This document contains details of a pre-proposal conference for a federal design-build solicitation. The solicitation is for design-build services for renovations to the parking garage at the Patrick V. McNamara Federal Building in Detroit, Michigan. The renovation project includes concrete repair and replacement, improvements to storm drainage and mechanical, fire and life safety, and electrical systems. The solicitation will utilize a two-phase qualifications-based procurement process, with phase one evaluating technical qualifications and past performance, and phase two involving a technical proposal and price proposal from a shortlist of up to three firms. Questions are due by August 14th and phase one proposals are due September 22nd, with award planned for August 2024 after concept reviews and interviews in phase two. The General Services Administration is the contracting agency overseeing the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment 001 is issued to provide the pre-proposal conference agenda (attached), provide the pre-proposal conference invitation with contact information (attached), and to correct Section I.B. of the Solicitation to "A maximum of 3 firms will be selected to submit Phase 2 proposals."

Capital & Customer Projects Contracting Branch 230 S Dearborn St Chicago, IL 60604 USA

47PF0023R0059

1 6

08/18/2023

07/21/2023

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

PreProposal Conference Agenda GSA Solicitation No. RFP 47PF0023R0059 Time/Date: 9:30 AM CST, Aug 8, 2023 Location: Virtual

The purpose of this Pre-Proposal Conference is to discuss the Phase I Request for Proposal (RFP), issued on July 21, 2023, for Design Build Services for the Patrick V. McNamara Parking Garage Renovation in Detroit, Michigan.

The goal of this Conference is to answer any questions regarding Phase I of the RFP, provide an understanding of the proposal structure, as well as a brief overview of the proposal submission requirements, evaluation criteria, and present the scope of work for the PVM Parking Garage Renovation.

A copy of the agenda and sign in sheet will be emailed following the discussion. The agenda and sign in sheet are not intended to reiterate everything discussed in the meeting, but identify those points that may affect an offerors’ understanding of the solicitation.

Please be aware that no oral statement made by the Government Representatives during the conference will have the effect of amending the solicitation. In the event that discussions during the conference indicate a need to change the solicitation, an amendment to the RFP will be issued in writing. All amendments must be acknowledged by the time/date proposals are due.

Currently, there are no amendments to the solicitation.

AGENDA

Introductions

● Contracting Officer: Jennifer Styzek

● Project Manager: Chris Giacalone

● COR: Brad Taplick

● Property Manager: Brian Green

Mike Bogue Dan Essenmacher Patrick Russell

● CMa Procon Consulting

Project Background & Overview of the Scope of Work

● The parking garage is a contributing structure to the Patrick V. McNamara Federal Building (1972). GSA has determined that the Center is eligible for listing in the National Register of Historic Places (NRHP). As such, GSA treats these buildings as if they are listed in the register so Section 106 of the Historic Preservation Act applies, and Secretary of the Interior’s Standards must be complied with.

● It will include concrete repair and replacement, improvements to the storm drain system, mechanical infrastructure, fire & life safety systems, EV charging stations, and electrical and lighting systems.

● The existing parking garage is a five-level 119,442 gsf reinforced concrete parking garage. The project site is located along the southeast side of the PVM Federal Building.

The garage consists of 3 levels below grade, 1 level at grade, and 1 level above grade.

The garage provides mission critical parking to the agencies located in the adjacent, historic, Patrick V. McNamara Federal Building.

● This has been designated as an Inflation Reduction Act (IRA) Pilot Project.

Overview & Logistics of Design Build Procurement Process

● Best value/trade-off procurement

● Two Phases

○ Phase 1 is qualifications based. Objective is to identify a shortlist of most qualified firms. (Technical Qualifications of Firms, Approach to Design Build, Lead Designer’s Portfolio, Past Performance). A maximum of 3 firms will be selected to submit Phase 2 proposals. Only those selected offerors are authorized to submit Phase 2 proposals.

○ Phase 2 is the request for Proposal. Only shortlisted teams will be engaged in Phase 2; includes technical and price proposals. (Quality of Design Concept;

Qualifications, Experience and Past Performance of Key Personnel; Management and Technical Approach; Sustainability; and Price Proposal)

● General Timeframe/Milestones

○ Questions are due by August 14, 2023

○ Phase 1 Proposals Due September 22, 2023

○ Shortlist will be announced in late December 2023

○ Phase 2 will consist of concept reviews and interviews

○ Award is planned for August 2024, NTP for design is August 2024, and NTP for

Construction January 2025

● Amendments, clarifications, attendance information, etc will be issued via SAM.gov.

● Questions

Phase I Submittal Requirements:

■ Technical Proposal - electronic/proposal to be sent to jennifer.styzek@gsa.gov - 35 pages

● Technical Qualifications of Firms

● Approach to Design Build

● Lead Designer’s Portfolio

● Past Performance of the offeror’s team

● Acknowledgement of any Amendments

● SAM registration

● Verification of firm’s VETS-4212 compliance

Questions on Process and Logistics

Any/all communication, including RFIs, Questions, or Comments following the pre-proposal conference and prior to receipt of proposals should be directed at the Contracting Officer, Jennifer Styzek at jennifer.styzek@gsa.gov.

jennifer.styzek@gsa.gov

PVM Garage Phase 1 Pre-proposal Conference Created by: Jennifer Styzek - 5P2QEB · Your response: Yes, I'm going

Time

9:30am - 10am (Central Time - Chicago)

Date

Tue Aug 8, 2023

My Notes

Guests afiebig@berglundco.com aholman@christmanconstructors.

com bames@christmanconstructors.com Brian Green - 5P1NAC Christopher Giacalone - 5P2DA delliott@restoreces.com dsanschagrin@pullman-services.com edexter@berglundco.com fserrato@fishbeck.com Jennifer Styzek - 5P2QEB jhavranek@grangerconstruction.com jmchugh@berglundco.com mfirsten@keoassoc.com pgentile@cpsconstructiongroup.com rjohnson@pullman-services.com rklein@walkerconsultants.com willmarkunas@golfconstruction.net wmurphy@keoassoc.com Daniel Essenmacher - 5P1NAC Patrick Russell - 5P1NAC Brad Taplick - 5P2DA Mil Leave achristy@cpsconstructiongroup.com bmarsico@cpsconstructiongroup.

com cblakely@restoreces.com jfratto@cpsconstructiongroup.com jrozeboom@fishbeck.com lculver@restoreces.com Michael Bogue - 5P1NAC mpostma@restoreces.com

File details come from the government source that posted it. Updated .