06_3Specifications_101018.pdf

PDF 1 MB Posted

Attached to
East, West and South Entrance Repairs
Solicitation number
47PF0019R0016
Issued by

About this file

Both the contract Specifications and Drawings were erroneously left off of the original package. Specifications

View the file

Other files

File Type Posted
06_2Drawings_101018.pdf PDF
47PF0019R0016__1442.pdf PDF
47PF0019R0016_-_Solicitation_Package.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Building & U.S. Courthouse – Exterior Door Replacement Milwaukee, WI PCN #

Table of Contents 000000 - 1

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

TABLE OF CONTENTS

VOLUME I-CONTRACT CLAUSES

DIVISION 0 – STANDARD AND GSA FORMS AND WAGE RATES

00 12 00 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

00 80 00 SUPPLEMENTARY CONDITIONS

VOLUME II – TECHNICAL SPECIFICATIONS

DIVISION 1 –GENERAL REQUIREMENTS

01 10 00 SUMMARY

01 14 00 WORK RESTRICTIONS

01 23 00 ALTERNATES

01 25 00 SUBSTITUTION PROCEDURES

01 31 00 PROJECT MANAGEMENT AND COORDINATION

01 31 20 CRITICAL PATH METHOD SCHEDULING

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

01 32 20 PHOTOGRAPHIC DOCUMENTATION

01 33 00 SUBMITTAL PROCEDURES

01 35 10 HISTORIC BUILDING TREATMENT PROCEDURES

01 40 00 QUALITY ASSURANC & CONTROL

01 42 00 REFERENCES

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 59 30 SECURITY REGULATIONS

01 59 50 SAFETY AND HEALTH

01 60 00 PRODUCT REQUIREMENTS

01 70 00 EXECUTION REQUIREMENTS

01 73 10 CUTTING AND PATCHING

01 73 20 SELECTIVE DEMOLITION

01 73 50 FIRE PREVENTION PRECAUTIONS FOR HOT WORK

01 74 10 CONSTRUCTION INDOOR AIR QUALITY

01 74 19 CONSTRUCTION NONHAZARDOUS WASTE MANAGEMENT AND DISPOSAL

Table of Contents 000000 - 2

Do not remove this notice

Properly destroy documents when no longer needed

TABLE OF CONTENTS (CONTINUED)

01 77 00 CLOSEOUT PROCEDURES

01 78 22 OPERATION AND MAINTENANCE DOCUMENTATION

DIVISIONS 2 THROUGH 4 – NOT USED

DIVISION 5 – METALS

05 91 00 HISTORIC TREATMENT OF ORNAMENTAL METAL

DIVISION 6 – NOT USED

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

07 92 00 JOINT SEALANTS

DIVISION 8 – DOORS AND WINDOWS

08 11 40 CUSTOM STEEL DOORS AND FRAMES

08 71 20 DOOR HARDWARE

08 80 10 SECURITY GLAZING

DIVISION 9 – FINISHES

09 91 20 PAINTING

09 99 20 PAINTING RESTORATION

DIVISIONS 10 THROUGH 32 – NOT USED

DRAWINGS

27-A-101 TITLE SHEET

27-A-102 617 N JACKSON EXTERIOR ELEVATION OF DOORS

27-A-103 617 N JACKSON INTERIOR ELEVATION OF DOORS

27-A-104 526 E MICHIGAN EXTERIOR ELEVATION OF DOORS

27-A-105 526 E MICHIGAN INTERIOR ELEVATION OF DOORS

27-A-106 616 N JEFFERSON EXTERIOR ELEVATION OF DOORS

27-A-107 616 N JEFFERSON INTERIOR ELEVATION OF DOORS

27-A-108 TEMPORARY RAMP – 616 N JEFFERSON

27-A-109 TEMPORARY RAMP OPTION – WISCONSIN AVENUE

Supplementary Instructions to Bidders 001200 - 1

INFORMATION FOR SPECIFICATION SECTION 00 12 00

PROJECT TITLE: Exterior Door Replacement CITY & STATE: Milwaukee, Wisconsin

PROJECT #: 34948

SECTION 00 12 00 - SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

Part 3 - OFFERS

Basis of Award

One lump sum bid is required.

