Indoor Firing Range Maintenance Thomas F. Eagleton U.S. Courthouse February 7, 2022
INDOOR FIRING RANGE CLEANING & MAINTENANCE
SECTION: SUMMARY OF WORK
The Contractor shall furnish all necessary labor, material, equipment, and supervision to accomplish the following work for the General Services Administration (GSA), at the Thomas F.
Eagleton U.S. Courthouse, 111 S. 10th Street, St. Louis, MO 63102. All work shall be performed in accordance with following specifications.
Contractors shall visit the site and perform a thorough site inspection. The contractor shall inspect the site to become familiar with the existing conditions relating to the work to be performed and the difficulties and restrictions to the work to be performed. Attendance at the site visit is mandatory to be considered for the award.
The base bid includes all cleaning, preventative maintenance and testing services in accordance with attached scope of work.
The Government reserves the right to order none or any combination of the line item. No minimum quantity for the line item is guaranteed by the Government.
The Offeror must demonstrate successful past performance and experience within the past three
(3) years of the issuance of this Solicitation for two (2) projects of similar size, scope, and complexity as that set forth in the Statement Work. The Offeror may rely on its own experience or that of its joint venture partner(s) and/or subcontractor(s) that will perform major or critical aspects of the requirement. The Offeror shall submit Customer Surveys with the following data/information for the projects submitted:
• Project title;
• Location;
• Contract Award Date;
• Date of Completion;
• Size refers to the dollar amount of contract at award;
• Scope refers to the type of work performed and
• Complexity refers to the difficulty of the scope.
Contractor will be responsible for disposal of all material as hazardous waste unless TCLP testing analysis shows lead content is less than 5.0 micrograms.
SECTION: SERVICES, ORDERING AND PRICES
Bid / Offer for Standard Services
0001 Quote a price for providing the cleaning, preventive maintenance and testing services in accordance with the following specifications.
February 7, 2022
$____________ per year
Bid / Offer for Above Standard Services
0002 Quote a price per panel to replace damaged noise insulation. Existing noise insulation is Pinta Acoustic Colortec (black). New material will be contractor furnished.
$____________ per panel
0003 Quote a price to remove ballistic rubber wall panels and install Dura Panel or similar ballistic rubber material. Range wall is approximately 100’ long by 8’ high. New material will be contractor furnished.
$____________ per job
0004 Quote a price to rearrange and replace government supplied Dura Blocs as required by manufacturer. Price shall include all costs for the installation and disposal. New material will be government furnished.
$____________ per job
0005 Quote a price to provide and install one set of pre-filters. Price shall include removal and disposal of used pre-filters as hazardous waste. One set of pre-filters includes (12) each HE40 Purolator pre-filters - 24" x 24" x 2" Merv 8.
New material will be contractor furnished.
$____________ per set
0006 Quote a price to provide and install one set of HEPA filters. Price shall include removal and disposal of used HEPA filters as hazardous waste. One set of HEPA filters includes (12) each – 24” x 24” x 12”. HEPA filters shall have a minimum MERV17 rating (99.97% capture efficiency at 0.3 µ IEST type A). New material will be government furnished.
$____________ per set
SECTION: WORK RESTRICTIONS
CONTRACTOR USE OF PREMISES: During the construction period the Contractor shall limit use of the premises to the work area indicated, to allow for Government occupancy and public use. The following guidance shall be adhered to:
1. Prior to construction, provide a written list of employees and subcontractor employees that will be working within the building during the contract period to the Building Manager or Contracting Officer’s Representative (COR).
February 7, 2022
2. Keep entrances serving the premises clear and available at all times to the Government, Government employees, and visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time required for storage of materials and equipment on site.
4. Take precautions to protect the building, its occupants, and the public during the construction period. The Contractor is responsible to provide all labor and materials for dust control, provide adequate barriers to prevent Government Employees or the public from entering the construction area, all signage indicating necessary requirements for entering the construction area, and any other precaution necessary to provide a safe environment for Contractor personnel, Government employees and the public.
5. Space on the premises will be made available for the Contractor’s storage and related activities, provided that its use will not interfere with the operation of the Government.
Arrange and gain approval for the use of this space through the Building Manager or the Contracting Officer’s Representative.
