CMS BOC Ph. 2 - 95% CD 011100 PROJECT PHASING.pdf
PDF 110 KB Posted
- Attached to
- CMS Back on Campus Phase II Federal contract opportunity
- Solicitation number
- 47PD0221R0072
About this file
This document outlines a federal solicitation for construction services. The General Services Administration is seeking offers for renovations totaling approximately 40,000 square feet across four areas of the Centers for Medicare and Medicaid Services campus in Woodlawn, Maryland. Work includes renovations to space in the Central Building Level 2, South Building Lower Level, Central Building Lower Level, and the campus Main Lobby. The scope of work includes upgrades to modernize aging buildings and systems to current space utilization and footprint standards. The order of magnitude for the project cost is estimated between $10-15 million. Evaluation criteria will consider offerors' project management approach, experience on relevant projects, and past performance on construction references. A bid guarantee and payment/performance bonds are required. The primary point of contact is the GSA contracting officer.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPERTY OF UNITED STATES GOVERNMENT -
FOR OFFICIAL USE ONLY
CMS PHASE 2
ISSUE FOR 95%
CONSTRUCTION DOCUMENTS
PROJECT PHASING 01 11 10 - 1
05/10/2022
SECTION 01110
PROJECT PHASING
PART 1 – GENERAL
1.1 SUMMARY
A. The intent of this Section is to identify major project sequencing requirements and inform the Contractor of Government’s known restrictions that will affect the timing of work and provide general phasing guidelines.
B. The phasing scope described in this Section shall not be deemed to constitute the comprehensive scope of all Contract requirements but is identified herein to assist the
Contractor in the understanding of existing systems and conditions which may affect the
Contractor’s planned work sequence.
C. The Contractor shall provide necessary resources as needed to perform required services including, but not limited to, those described in the RFP, the construction documents, exhibits, and attachments made a part of the contract to successfully complete the construction work required for Back on Campus Phase 02.
D. The ultimate responsibility of comprehensive project phasing rests with the Contractor. All
Contractor phasing plans must be documented in a submittal and reviewed and approved by the Government prior to commencing with such plan. Also phasing activities shall be reflected in the Contractor’s baseline schedule (Project Schedule) and monthly updated
CPM construction schedules. Refer to Section 013110 – Critical Path Method Scheduling for submission of Contractor’s Preliminary, Baseline and updated CPM Project Schedules.
1.2 PHASING AROUND CMS OCCUPANCY
A. The project comprises three distinct portions of work, each with unique occupancy requirements which will influence how construction is sequenced and phased. One construction Notice to Proceed (NTP) date is anticipated on or about November 15, 2022 for all three portions. See also section 011000 for milestone dates for design and construction. However, there may be opportunities for early work packages which could necessitate more than one construction NTP.
1. C2: Upon NTP, C2 will have existing furniture and fixtures that remain and will be part of the GC demolition scope. There are two restrooms serving the C2 spaces. When contractor sequencing and phasing require, both restrooms will be allowed to be closed for a defined period. The defined period will require work plans, review and approval by GSA Building Management.
a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding
65db or noise levels that are consistent will be considered disrupting tenant functions.
SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT, COPYING, DISSEMINATION, OR DISTRIBUTION OF THIS DOCUMENT TO UNAUTHORIZED RECIPIENTS IS PROHIBITED. Do not remove this notice. Properly destroy or return documents When no longer needed.
CONSTRUCTION DOCUMENTS
PROJECT PHASING 01 11 10 - 2
05/10/2022
2. SLL: The Badging Office currently occupying space on SLL is required to be functional all times during construction, therefore, sequencing for SLL will require in depth analysis with CMS and GC. As such, life safety and building systems serving the occupied spaces as well as egress pathways must be maintained. Upon NTP, SLL will have existing furniture and fixtures that remain and will be part of the GC demolition scope. There are two restrooms serving the SLL spaces. When contractor sequencing and phasing require, both restrooms will be allowed to be closed for a defined period. The defined period will require work plans, review and approval by
GSA Building Management.
a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding
65db or noise levels that are consistent will be considered disrupting tenant functions.