Part 4 - PRE-BID REQUIREMENTS AND NOTICES

Visit to Site:

GSA Contact: Tim Hansmann Address: 517 East Wisconsin Avenue, GSA 232 Phone: (414) 203-6205

Part 5 - COST BREAKDOWN OF BID AFTER AWARD

The contractor awarded this project will, after contract award, be required to submit to the government a cost breakdown of the bid price. The contractor awarded this project will further be required to maintain and update the cost breakdown in the format specified throughout the construction period, accounting for any and all change orders authorized during construction.

Supplementary Conditions 008000 - 1

INFORMATION FOR SPECIFICATION SECTION 00 80 00

PROJECT TITLE: Exterior Door Replacement CITY & STATE: Milwaukee, Wisconsin

PROJECT #: 34948

SECTION 00 80 00 - SUPPLEMENTARY CONDITIONS

Part 2 - PERFORMANCE

2.01 (c) Complete the entire work ready for use not later than 45 calendar days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.

2.02 (a) If the contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay to the Government as liquidated damages, the sum of $94.49 for each calendar day of delay.

Part 5 - EMPLOYMENT PRACTICES

5.01 (e) Covered Area: City: Milwaukee County: Milwaukee State: Wisconsin

State any other special requirements or restrictions not covered elsewhere in the drawings or specifications.

Summary 011000 - 1

SECTION 01 10 00 – SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Name and Location:

Exterior Door Replacement Milwaukee Federal Building & U.S. Courthouse 517 East Wisconsin Avenue Milwaukee, WI 53202

B. Project Summary Description: Replacement of the entry doors and renovation of exterior door frames located at 616 N. Jefferson Street, 617 N. Jackson Street, and 526 E. Michigan Street.

The project includes but is not limited to all work as indicated in accordance with the contract documents.

C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by the General Services Administration.

D. Project Delivery Method: single prime contract.

E. The Contracting Officer for the project is: Phyllis Pirtle, (312) 385-3031, Phyllis.pirtle@gsa.gov

1.2 WORK SEQUENCE

A. The work shall be conducted in three (3) phases in the following order, with each phase substantially complete before beginning the next phase:

1. Phase 1: The following work shall be substantially complete, ready for occupancy use, within 90 calendar days after notice to proceed: Replacement of the exterior doors at 617 N. Jackson Street.

2. Phase 2: The following work shall be substantially complete, ready for occupancy use, within 60 calendar days after substantial completion of Phase 1: Replacement of the exterior doors at 616 N. Jefferson Street.

3. Phase 3: The following work shall be substantially complete, ready for occupancy use, within 40 calendar days after substantial completion of Phase 2: Replacement of the exterior doors at 526 E. Michigan Street.

B. Before commencing Work of each phase, Contractor shall submit a schedule showing the sequence, commencement, and completion dates for all phases of the Work.

1.3 MISCELLANEOUS PROVISIONS

A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.

Summary 011000 - 2

B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.

Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.

1. Replacements of existing conditions that are removed shall match similar existing conditions.

2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.

3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.

4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.

C. Existing structures will remain in place.

D. Existing utility services with related meters and equipment will remain in place.

E. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 01 10 00

Work Restrictions 011400 - 1

SECTION 01 14 00 - WORK RESTRICTIONS

1.1 CONTRACTOR USE OF PREMISES

A. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to the Government prior to the commencement of any construction activity.

B. During the construction period, the Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the Government's right to perform work or retain other contractors to perform work on portions of the project.

C. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy and public use.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

4. Maintain existing building in a safe and weather-tight condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the building, its occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur.

5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.

6. Space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government.

Arrange and gain approval for use of this space through the Contracting Officer.

7. Use of the existing loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis. The Contractor shall coordinate with the Property Manager for availability.

8. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.

9. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.

10. Smoking is not permitted in or around the building, see Facilities Management Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.

Work Restrictions 011400 - 2

11. No parking will be available on site during working hours. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site.

12. No apparatus with an open flame is allowed to be used within the facility without the prior receipt of a burn permit. Contact the Field Office to obtain burn permits. Burn permits are required for each separate occurrence.

13. Permits: Refer to FAR 52.236-7

14. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.