6. Daily issuance of keys and / or key cards will be provided by an on-site GSA field office representative. Keys will only be issued to the General Contractor unless the General Contractor provides a list of sub’s authorized to sign for keys. Keys will only be issued to people that have received a favorable HSPD-12 security clearance. Keys must be returned to the GSA office daily.
7. Use of the loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis.
8. No apparatus with an open flame, grinding that creates sparks, or grinding that creates excessive dust is allowed to be used within the facility without prior receipt of a burn permit. Burn permits are required for each separate occurrence. Burn permits will be issued on a daily basis by a GSA representative.
CONTRACT PERIOD: All work shall be completed within (180) calendar days of notice to proceed.
WORKING HOURS: Work shall be completed during normal working hours of 7:00 AM & 4:00 PM Monday through Friday.
All work shall be scheduled through the Building Manager or their representative at a minimum of two weeks advance notice. Work shall be performed in a manner to avoid disruption of court proceedings.
SECTION: SUBMITTALS AND SUBSTITUTIONS
SUBMITTALS: Contractor shall provide submittals to the Project Manager or COR for approval within 10 days after receiving notice to proceed. No work shall proceed until submittals are approved by the COR. The Contractor shall submit for review to the COR prior to demolition, purchase, fabrication, or installation of materials.
February 7, 2022
1. Comprehensive work plan detailing the work to be accomplished and chronology, safety and health plan, and insurance certificate
2. Contaminated materials packaging, transport and disposal plan
3. Recyclable metals packaging, transport and recycling facility
4. Standard Operating Procedures (SOPs) for IFR cleaning
5. Past personal air sampling per OSHA 29 CFR 1910.1025(d)
6. Contractor approval list
PRODUCT SUBSTITUTIONS: An Offeror who proposes to submit a quote based on an alternate or substitute construction material shall provide a sample of the alternate material with cut sheets, warranty, maintenance data, and sufficient technical information to ensure the material meets all salient characteristics of the building materials specified in this specification with their quote. The alternate or “equal” material information and material sample must be provided on or before the due date of the Request for Quote (RFQ).
SECTION: QUALITY REQUIREMENT
All work performed to accomplish the work specified herein shall be in strict compliance with the manufacturers’ written recommendations and all nationally or locally recognized governing bodies. Qualified installers shall install each category of work. Contractor shall without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of this work. If two codes are in conflict, the most stringent will be applied.
All work to be performed under this contract shall be executed in a careful and orderly manner by workmen skilled in their respective trades or class of work. The work shall consist of furnishing and installing all new work and doing all necessary removing, patching, filling-in, repairing, and altering of existing work specified to be performed. The materials and methods of application for new work and for patching, filling-in, and repairing shall be similar and equal quality in its new state and shall be installed in compliance with standard trade practices.
All work shall be completed in compliance with Building Standards. Lists of Building Standards are available in the Field Office upon request.
SECTION: TEMPORARY FACILITIES AND CONTROLS
UTILITY SHUTDOWN: All utility (electrical, water, sanitary, sprinkler, or HVAC) shutdowns must be scheduled with the GSA Building Manager or the COR, at a minimum of seventy-two
(72) hours in advance, and may be required to be completed after hours.
SECTION: EXECUTION REQUIREMENTS
All work must be performed by the Contractor unless noted otherwise.
February 7, 2022
WORKMANSHIP STANDARDS: The Contractor shall ensure that personnel performing tasks required under this contract are skilled and knowledgeable in the methods and craftsmanship needed to produce journeymen level of workmanship. Remove and replace work that does not comply with workmanship specified and standards recognized in the construction industry for the applications indicated. Any work performed by the Contractor that is found to be faulty or fails to meet acceptable construction standards shall be removed and replaced by the Contractor at no additional cost to the Government.
1. Manufacturer's Instructions: Where installations include manufactured products, comply with manufacturer's applicable installation instructions and recommendations to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in the Contract Documents.
2. Specialists: Where the individual sections of the specifications require specialists to perform the work, comply with the requirements specified. The assignment of a specialist shall not relieve the Contractor of installation in accordance with all manufacturers’ written instructions and all nationally or locally recognized governing bodies.
3. Measurement Verification: It is the Contractor’s responsibility to verify all dimensions and job site conditions, and order sufficient material to perform the job. Contractor shall be responsible for the accuracy of the measurements of total square footage.