3. CLL: Upon NTP, CLL will have existing furniture and fixtures that remain and will be part of the GC demolition scope.
a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding
65db or noise levels that are consistent will be considered disrupting tenant functions.
b. Removal of trash activities on the Lower Level of the Central building (CLL) shall be performed during off-hours
4. C1: Upon NTP, the first level of the Central building (C1) space will have existing furniture and fixtures that remain and will be part of the GC demolition scope. The contractor will require to coordinate with CMS and to provide the access to the auditorium.
a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding
65db or noise levels that are consistent will be considered disrupting tenant functions.
b. Removal of trash activities on the Lower Level of the Central building (C1) shall be performed during off-hours
1.3 BUILDING SYSTEMS INTERFACE
A. Contract work that ties into and/or requires cutting & capping of the operational building systems must be coordinated so that required systems remain fully functional for the duration of this project. Coordination with the CMa and GSA Building Management staff is required to ensure operations are not impacted during project installations and testing.
Following is a brief summary of systems which may require contractor awareness and consideration as system tie-ins or cut/cap activities are conducted.
B. Sprinkler: The building has a full sprinkler system consisting of vertical sprinkler mains, combined risers and sprinkler floor control valve assemblies which are located in the
PROPERTY OF UNITED STATES GOVERNMENT -
FOR OFFICIAL USE ONLY
CONSTRUCTION DOCUMENTS
PROJECT PHASING 01 11 10 - 3
05/10/2022 egress stairways. GSA Building Management will work directly with Construction
Manager and the Contractor to coordinate all outage requests in advance with GSA Fire
Shop. This also includes daily burning permits which will require coordination between
GC, CMa and GSA Building Management and call made daily to GSA Fire Shop and CMS
Security. See also section 013100 for requirements and processes for utility service interruptions or outages necessary to complete the project.
C. Existing addressable Fire Alarm: The GC is responsible for a fully operational fire alarm system throughout the renovations. The existing FACP and related systems are to remain in service throughout demolition and renovation phases; there will be de commissioning of many existing fire alarm points, re programming and re testing by AHJ. These efforts are the responsibility of the GC. GC to survey and verify requirements of existing fire alarm cable and termination panels.
D. Existing IT/AV/PA/Security cabling: Cabling for security, infrastructure technology, Public
Address System, and Audio Visual services may run through the renovation areas but be connected to other occupied spaces. The GC is to identify, protect and relocate prior to demolishing these existing systems.
PART 2 - PRODUCTS (Not Applicable)
PART 3 – EXECUTION (Not Applicable)
| PART 1 – GENERAL |
| 1.2 Phasing around CMS Occupancy |
| 1. C2: Upon NTP, C2 will have existing furniture and fixtures that remain and will be part of the GC demolition scope. There are two restrooms serving the C2 spaces. When contractor sequencing and phasing require, both restrooms will be allowed to be ... |
| a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding 65db or noise levels that are consistent will be considered disrupting tenant functions. |
| 2. SLL: The Badging Office currently occupying space on SLL is required to be functional all times during construction, therefore, sequencing for SLL will require in depth analysis with CMS and GC. As such, life safety and building systems serving the... |
| a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding 65db or noise levels that are consistent will be considered disrupting tenant functions. |
| 3. CLL: Upon NTP, CLL will have existing furniture and fixtures that remain and will be part of the GC demolition scope. |
| a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding 65db or noise levels that are consistent will be considered disrupting tenant functions. |
| b. Removal of trash activities on the Lower Level of the Central building (CLL) shall be performed during off-hours |
| 4. C1: Upon NTP, the first level of the Central building (C1) space will have existing furniture and fixtures that remain and will be part of the GC demolition scope. The contractor will require to coordinate with CMS and to provide the access to the ... |
| a. Noisy producing work that may disrupt tenant operations in adjacent spaces must be performed during off-hours or weekend schedules. Noise levels exceeding 65db or noise levels that are consistent will be considered disrupting tenant functions. |
| b. Removal of trash activities on the Lower Level of the Central building (C1) shall be performed during off-hours |
1.3 BUILDING SYSTEMS INTERFACE