15. Coordinate with the GSA Property Manager and the COR for site access.

16. Coordinate with the GSA Property Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.

17. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.

18. Protect building site from flying debris.

1.2 GOVERNMENT OCCUPANCY

A. The Government will occupy the site and the existing building during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.

B. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

1.3 WORKING HOURS

A. Government Occupied Hours: Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through Friday, except for established Government Holidays 6:00 PM to 6:00 AM. Working hours for the particular Project space may be different, coordinate with GSA Property Manager.

B. Government Unoccupied Hours: Government personnel are not scheduled to occupy the building during times not indicated as Government Occupied Hours.

C. Contractor's General Working Hours: The Contractor working hours shall be generally established to occur during Government Occupied Hours unless noted otherwise.

D. Contractor's Required Working Hours: The following work shall be performed during Government Unoccupied Hours:

1. Noisy and/or odor-producing work that may disrupt tenant operations in adjacent spaces.

Work Restrictions 011400 - 3

2. While U.S. Courts are in session.

E. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Contractor shall submit a proposed schedule and gain the Contracting Officer's approval at least 48 hours before proceeding with any work during Government Unoccupied Hours.

PART 2 - PRODUCTS (Not Applicable)

END OF SECTION 01 14 00

Alternates 012300 - 1

SECTION 012300 - ALTERNATES

1.1 SUMMARY

A. An alternate provides an amount proposed by the Contractor and stated on the pricing form for certain work that will adjust the Base Contract Amount if the Government decides to accept the corresponding scope of work products, materials, equipment, systems or installation methods described in the Contract Documents.

B. The amount for an alternate is the total net adjustment to the Base Bid to incorporate the alternate work into the project.

C. Alternate work shall include miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation, whether or not mentioned as part of the alternate description.

1.2 PROCEDURES

A. Selection: Acceptance or rejection of each alternate will be made by the Government prior to award of the Contract, and the Base Bid amount will be adjusted accordingly for accepted alternates to establish the contract price.

B. Coordination: The Contractor shall modify or adjust affected work as necessary to completely and fully integrate the accepted alternate work into the project Work.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. Alternate No. 1: Replace door hardware for interior vestibule doors at Jackson Street entrance.

See hardware Set 4.0 in Specification Section 08 71 00 Door Hardware.

END OF SECTION 01 23 00

Substitution Procedures 012500-1

SECTION 01 25 00 - SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 012300 Section "Alternates" for products selected under an alternate.

2. Division 016000 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

3. Divisions 02 through 49 Sections for specific requirements and limitations for substitutions.

1.3 DEFINITIONS

A. Substitutions: Proposed changes to the Contract Documents by the Contractor for products, materials, equipment, and methods of construction.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner

1.4 SUBMITTALS for Cause or Convenience:

A. Substitution Requests: Per Submittal Procedures Section 013300 submit electronic copies through ePM of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: To be requested from GSA Contracting Officer’s Representative (COR).

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Government and separate contractors that will be necessary to accommodate proposed substitution.

b. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, energy and resource performance goals, warranties, and specific features and requirements indicated.

Indicate deviations, if any, from the Work specified.

c. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

d. Samples, where applicable or requested.

e. Certificates and qualification data, where applicable or requested.

f. List of similar installations for completed projects with project name, location and contact information of owner and architect/engineer of record.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

h. Research reports evidencing compliance with building code in effect for project, when applicable for the proposed substitution.

i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. Provide a schedule fragnet with a time impact analysis to allow the Government to consider the proposed substitution.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

k. Proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

l. The Contracting Officer may require the Contractor to provide a contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. The Contracting Officer or Contracting Officer’s Representative (CO) or (COR) Action: If necessary, the Contracting Officer or COR will request additional information or documentation for evaluation. The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty working days.

1.5 Failure by the government to respond does not constitute acceptance of the proposed substitution.

1.6 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.7 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 15 business days prior to time required for preparation and review of related submittals.

1. Conditions: The Contracting Officer (CO) will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, the Contracting Officer (CO) will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan. .

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: The Contracting Officer (CO) will consider requests for substitution if received within 30 days after the Notice to Proceed . Requests received after that time may be considered or rejected at discretion of the Contracting Officer (CO) or the Contracting Officer Representative (COR).