CLEAN-UP: The Contractor shall be responsible for removal and legal disposal of all debris created by the work specified herein from the premises. The Contractor shall clean up the immediate area on a daily basis and must keep the area safe at all times.
SECTION: CLOSEOUT
SUBSTANTIAL COMPLETION is defined as that state when the Contractor has complied with the Contract Requirements, except for minor deviations, and the project is sufficiently complete and capable of being occupied and used by the Government for the intended purpose.
INSPECTION PROCEDURES: On receipt of the Contractor’s request for inspection, the COR or government designated representative will either proceed with the inspection or advise the Contractor of unfilled requirements. If the Contractor is aware of any unfilled requirements prior to the inspection, the Contractor shall provide a list of incomplete items with a reason work is not complete. The COR will notify the Contractor once the project is substantially complete. This does not relieve the Contractor from correcting all punch list items. The Government may withhold funds until all items included in the Contract have been successfully completed.
SECTION: RECORD DOCUMENTS
Contractor is required to provide record documents as noted below:
February 7, 2022
1. USMS Final Report
FINAL CLEANING: Employ experienced workers or professional cleaners for final cleaning.
Clean each surface or unit to the condition expected in a normal, commercial cleaning and maintenance program. Comply with the manufacturer’s instructions. Remove all temporary protection or facilities installed for the protection of new work and all barriers erected around the construction area for dust control, noise, fall protection, or any other barrier that was required for construction.
SECTION: SUSTAINABLE DESIGN REQUIREMENTS
GENERAL PHILOSOPHY: The General Services Administration (GSA) is committed to the purchase and use of environmentally sustainable products and services. “Green purchasing” is the procurement of sustainable products and services that contain recycled/recovered material(s);
are bio-based and/or non-ozone-depleting; are energy-efficient or water-efficient (are certified ENERGY STAR and/or Water Sense); contain chemicals that are less ozone-depleting or hazardous; or have other sustainable attributes.
REQUIREMENTS FOR VENDORS/CONTRACTORS: Vendors/Contractors are required to consider and use “green (sustainable) products” if at all possible when providing any goods and/or services to the GSA.
The only three (3) exceptions to the requirements for “green products” are:
1. Unavailability
2. Products meeting the requirements do not satisfy performance requirements
3. The green product is only available at an unreasonable price.
Any exception must be documented and discussed with your GSA Contracting Officer prior to submission of your offer/proposal. In the case of unreasonable pricing, the price of the green product must be furnished and compared to the price of the product proposed for use. If you have questions regarding this please contact your GSA Contracting Officer.
SECTION: CLEANING
Contractor must submit as a minimum, a comprehensive work plan detailing the work to be accomplished, chronology, safety and health plan, insurance certificate; contaminated materials sampling, packaging, transport and disposal plan; recyclable metals packaging, transport and name of recycling facility(s).
The contractor’s work plan must be approved by the GSA Contracting Officer (GSACO) or Contracting Officer’s representative (GSACOR) and shall be reviewed by the USMS IFR coordinator at USMS HQ prior to start of on-site work. Contractors must demonstrate their compliance with Federal and State health and safety regulations including, but not limited to 29 CFR 1910.1025 – Toxic and Hazardous Substances, Lead. Also, contractor Standard Operating Procedures (SOPs) for IFR cleaning shall be provided along with past personal air sampling
February 7, 2022
(Personally Identifiable Information (PII) redacted) per OSHA 29 CFR 1910.1025(d). These documents including the contractor’s work plan shall be reviewed by the USMS IFR coordinator at USMS HQ prior to initiating work.
A. Cleaning Requirements – General Requirements
● All personnel shall be trained and certified in accordance with regulatory lead hazards and shall also be trained and certified in accordance with applicable local environmental cleanup requirements.
● The IFR ventilation system shall be on during all maintenance and cleanings.
● Place walk-off sticky mats just outside of all access/exit doors to the IFR.
● Collect spent brass shells in 2 to 5 gallon sealable bucket(s) labeled “brass only”. Collect spent lead in in 2 to 5 gallon sealable bucket(s) labeled “lead only”. Store buckets in a secure area (i.e. bullet trap room if available) until the disposal/recycling pickup.
