This Building Information Model Execution Plan (BEP) outlines the use of Building Information Modeling (BIM) for the CMS Back on Campus Phase II project. The project involves renovations totaling approximately 40,000 square feet of space across four areas in the CMS campus in Windsor Mill, Maryland.
The BEP defines BIM goals including leveraging spatial data management for code reviews and energy analysis, as well as constructability verification through clash detection. It identifies key contacts and their BIM roles, collaboration procedures for model sharing and coordination meetings, quality control processes, software and standards to be used, model structure and naming conventions, and required project deliverables. BIM uses include visualization, programming, design authoring, cost estimation, documentation, analysis and more. The project is scheduled from July 2021 through completion in 2022.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIM EXECUTION PLAN
FOR
CMS PHASE 2 BACK ON CAMPUS
Version: 2.0
Submitted Date: 02/24/2021
Submitted By:
Krueck Sexton Partners 221 W Erie St Chicago, IL 60654
U.S. General Services Administration
Public Buildings Service
Building Information Model Execution Plan, Version [1.1] CMS Phase 1: Back on Campus Solicitation Number [47PD0219F0014] ii
Forward The BIM Execution Plan (BEP) is developed to provide a master information/data management plan and assignment of roles and responsibilities for model creation and data integration at project initiation. The BEP aligns the project acquisition strategy needs and requirements with GSA technical standards, team member skills, construction industry capability, and technology maturity. Through this process, the team members and GSA project management have jointly agreed on how, when, why, to what level, and for which project outcomes BIM will be used.
iii
BIM PROJECT EXECUTION PLAN
FOR
Phase1: CMS BACK ON CAMPUS
Table of Contents
SECTION A: BIM PROJECT EXECUTION PLAN OVERVIEW
SECTION B: PROJECT INFORMATION
SECTION C: KEY PROJECT CONTACTS
SECTION D: PROJECT GOALS / BIM USES
SECTION E: COLLABORATION PROCEDURES
SECTION F: QUALITY CONTROL
SECTION G: TECHNOLOGICAL INFRASTRUCTURE NEEDS
SECTION H: MODEL STRUCTURE
SECTION I: PROJECT DELIVERABLES
SECTION J: ATTACHMENTS ............................................................................ ERROR! BOOKMARK NOT DEFINED.
SECTION A: BIM PROJECT EXECUTION PLAN OVERVIEW
To successfully implement Building Information Modeling (BIM) on a project, the project team has developed this detailed BIM Project Execution Plan. The BIM Project Execution Plan defines uses for BIM on the project (e.g. design authoring, spatial data management, and design coordination), along with a detailed design of the process for executing BIM throughout the project lifecycle.
SECTION B: PROJECT INFORMATION
This section defines basic project reference information and project milestones.
1. Project Basics:
Project Owner: GSA CMS Project Name: CMS Phase 1 Back On Campus Project Location and Address: 7500 Security Boulevard Windsor Mill, MD 21244 Brief Project Description: [Design and documentation for renovation of Central Lower) office space), Level 1 (Main Campus Lobby) and Level 2 and South Lower level (office spaces).
2. Project Numbers:
Project Information Number Task Order Number 47PD0219F0020
GSA Building Number MD0415HC
Krueck + Sexton Project Number 2008
3. Project Schedule/Phases/Milestones:
*see attachment 1 – Model Progression Matrix for detailed breakdown
Project Stage / Milestone Estimated Start Date Estimated Completion Date
Project Stakeholders Involved
Design Stage
Design Model
Design concept phase
LOD 100-200
07/19/2021 09/03/2021 GSA, CMS, A+E Team
Design development phase
LOD 200-300
9/13/2021 12/02/2021 GSA, CMS, A+E Team
Construction Documents Phase LOD 300 Complete
12/03/2021 06/22/2022 GSA, CMS, A+E Team
Construction Stage
As-built Model
Construction delivery Phase LOD 400 Complete
Project close-out phase LOD 500 Complete
4. Project Management System ePM is the standard GSA Project Management System(PMS). If additional systems will be used, list them below.
SECTION C: KEY PROJECT CONTACTS AND ROLES
The team has identified who will be responsible for various aspects of the project based on delivering the BIM goals.
The intent of the team is only to help clarify contractual obligations of the team members and stakeholders. No portion of this is intended to redefine or override any contractual obligations each party owes under their respective contracts.