1. Conditions: The Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied.

a. Requested substitution offers the Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional obligations the Government incurs.

b. Requested substitution is consistent with the Contract Documents and will produce indicated results.

c. Substitution request is fully documented and properly submitted.

If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 EXECUTION (Not Used)

END OF SECTION 01 25 00

Project Management & Coordination 013100 - 1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Coordination drawings.

3. Conservation.

4. Administrative and supervisory personnel.

5. Conferences and meetings.

6. Utility service interruptions.

7. Cleaning and protection.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space.

Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

3. Minimize roof penetrations.

B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work.

Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities.

3. Security packages and systems by others (i.e. U.S. Marshals Service (USMS), Federal

Protective Service (FPS), tenants, etc.)

4. Audio Visual (AV) and technology requirements and packages for tenants and/or end users.

5. Telecommunication, data, internet and other tele-work systems for GSA, tenants and/or end users.

Project Management & Coordination 013100 - 2

6. Delivery and processing of submittals.

7. Progress meetings.

8. Project closeout activities.

9. Startup and adjustment of systems.

1.3 CONSERVATION

A. Coordinate conservation of energy, water and materials in the conduct of construction operation.

Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.

B. Comply with Green Purchasing Plan requirements. See KSP references in Statement of Work.

1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.

B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:

1. Scheduling and sequencing of Work.

2. Sharing access to work spaces.

3. Installations.

4. Protection of work.

5. Cutting and patching.

6. Selections for compatibility.

7. Preparation of coordination of drawings.

8. Inspection and tests.

9. Temporary services and facilities.

C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."

D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.

1.5 CONFERENCES AND MEETINGS

A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.

1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:

a. Government.

b. Architect.

Project Management & Coordination 013100 - 3

c. Major design consultants.

d. Contractor.

e. Major subcontractors.

f. Major suppliers.

g. Other concerned parties.

2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:

a. Tentative construction schedule.

b. Critical work sequencing.

c. Designation of responsible personnel.

d. Procedures for processing field decisions and Change Orders.

e. Procedures for processing Applications for Payment.

f. Distribution of Contract Documents.

g. Submittal of Shop Drawings, Product Data, and Samples.

h. Preparation of Record Documents.

i. Use of the premises.

j. Parking availability.

k. Office, work, and storage areas.

l. Equipment deliveries and priorities.

m. Safety procedures.

n. First aid.

o. Security.

p. Housekeeping and progress cleaning.

q. Working hours.

r. Energy and resource efficiency / sustainability

s. Waste management

B. Progress Meetings: The Government or designee shall conduct progress meetings at the Project Site at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request.

1. Attendees: In addition to the Contractor's and Government's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.

a. Contractor's Construction Schedule: Review progress since the last progress meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. Provide

(X) week schedule look ahead.

b. Review the present and future needs of each entity present, including but not limited to the following:

1) Interface requirements.

Project Management & Coordination 013100 - 4

2) Time.

3) Sequences of operations.

4) Status of submittals.

5) Deliveries.

6) Off-site fabrication.

7) Access.

8) Site utilization.

9) Temporary facilities and controls.

10) Hours of work.

11) Hazards and risks.

12) Housekeeping and progress cleaning.

13) Quality and work standards.

14) Change Orders.

15) Documentation of information for payment requests.

16) Updating of Record Documents.

3. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.

4. Minutes: Record significant discussions and agreements and disagreements of each conference. No later than 3 calendar days after each conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties, including the Contracting Officer.

D. Project Closeout Conference: GSA will schedule and conduct a Project closeout conference, at a time convenient to Contractor, CM and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion.

Attendees: Authorized representatives of GSA, CM, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

5. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Coordination of final commissioning requirements and submittal of written warranties.

d. Requirements for completing sustainable design documentation.

e. Requirements for preparing operations and maintenance data.

f. Requirements for delivery of material samples, attic stock, and spare parts.

g. Requirements for demonstration and training.

h. Preparation of Contractor's punch list.

i. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

j. Submittal procedures.

k. Coordination of separate contracts, if any.

l. GSA's partial occupancy requirements.

m. Installation of GSA's furniture, fixtures, and equipment.

n. Responsibility for removing temporary facilities and controls.