● Inspect, clean and maintain firearm accidental discharge clearing trap per manufacturer’s recommendations.
● Cleaning of the range areas will be done in a sequential manner to minimize the spread of dust (i.e. from clean to less clean - start cleaning from the control room side moving towards the backstop and backstop access area.
● Wet wipe with a lead specific cleaner all surfaces in the firing range, control room, gun cleaning area, storage room, secured storage room, and backstop service room (if present) including; but not limited to walls, baffles, ceilings, firing lane partitions, target rails, backstop, bullet trap, doors and knobs, light switches, countertops, shelves, exhaust filter frames/housings, ducting, etc.
● Floors and surfaces that are not smooth and, consequently, cannot be wet wiped shall be HEPA vacuumed. This will include all noise reduction insulation (i.e. walls and ceiling).
HEPA vacuum all areas within 15 feet outside of bullet trap access door and any range exit doors.
● Verify that all alarms and fan interlocks are working properly and document any issues on the Table 4 - Inspection Checklist .
● Inspect signage, lighting, targeting systems, storage areas, and cleaning facilities associated with the IFR. Repair if possible, any signage, lighting, storage areas, and cleaning facilities.
Clearly document any identified damage or items needing repair on the Table 4 - Inspection Checklist notes section.
● Dura Block Type backstop o Inspect the Dura Blocks for excessive damage, o Replace heavily damaged Dura blocks, and o Move lightly to moderately damaged Dura blocks to perimeters of backstop.
● HVAC System and Filters o Determine the pressure drop for each filter level including pre-filter and HEPA filter.
o If there are no pressure sensors installed to measure pressure differential before/after filter levels, sensors must be installed or portable monitors used.
� The installed pressure sensors shall feed to the DDC of the IFR (if applicable).
� If only one (1) pressure differential sensor is installed to measure the pressure drop of both the pre-filters and final filters and the pressure drop is significant, February 7, 2022 replace the pre-filters and check full pressure drop of both filter sections combined.
o Measure full volumetric exhausted airflow (cfm).
� Calculate airflow (cfm) for each HEPA filter. Use this number to compare to filter manufacturer’s pressure drop vs. airflow volume to determine change out requirements.
o Replace HVAC filters (pre-filters and/or HEPA) only if there indicates a pressure drop more than twice the manufacturer’s pressure drop for the designed air flow (i.e. 1” wg @ 2400 cfm for HEPA filters).
o Filters requiring replacement per above will be replaced by GSA-furnished filters that meet the specifications of USMS Publication 64, Section A10.2. The filters shall consist of a pre-filter stage of a minimum MERV 8 rating followed by a final filtration stage.
Final HEPA filter(s) shall have a minimum MERV 17 rating (99.97% capture efficiency at 0.3µ IEST type A).
o Wet wipe the inside of the exhaust filter housing if potential exists for contamination .1
B. Verification of Cleaning
The Contractor is responsible to provide services of an independent Certified Industrial Hygienist (CIH) to conduct proper surface sampling protocol to complete the following:
● Collect surface wipe samples based upon the table below, as a minimum of 15 locations and an adequate quantity of Quality Assurance/Quality Control samples.
● Sampling locations and sample results criteria are detailed in the following table:
Table 1 - Lead Sampling Locations
Description (quantity) Criteria (µg/ft2)
• Top of target rail(s), 10’ downrange (3 - 4) 800
• Floor midway down range, 1 range center and 1, 1’ from side wall, (2) 800
• Within 3’ of front of the bullet trap, 1 range center and 1 - 1’ from side wall, (2)
• Storage room floor, (1) 200
• Gun cleaning area floor and table, (2) 200
• Floor within 5’ outside the entrance to range. If carpeted, 5’ high, exterior wall adjacent to IFR access door may be sampled. (1)
• Floor immediately outside downrange or bullet trap door (if applicable), (1)
• IFR exhaust duct discharge grills, (1) 200
• Firearms instructor’s control room desk and floor, (2) 200
1 It is mandatory to lock out tag out all potential energy sources which may cause the exhaust fans to turn on while workers are in the fan housing.
