when designing and implementing and building system. Coordination with facility managers, operation and maintenance engineers and other parties invested in the technology should be considered early and often during design stages. Goals of the system use should be agreed upon by the project team for the building operators to have targets for building metrics.
3) Installation of Non-preparatory Niagara Edge Controllers
a. This applies to all Niagara controllers found throughout the facility as it relates to the building automation system.
b. Configure TCP/IP information for new Niagara controllers.
c. This shall include coordination of MAC addresses with region 6 smart building team.
d. Utilize the most current GSA approved Niagara version.
e. Any and all new wiring and network connections MUST be added by the contractor.
g. As applicable: Install new field level controllers on all units to accommodate the additional DDC outputs
NOTE: The installation of ANY new DDC devices, sensors, controllers, and related equipment shall include all materials necessary for installation. Materials may include, but are not limited to wiring, connections, electrical.
components, cabinets, network cabling, and other related items
4) Programming Additions
a. Programming of the Niagara controllers shall be incorporated as part of this project.
b. GSAlink (SkySpark Technology through SkyFoundry)
i. GSA utilizes a tailored SkySpark product produced by SkyFoundary known as GSAlink. The analytics software program has several points mapped from the existing BAS as a function of the analytics. To meet continuation of service requirements, point mapping information will need to be provided as a deliverable.
1. Create a point mapping list of all the equipment to provide as part of the required deliverables
a. Must be a complete list of points and relevant mapping data
ii. List to be provided to GSA project management staff and the GSA region 6 smart buildings team.
5) Building Automation System Testing and Verification
a. Validation and testing of overall building automation system for functionality
i. Validation includes verification that all controllers and field level devices are online, and no alarms are present
b. Validation of proper creation/mapping of end nodes
c. Validation and testing of proper accessibility to the logic application tools
d. Validation of proper end device configurations
e. Validation of proper creation of ALL existing graphic pages and pertinent point data
6) Conduct Training of Local Staff
a. Provide 16 hours of onsite training to review the system and its operation of the new building automation system.
BUILDING AUTOMATION SYSTEM REQUIREMENTS
Buildings systems traditionally rely on network management software, application configuration software, system monitoring software and other system software tools for operating and maintaining a building system.
1) Basic Requirements
a. BAS software must be installed in the GSA environment, including server software, client software and any additional tools needed for management and control of the system.
This includes system update tools, network management tools and any software that is used to make changes to the controllers
b. BAS software shall be compatible with the most current version of required standard software and all OS and database software updates (i.e. Microsoft Server, Linux, SQL, etc.)
c. BAS software must be capable of trending and exporting data
d. BAS software shall have multiple user level controls, including administrator, programmer, and users. These user levels shall be capable of an audit to determine operator’s use
e. BAS software credentials shall be unique for every user
f. BAS software shall be installed with a minimum number of licenses needed for system use. In cases of virtual environment installation, the number of licenses required should consider the cases that client use could come from an off-site user
g. BAS client software shall have point and click graphics, configured for system operators, unless a Unified User Interface is included in the project scope
h. BAS software licenses shall be software licenses and not rely on a physical license key or dongle
i. BAS must be licensed to GSA. End user license agreements (EULA) must be approved by GSA IT prior to installation onto GSA equipment
2) Basic Recommendation
a. BAS software should be capable residing on a virtual server and residing on a separate
VLAN from the devices. This software includes the server, client, and management tools
b. BAS client software should be a thin client, allowing for an unlimited number of users to access graphics and system management tools via a web browser on a connected network
c. BAS software should support open protocols, open support structure and open integration for third party software
d. BAS software should integrate to GSA’s Active Directory to ensure unique user accounts and security.
3) Basic Considerations
a. When configuring BAS software for the GSA, the virtual environment of the BSN should be understood, and the system should be configured to best meet the requirements and challenges the BSN produces. This includes the desire of the GSA to build a single server to run all applications needed for building control including server and client software
4) Specific BAS software Salient Characteristics
a. Software shall be compatible and contain the following salient characteristics found in other buildings and shall be adhered to in providing a product solution for the Zorinsky Federal Building.