6. Minutes: Entity conducting meeting will record and distribute meeting minutes within 3 working days. Meeting Minutes should be uploaded or documented within ePM.

Project Management & Coordination 013100 - 5

1.6 UTILITY SERVICE INTERRUPTIONS

A. Utility Service Interruption Plan: Within 7 calendar days from Notice to Proceed (NTP) Contractor shall submit a utility service interruption plan for the project. Plan shall include dates and times of each scheduled interruption, with estimated period of outage, list of existing equipment that will be affected by the interruption, proposed sequence of equipment shut-down and start-up, and responsible personnel.

1. Keep interruptions and periods of interruption to a minimum.

2. Schedule interruptions during times when the facility is unoccupied.

3. Plan must be approved in writing by the Building Manager and the Government or the

Government's representative. If not approved, consult with the Building Manager, and revise and resubmit the plan until approved.

B. Coordination of Interruptions: Sufficiently in advance of each scheduled utility interruption, the Contractor shall issue a notice to all affected parties, confirming each provision of the interruption, or canceling and rescheduling. Coordinate with the Building Manager and Government's representative, and confirm that the responsible personnel are prepared to execute the shut-down and start-up of affected existing equipment, prior to each interruption.

1.7 SUBMITTALS

A. Subcontract List: Within 7 calendar days from Notice to Proceed (NTP) prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

4. Coordination Drawings: Comply with the shop drawing requirements specified in Division 1

Section "Submittal Procedures".

B. Staff Names: Within 7 calendar days after commencement of construction, submit a list of principal staff assignments, including the superintendent and other primary personnel at the Project site. Identify individuals by name, duties and responsibilities, home address, and business and home telephone numbers.

PART 2 - PRODUCTS (Not applicable)

PART 3 - EXECUTION

3.1 GENERAL COORDINATION PROVISIONS

A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.

1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

Project Management & Coordination 013100 - 6

2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.

B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.

C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.

D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:

1. Excessive static or dynamic loading.

2. Excessive internal or external pressures.

3. Excessively high or low temperatures.

4. Thermal shock.

5. Excessively high or low humidity.

6. Pollution and air contamination.

7. Water or ice.

8. Chemicals and solvents.

9. Light.

10. Radiation.

11. Puncture.

12. Abrasion.

13. Heavy traffic.

14. Soiling, staining, and corrosion.

15. Bacteria.

16. Rodent and insect infestation.

17. Combustion.

18. Electrical current.

19. High-speed operation.

20. Improper lubrication.

21. Unusual wear or other misuse.

22. Contact between incompatible materials.

23. Destructive testing.

24. Misalignment.

25. Excessive weathering.

26. Unprotected storage.

27. Improper shipping or handling.

28. Theft or vandalism.

END OF SECTION 01 31 00

Critical Path Method Scheduling 013120 - 1

SECTION 01 31 20 - CRITICAL PATH METHOD SCHEDULING FOR SHORT DURATION PROJECTS

1.01 SUMMARY

A. Develop a detailed Network Plan using electronic scheduling software, demonstrating complete fulfillment of all Work shown in the contract documents. Regularly update the Network Plan in accordance with the requirements of this Section, and use it in planning, coordinating, and performing all the Work under this contract. Schedule activities shall accurately depict the entire scope of work to be performed to complete the project including, but not limited to, all activities of subcontractors, consultants, equipment vendors and suppliers, GSA, and others, as required.

Provide look ahead schedules.

C. The purpose of the Project Schedule shall be to:

1. Plan the project and communicate that plan.

2. Provide the status and forecast the timely completion of the work.

3. Record the actual start dates, actual finish dates and actual sequence of the work.

4. Ensure adequate planning, staffing, scheduling and reporting during execution of the Work by the Contractor;

5. Ensure coordination of the Work among all affected parties;

6. Assist the Contractor and GSA in the preparation and evaluation of the Contractor’s monthly progress payments; and

7. Assist the Contractor and GSA in monitoring the progress of the work, and evaluating proposed changes to the Contract and/or requests for additional time to Project Completion.

1.02 RELATED SECTIONS

A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and provisions of the Contract including General and Supplementary Conditions apply to this Section as if repeated herein.