February 7, 2022
• Floor inside rear backstop access area (if applicable) (1) 200
• Floor at each of the firing positions, 1 central each lane (3 - 4) 200
• Fire lane dividers, 4’ high, left or right (3 – 4) 200
● Send all samples for analysis to a laboratory approved by the American Industrial Hygiene Association and recognized by the National Lead Laboratory Accreditation Program (NLLAP) as being proficient in lead in dust analysis.
● Surface contamination by lead shall be evaluated using ASTM E1728-03 methods.
● Cleaning Criteria: If any of the wipe sample analyses indicate levels exceeding the clearance standard as described in the above table, the Contractor shall clean that area again where those surface samples were taken and have the surfaces sampled again by the independent CIH and verified until the clearance standards are met.
C. Measurements and Evaluations
The Contractor is also responsible to provide services of an independent Certified Industrial Hygienist (CIH) to conduct proper airflow and pressure measurements and evaluations based upon applicable protocol to complete the following:
● Measure and document all pressure differentials (pd) between the different zones (as applicable by IFR design) using as a reference, the Figure 1 – Indoor Firing Range Top-view Zones, Sensor and Vent Locations as an example of pd reading locations. Record these pd’s on the Figure 2 – Lead Sample References, Sampling Locations and PD Template and include in final report.
● Measure and document airflows using procedures described in the following section.
Document and/or sketch those tests for 1) each lanes respective three firing positions, 2) mid-lane locations, midway between firing lines and bullet trap for each firing lane, and 3) mid-lane locations within 6 feet of front of bullet trap for each firing lane and document the results in the Figure 3 – Air Flow Pattern and Velocity Templates and include in final report.
● Evaluate and document air flow patterns at each lane’s respective three (3) firing positions.
Document those results on Figure 3 – Air Flow Pattern and Velocity Templates and include in final report.
● Verify that all alarms and fan interlocks are working properly and document any issues on the Table 4 - Inspection Checklist .
● Inspect signage, lighting, targeting systems, storage areas, and cleaning facilities associated with the IFR. Repair if possible any signage, lighting, storage areas, and cleaning facilities.
Clearly document any identified damage or items needing repair on the Table 4 - Inspection Checklist notes section.
● Complete, initial and sign Table 4 - Inspection Checklist .
D. Air Pathway Testing and Airflow Velocity Procedures
Smoke testing and airflow velocities of the lane’s shooting positions shall be conducted in a standard procedure. The following procedures shall be followed as closely as possible:
● Sampler shall position their bodies as would a shooter at each lane and each of the three shooting positions – standing, kneeling, and prone.
February 7, 2022
● The sampler shall locate the smoke generator at the locations where the guns will be discharged (i.e. hold smoke generator with arms outstretched in front of shooter for approximately 10 seconds) for each of the locations and positions listed in #1 above. Allow for normalization of position (about 10 seconds) before recording smoke movement in sketch.
● Please provide a sketch of the smoke movement from each lane and the 3 positions.
o Ideal sketch will use three colors, one color each for the shooters/samplers positions.
o Green color indicating standing position, blue indicating kneeling position, and red indicating prone position.
o Smoke movement lines should be sketched onto the diagrams provided.
o These sketched lines should start on the diagrams from the shooting location (estimate) and be drawn through to the perspective where the smoke disappears or becomes too diluted to observe. The length of the sketched lines should proportionally estimate the actual length and direction(s) the smoke traveled onto the provided diagram (i.e. a 4’ actual is equal to about 1/2” on diagram).
● Record airflow velocities (fpm) in the breathing zone of the shooter (or sampler) for each of the lanes/positions indicated in #1 above. Breathing zone is identified as within approximately 1 foot of the nose/mouth, preferably to the side in this case.
● Downrange airflow velocities (fpm) (mid-range and in front of backstop) should be taken in the middle of each lane, approximately midway from the floor to the bottom of the ceiling baffles.
● Supply air volumetric measurements (cfm) should be taken at the outside air supply vent using applicable procedures for accurate measurements.
● Exhaust air volumetric measurements (cfm) should be taken at the final outside air exhaust vent using applicable procedures for accurate measurements.
o If this is not a single pass HVAC system (i.e. with return air ducting, shared ventilation with other areas, etc.) please note on Table 4 - Inspection Checklist notes section.