§ Salient characteristics of building automation platform:
§ Driver framework to include:
§ Basic Driver Framework § Dev Driver Framework § nDriver Framework
§ Scheduling:
§ Hx Scheduler § Wbapplet Scheduler
§ Alarming:
§ Event Service § Hx Alarm Console § Wbapplet Alarm Console § AX Alarm DB Manager
§ Data Trending and Management § Queryable BQL DB § AZ Export Tags § History Transforms § AX Charting § AX History DB Manager
§ User Interface § Built in graphics library § SVG File Format Support § Hx HTML UI Profile § Wbapplet Java UI Profile § BajaScript v1.0
§ Security § Certificate Manager § LDAPv2 § LDAPv3 § Configurable Password Strength Parameters
§ BACnet, LonWorks, Modbus open-source protocols § Virtual server capable using software licenses § Use of Active Directory account logins
5) Open-Source Protocol Requirements
a. Open-source protocol requirements are limited to the following:
§ BACnet § LonMark
b. Open-source devices must conform to existing open-source protocols found within the facility without deviation
c. Because Layer 2 network traffic cannot be effectively managed at this time on the GSA network between subnets, BACnet/Ethernet is expressly prohibited from being implemented on the GSA WAN. BACnet/Ethernet can be used at a given field site, provided all devices are on the same subnet.
d. All device instance numbers associated with a BACnet network must be unique. This can be challenging on the GSA network because a vendor installing a BACnet system is likely not aware of the device instances of other BACnet systems that have devices, which may be discoverable over the GSA WAN
e. To prevent BACnet collisions, systems with BACnet devices communicating on the network must comply with the GSA’s UDP port range requirements. 24 unique UDP ports have been assigned to each region. Vendors must coordinate with the region on any additional details regarding UDP port designations within these ranges as their individual management requirements may differ (building based, vendor based, etc.)
f. Multicasting is not allowed on the GSA WAN, and shall not be applied when configuring a BACnet system on the GSA network
DELIVERABLES
The contractor shall coordinate all proposed work schedules, construction schedules with the GSA representatives upon contract award. Operation and Maintenance manuals and Warranties are due upon completion.
1. Work schedule prior to beginning any work
2. Proper notification for permission to proceed with work
3. Installation of new JACE 8000 or JACE 9000 controllers
4. Installation of Non-preparatory Niagara Edge-10 air handler controllers
5. Installation of Non-preparatory Niagara Edge vav controllers
6. Any and all new wiring and network connections MUST be added by the contractor
7. Network diagrams
8. Programming of air handlers
9. Sequence of operations
10. Create new BAS air handler and vav graphics
11. Post deployment building automation backup of previous and new platforms to the building manager and GSA Region 6 Smart Buildings Team
12. Clearance documents along with ENT credentials
13. All hardware and device submittals for products added to the building automation system
14. All Applicable licenses
15. VSI in GSAs name
16. Post deployment building automation backup of previous and new platforms to the building manager and GSA region 6 smart buildings team
17. Clearance documents along with ENT credentials
18. All hardware and device submittals for products added to the building automation system.
CONTRACTOR DELIVERIES
All deliveries are the contractor’s responsibility. The contractor shall coordinate all project related deliveries to the GSA Point of Contact prior to the delivery, specifying the date and time. Also, the contractor shall be responsible for off and on loading equipment and materials.
SUBSTANTIAL COMPLETION AND FINAL INSPECTION
When the service contract is complete the contractor shall request a final review of documented services to include but not be limited to monthly work progress as identified in the Monthly meeting minutes. Upon receipt of request that service contract is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the service contract from being designated substantially complete.
PROJECTED SCHEDULE
This project shall be allotted 90 days for inspections and initial submittals, 360 days for the completed items and 90 days for final inspection and project close out.
WARRANTY
Contractor shall warrant work, materials, and equipment for a period of one year at minimum and provide additional periods on materials if applicable.