B. Section 013200 – Construction Progress Documentation

1.03 DEFINITIONS

A. Definitions applicable to this Section include the following:

1. Activity - An element of the Work or task performed during the course of the project. Each schedule activity shall be a clearly defined, manageable and monitorable task depicting an estimated duration and an estimated cost. Each activity shall be limited to one trade unless the GSA specifically approves otherwise on an exception basis.

2. Baseline Schedule - The original work plan approved by GSA as the Project Schedule depicting the contractor’s plan to prosecute the work.

3. Constraint - A scheduling restriction imposed on the start, finish or float of an activity. No constraints will be allowed. Exception: for projects with limited or no storage areas requiring

Critical Path Method Scheduling 013120 - 2

“just in time” deliveries, a zero free float may be acceptable.

4. Critical Path - The Project critical path is defined as the longest, continuous path of interrelated activities depicting project work from Notice To Proceed (NTP) to project completion. All reports and graphics indicating the Critical Path shall depict the longest path of interrelated activities. Unless otherwise approved by GSA, the Baseline Schedule Critical Path shall use all allotted Contract time. The contractor has the right to develop a schedule that forecasts an early finish. However, all time between the forecasted early finish of substantial completion and the contractual substantial completion date shall be shown as float and shall be available to the Project team.

5. Critical Path Method (CPM) - A scheduling technique using activities, durations, and interrelationships/dependencies (logic), such that all activities are interrelated with logic ties from the beginning of the project to the completion of the project. There shall be no open ended relationships in the schedule. All activities shall have at least one successor with a finish relationship (“finish to start” or “finish to finish”) except the last activity in the network.

6. Data Date - The date to which progress is updated. In most scheduling software, the data date represents the next day of work and all progress is updated through the day prior to the data date.

7. Float – is the difference between the forecasted early dates and the forecasted late dates; the amount of time an activity can be delayed without delaying the Substantial Completion Date.

Float is considered a project commodity jointly shared between GSA and the Contractor and shall be used in the best interest of completing the Project on time. The critical path is not dependent on float. Float is calculated after the critical (longest) path has been determined.

8. Float Suppression – the masking of available float through the use of constraints, unreasonable logical relationships or unreasonable durations. Float suppression techniques are not allowed. On an exception basis, the use of a zero free float constraint to depict “just in time” deliveries on projects with little or no storage might be acceptable.

9. Fragnet - A subset group of interrelated activities representing only a portion of the CPM schedule.

10. Network Plan - The Network Plan is the entire database of activities, logic, durations, and all items relating to any activity input into the scheduling software and is the complete representation of the Project Schedule prepared using the Critical Path Method and graphically shown in a time-scaled form. The network shows the sequence and interdependence of the activities, and planned and actual progress by activity, required for complete performance of the Work.

11. Project Schedule - The Project Schedule includes the Preliminary Schedule (submitted at bid or as determined by the CO), the approved Baseline Schedule (developed based on the Preliminary Schedule), and all subsequent Schedule Updates, Schedule Revisions, Recovery Schedules, and As-Built Schedule.

12. Recovery Schedule – A schedule depicting the Contractor's plan for recovery of time lost on the project.

13. Schedule Revision - A schedule in which the plan for the work is revised. A Schedule Revision is required when the current schedule no longer represents the actual or planned prosecution of the Work.

14. Schedule Update - A schedule in which only actual start dates, actual finish dates and duration percent complete is updated from the prior data date to the current data date. No revisions will be permitted in a Schedule Update (i.e. added activities, deleted activities, logical relationships, etc.).

15. Time Impact Analysis - A technique to demonstrate the effect of a schedule revision or proposed revision against the current approved Project Schedule.

16. Total Float - The amount of time an activity (or chain of activities) can be delayed without affecting the Project Substantial Completion Date.

17. Working Day - A Working Day is a calendar day scheduled for active prosecution of the work.

1.04 CRITICAL PATH METHOD SCHEDULE

Critical Path Method Scheduling 013120 - 3

A. Provide a detailed, time-scaled computer generated Project Schedule with activities representing each portion of the Work for the entire Contract Performance Period. The Project Schedule shall use the Critical Path Method (CPM) for the planning, scheduling and reporting of the work to be performed under the contract.