E. Final Report
The contractor must submit a final report package to the GSA Contracting Officer. The report templates and format are included in Attachment A. The GSA Contracting Officer shall provide the local USMS representative (i.e. Range Master) and the USMS HQ OSSH’s IFR Coordinator, the following information prior to allowing use of the firing range. The firing range shall not be used until approval by authority of the USMS HQ as represented by final signature on the Table 4
- Inspection Checklist
• Tasks completed,
• Completed and fully approved and signed Table 4 - Inspection Checklist including condition of the baffles, bullet trap, lighting, alarms, fan interlock, targeting system, etc.,
• Sample reference and sampling locations documented on Figure 2 – Lead Sample References, Sampling locations and PD Template.
• Laboratory certifications along with final samples analyses report,
• Pressure differential readings for each zone while ventilation is operating documented on
Figure 2 – Lead Sample References, Sampling Locations and PD Template, February 7, 2022
• CIH completed Figure 2 – Lead Sample References, Sampling Locations and PD Template and Figure 3 – Air Flow Pattern and Velocity Templates.
• Brand, model #, quantity and specifications (i.e. manufacturers cfm and pressure drop) for any filters installed,
• Weight and price of lead and brass recyclable metals with proof that the total amount was recycled and value refunded to government,
• Legibly completed and signed manifest for hazardous waste with weights and disposition of waste specified, and
• Results of any TCLP testing done and description of tested items for hazardous waste (if applicable).
F. Environmental
Indoor Firing Ranges produce various levels of recyclable materials and/or hazardous waste. The principle hazardous waste includes lead contaminated materials. All efforts shall be made to reduce the monthly hazardous waste stream to less than 220 pounds. Generators of less than or equal to 220 pounds per month of hazardous waste are considered Conditionally Exempt Small Quantity Generator under current EPA standards. Conditionally Exempt Small Quantity Generator are typically subject to lower levels of regulations than those of Small or Large Quantity Generators. Hazardous waste may include lead contaminated HVAC filters, Dura blocks, target debris, tacky mats, lead contaminated soiled rags, disposable wipes, HEPA vacuum filters, HEPA vacuum dirt container, used personal protective equipment, etc. HEPA filters and Dura blocks represent the largest quantity by weight of contaminated wastes as spent lead bullets and shell casings are recycled.
● Disposition of Collected Spent Lead and Shell Casings o Spent lead bullets and shell casings shall be recycled.
o Cleaning contractor(s) shall collect the spent lead bullets and shell casings and deliver to a recycling facility.
o Cleaning contractor(s) shall sell the spent lead bullets and shell casings and deduct the proceeds from the cleaning invoice.
o An official receipt of sale for the recycled lead bullets and shell casings shall be provided as evidence of recycling and value deducted from cleaning invoice.
G. Recycling
All efforts shall be used to minimize weight of hazardous waste generated. To that goal, all efforts shall be made to recycle all rubber components of the target range backstop including Dura blocks, granulated rubber, rubber bladders, etc. All efforts shall be made to change out HEPA filters only when necessary and as prescribed in this document.
H. Hazardous Waste
Collect lead contaminated HVAC filters, target debris, tacky mats, soiled rags, disposable wipes, HEPA vacuum filter, HEPA vacuum dirt container, used personal protective equipment, and all other contaminated waste and store in a solid container durably labeled
February 7, 2022
“lead contaminated waste.” This containers label shall also identify the weight of the wastes and the date of generation to use for calculating generation rates.
● These wastes shall be either delivered to or picked up by a certified hazardous waste transport, storage, and disposal facility during Comprehensive maintenance.
● These wastes shall be properly packaged, labeled and temporarily stored until the next disposal if collection was done during housekeeping cleaning.
● Weight of all lead contaminated wastes shall be documented on the Table 4 - Inspection Checklist .
Figure 1 - Indoor Firing Range Top-view Zones, Sensor and Vent Locations
Table 2 - IFR Zone Description and Use
Color Zone Description Exhaust % of supply air Zone 0 Outside Garage/outdoor pressure
Zone 1 Public areas, administrative offices, garage, etc.
Building static pressure. Supply, return, and outside air rates based upon ASHRAE standards.
Zone 2
Support room, locked storage, control room, etc. Areas where air should be relatively clean with minimal contamination by firearms due to cleaning, breakdown.
Exhaust air rate 5% greater than outside air supply rate.
February 7, 2022
Zone 3 Corridors, airlock, etc. area provided to preserve the hermetic pressure of the shooting range.