B. No unspecified constraints, float suppression techniques, or use of activity durations, logic ties and/or sequences deemed unreasonable by GSA shall be used in the Project Schedule.

C. As defined by the Contract, the entire project performance period shall establish the Project

Substantial Completion Date which shall be used in the planning and presentation of the Contractor’s Project Schedule. GSA reserves the right not to approve any schedule deemed to have an unrealistic forecasted Substantial Completion Date. Government approval of an early completion Project Schedule shall not modify the Contractual Substantial Completion Date or Project Completion Date. The time difference between the Contractor’s planned Substantial Completion Date and the Contract directed Substantial Completion Date shall be considered Project Float, jointly owned and for the mutual use of both the Contractor and GSA.

D. The Contractor shall provide the computer processing of the CPM schedule required under this

Section or as requested by GSA in electronic format to GSA throughout the entire project performance period until Project completion is achieved.

1.05 SUBMITTALS and MEETINGS

A. Project Schedule Requirements Meeting:

1. The Contractor shall meet with GSA within seven (7) calendar days after Notice to Proceed to conduct a joint review of the Project Schedule requirements in this Section.

B. Preliminary Schedule:

1. Within fourteen (14) calendar days of Notice to Proceed, Contractor shall submit a Preliminary

Schedule detailing the complete scope of work and proposed logical relationships. All owner furnished equipment and materials shall be identified with dates needed to be received by the contractor.

2. Within seven (7) calendar days of receipt by the GSA of the Preliminary Schedule, the Contractor and GSA shall meet to discuss the results of GSA's schedule review. To the extent that revisions are required, the Contractor shall resubmit the Preliminary Schedule to the GSA for approval within [seven (7) calendar] days of receipt of the GSA's comments.

C. Baseline Project Schedule

1. The Contractor shall submit the Baseline Project Schedule within seven (7) calendar days after approval of the Preliminary Schedule. The Baseline Schedule shall be the Contractor's detailed plan for ALL work from NTP through contract completion. All punchlist work shall be completed to, or prior to, the Contract Completion Date.

2. Unless otherwise approved by the GSA, the Project Schedule shall include, but is not limited to, the following items:

a. Activities necessary to depict time to prepare submittals, time for the GSA to review submittals, procurement, design, construction, third party inspections, close-out, start-up, Critical Path Method Scheduling 013120 - 4 testing and balancing, commissioning and turnover, and work by separate contractors.

b. The schedule shall include separate activities for the submittal, review, procurement or fabrication, and delivery of key and long-lead items. The Project Schedule shall indicate submittal dates, and depict the review period as defined in the Contract or Supplementary Provisions for A/E/GSA review. Procurement/submittal activities shall be assigned codes that will allow these activities to be sorted and printed separately from the construction/close-out/commissioning work activities.

c. Activity descriptions of the work shall include area designators sufficient to identify where the Work will occur, and shall match the Key Plans. The work related to each Activity shall be limited to one work trade and one area.

d. Interrelationships (logic) and sequencing for ALL activities. Each activity shall have at least one successor (except for the last activity) relationship to form a logically connected Network Plan from NTP to the Contract Completion Date. Each activity shall have at least one successor with a finish relationship (finish-to-start or finish-to-finish relationship).

e. Activity durations shall be in units of whole work days. Except submittal and procurement activities, durations shall not exceed one reporting period , unless approved by the GSA.

Durations for Government submittal reviews shall meet the requirements set forth in the Contract Documents. Activity durations shall not be overly short. One day durations shall not be assigned unless specifically requested by the contractor and specifically accepted by the GSA. Activity durations are expected to be between one week and one month, however shorter or longer durations can be assigned as needed to properly plan and coordinate the work.

f. Contractual milestone events as defined in the Contract Documents including, but not limited to, phased work, work restrictions/access/shift work, and work being performed by separate contractors shall be included in the schedule. The substantial completion and project completion tasks shall be assigned to a seven (7) day work week calendar.

g. ALL activities shall at a minimum be coded by Area, Responsibility (trade/ subcontractor), and Phase. Additional codes are allowed to sufficiently identify where work will occur.

Codes shall be a…