Exhaust air rate 10% greater than outside air supply rate.
Zone 4 Area of highest potential of airborne hazards due to firearm discharge, cleaning, etc.
Exhaust air rate 15% greater than outside air supply rate.
Table 3 - IFR Sensor Description and Use
Sensor Description Location of pressure sensor(s)
Measures pressure differential between zone 2 support room and/or control room with zone 1, administrative/public area spaces.
Must measure that support room and/or control room have negative pressure compared to administrative/public zone 1.
Measures pressure differential between support room and/or control room and airlock into the firing area
Must measure that zone 3, airlock have negative pressure compared to support room and/or control room.
3 Measures pressure differential between control room and the firing area
Must measure the pressure differential between the firing area and control room.
Measures pressure differential between the firing area and either the garage, administrative and or public areas.
Must measure pressure differential between the zone 4 (shooting area) and either zone 1 or zone 0 (outside pressure)
February 7, 2022
Attachment A – Final Report Templates
Date of Completion: _____________
UNITED STATES MARSHAL SERVICE
INDOOR FIRING RANGE MAINTENANCE REPORT
Building Name:
Address:
Range Master:
Phone:
GSA COR:
Phone:
Contractor:
Contact Name:
Phone:
Tasks Completed
Table 4 - Inspection Checklist
Inspection Checklist for Post-IFR Comprehensive and Cleaning
Date: District: Address:
Explain in notes sections for all “No” or “N/A” answers recorded
Inspection Criteria Contractor
Initials CIH Inspector
Initials
SECTION I – CLEANLINESS INSPECTION
1. All floors and horizontal surfaces inside the firing range, control, entry, gun cleaning and storage rooms have been wet-wiped/mopped with lead specific cleaner or HEPA vacuumed.
2. All cartridges, bullets and bullet fragments and other shooting related debris have been removed and collected including within, under and behind the bullet trap/backstop.
3. The following areas were inspected for settled dust on floor, benches, and other horizontal surfaces. No settled dust was observed.
a. Top of target rails
b. Midway down range
c. Front of the bullet trap
d. Storage room
e. Gun cleaning areas
f. Firearms instructor’s control room
g. Within 15’ outside the entrance to range
h. Within 15’ outside downrange or bullet trap door
i. IFR exhaust duct
j. Firearms instructor’s control room
4. (If applicable) Rubber granules in the bullet trap were redistributed as necessary (Comprehensive & Housekeeping) and rubber bladder patched or replaced (Comprehensive).
SECTION II – SURFACE SAMPLING RESULTS
5. Surface dust was sampled in the following locations: results did not exceed specified micrograms per square foot (µg/ft2). A diagram of sampling locations and laboratory results are attached.
a. Top of target rail(s), 1 central and 1 side (2) 800(µg/ft2).
b. Midway down range, 1 center and 1 side, 1’ from wall (2) 800(µg/ft2).
c. Within 3’ of front of the bullet trap, 1 center and 1 side, 1’ from wall, (1) 800(µg/ft2).
d. Storage room floor, (1) 200(µg/ft2).
e. Gun cleaning area floor and table, (2) 200(µg/ft2).
f. Firearms instructor’s control room desk, (1) 200(µg/ft2)
g. Floor within 5’ outside the entrance to range. If carpeted, adjacent wall may be sampled.
(1) 200(µg/ft2).
h. Floor immediately outside downrange or bullet trap door, (1) 200 (µg/ft2)
i. Interior of IFR exhaust duct discharge, (1) 200(µg/ft2).
j. Firearms instructor’s control room desk, (1) 200(µg/ft2).
SECTION III – OPERATIONAL INSPECTION
6. The baffles, bullet trap, and targeting system components were inspected for wear, damage, and proper function. Any uncorrected deficiencies are noted in the “Notes” section.
SECTION IV – ENVIRONMENTAL
7. All wastes generated as part of this contract were properly collected, tested, packaged, and disposed of IAW local and/or US
EPA waste laws. Bullet casings, lead slugs and rubber backstop materials were recycled.
8. All wastes, bullet casings and lead slugs generated as part of this contract were properly collected, sealed in labeled buckets and properly stored until disposal.
SECTION V – VENTILATION INSPECTION
9. Pressure differential for the pre-filter and HEPA filters was measured and found to be:
Pre-filter ____”wg, HEPA ____”wg, which were Pre-filter_______%, HEPA ________%, of manufacturer’s recommendations (2x).
10. The following exhaust air filters were changed out and new filters installed with the following quantities and models: #___ Pre-filter____________, #___ HEPA _____________
11. Air flow immediately behind the firing line was tested using smoke candles and was found to proceed downrange to the bullet trap without reverse currents, significant turbulence or dead spots at any location.
12. Average air velocity measurements at the firing line were found to have a velocity of ________ feet per minute (fpm) (between 50 – 75 fpm is recognized as adequate with no measurement outside this range).
13. Average air velocity measurements midway down the firing range was found to have an average velocity of ________ fpm. (A minimum of 30 fpm is recognized as adequate.)
14. Average air velocity at the bullet trap was found to have a velocity of ________ fpm. (A minimum of 30 fpm is recognized as adequate).
15. The percent surplus of exhaust to supply volumetric airflow for each zone was measured and determined to be: zone 2 _______%, zone 3 _______%, zone 4 _______%.
16. The pressure differential of the zone 2 of the firing range relative to zone 1 of the building spaces immediately outside the range was measured and found to be ________ inches wg. (A minimum pressure differential of -0.03” wg is recognized as adequate).
17. Any air leaks identified that could allow contaminated air to escape the firing range? Any evidence of leaks of contaminated air from the IFR (i.e. smells, dust staining) outside of IFR?
SECTION VI - SUMMARY
Based upon the cleaning, testing and observations made during the work accomplished under this project, it is recommended the range be classified as follows (a classification of “Limited Use” or “Unsafe” will be explained in the “Notes” section.
☐ Safe ☐ Limited Use ☐ Unsafe
☐ Safe ☐ Limited Use ☐ Unsafe
SECTION VII – NOTES
Range Master Signature: Date:
USMS HQ Signature: Date:
Figure 2 - Lead Sample References, Sampling Locations and PD Template
• Laboratory certifications along with final samples analyses report
Figure 2 - Air Flow Pattern and Velocity Templates
Table 5 - Airflow Measurements Documentation
Shooting positions Range positions Total air volumes
Lane 1' Prone
3' Kneeling
5' Standing
Midway firing line/ backstop
5' front of backstop
Air supply (cfm) @ intake*
Air exhaust (cfm) @ exhaust*
NA NA
NA NA
NA NA
NA NA
*Misc.
Notes:
*Measurements of total volumetric airflows may be done using the measured ESP at both the supply fan and exhaust fan locations. Volumetric airflow can then be calculated using the fan manufacturer’s airflow / fan speed curves.
• Brand, model #, quantity and specifications (i.e. manufacturers cfm and pressure drop) for any filters installed
• Weight and price of lead and brass recyclable metals with proof that the total amount was recycled and value refunded to government
• Legibly completed and signed manifest for hazardous waste with weights and disposition of waste specified
• Results of any TCLP testing done and description of tested items for hazardous waste
Table 6 - HVAC Filter Change-Out Maintenance Tasks Company:
Technician:
Phone #:
Company wo:
Date:
ACTIVITY
• Check unit and record any unusual bearing noise, vibration, odor, corrosion, and structural damage.
• Throw unit power disconnect switch to off position. Use appropriate Lock Out/Tag Out
(LOTO) procedures and lockout tools to assure power isn’t initiated accidentally.
• Install new filters if pd for filter stage is greater than 2x manufacturers recommendations for the specified airflow. Record filter information. Replacement with filters in accordance to USMS Pub 64.
• Remove old filters and place into white plastic garbage bags.
• Mark garbage bags as lead containing waste and follow USMS Pub 64 for disposal/recycle.
• Check that filter doors and access panels are secure with no air leakage. Repair seals as needed.
• Throw unit power disconnect switch back to the on position. Use appropriate LOTO procedures and appropriately remove lockout tools and tags.
• Clean up and secure work area.
Supply/Exhaust Stage Manuf. Model/Dimensions Manuf . CFM/pd Quant.
Remarks:
Technician's Signature: Date:
Range Master Signature*: Date:
*Range Master Signature only signifies receipt of documents and termination of work, not completeness or quality of work.