1. BIM Roles and Responsibilities This section is intended to cover the macro level major responsibilities of the team members.
Stakeholder Scope of Work
Architect Overall design lead responsible for overseeing the design through LOD300 and contributing to the LOD400 and LOD500 efforts. Establish and maintain the projects DMS through project close out.
Engineer Establish and construct the design BIMs for all mechanical, electrical, and plumbing systems.
2. Project Contacts These are the primary management and technical contacts. These contacts should be used to seek immediate resolution of projects coordination challenges.
Design Team
Role Organization Contact Name Location E-Mail Phone
Lead Q/C Krueck and Sexton Don Semple Chicago, IL dsemple@ks.partners.com 312-374-1427
End User CMS
GSA BIM Rep. GSA
Project Manager(s) Krueck and Sexton Don Semple Chicago, IL dsemple@ks.partners.com 312-374-1427
Project Architect(s) Krueck and Sexton Veronica Widholm Chicago, IL vwidholm@ks.partners.com 312-4979365
BIM Manager(s) Krueck and Sexton Michael
Pfammetter
Chicago, IL Mpfammatter@ks.partners.com
Consultant MEP Engineer WSP Engineering Sam Ciulla New York City, NY Cathy.Chang@WSPGroup.com 212-951-2757
Consultant BIM Manager (s) WSP Engineering Abel Francis….. Chicago, IL abel.francis@wsp.com 1 (646) 487-5562
Consultant AV+Acoustic Threshold Acoustics Constance Walker Chicago, IL cwalker@thresholdacoustics.com 312-386-1400 x106
Consultant Structural Thornton Thomasetti Jose Medero Chicago, IL JMedero@ThorntonTomasetti.com 312-596-2110 mailto:dsemple@ks.partners.com mailto:dsemple@ks.partners.com mailto:Cathy.Chang@WSPGroup.com mailto:cwalker@thresholdacoustics.com mailto:JMedero@ThorntonTomasetti.com
Construction Team
Role Organization Contact Name Location E-Mail Phone
Lead Project Integrator
Lead Q/C
Project Manager(s)
BIM Manager(s)
Discipline Leads
Other Project Roles
SECTION D: PROJECT GOALS/BIM USES
1. Major BIM Goals / Objectives:
The projects goals are defined below as well as what metric is being used to validate their success. After careful consideration of the BIM maturity of the team members tasked with their completion, the team believes that all goals listed are achievable.
The team believes that the success of all goals defined is a team effort and expects all stakeholders and project participants to positively contribute to their success.
Priority / Measure ment
Goal / Achieved if Primary Responsibility
Pr io rit y
Hi gh
Goal:
Leverage Spatial Data Management to conduct digital code reviews and energy analysis.
Owner / Operator Provide standards to design team. Inform the team of historic energy data as well as local code related issues.
Architect
Embed the SDM into the design model, and assist with embedding this data into the construction model. Will conduct reviews of energy model. Will lead digital code review meetings.
Mechanical Consultant
Will use the SDM data from the Architect to programmatically derive the Space elements used for energy calculations. Will conduct digital energy analysis and track results through the design of the project.
Builder / Contractor Ensure that proper SDM data is included within the construction model.
M ea su re m en t Achieved if:
• Energy consumption projections are reduced by >15% using the model.
• No substantial code violations surface during construction.
Builder / Contractor
Track code compliance through construction.
Report any code related issues to the team including costs to the project in both dollars and time.
Architect
Perform root-cause analysis on any code issues that cost the project during construction and present the results to the team.
MEP Contractors
Ensure that strategies for energy consumption reduction are taken from design to the real world. Report any deviations to the team.
1. Major BIM Goals / Objectives (Cont.):
Priority /
Measurement Goal /
Achieved if Primary Responsibility
Priority High
Goal:
Model based constructability verification (clash detection, clearance verification, etc.)
Owner / Operator Provide accurate dimensional information for service and maintenance requirements.
End-user
Attend coordination meetings to verify requirements are implemented correctly within the model.
Architect
Generate BIM in a way to facilitate the goal. Ensure that both real objects and non-real space claims are properly modeled.
MEP Contractors Ensure that MEP LOD is sufficient to achieve the goal.
VDC Consultant Verify weekly that all parties are working towards achieving the goal.
Measurement Achieved if:
• Change orders and RFIs are reduced by 50% or more from a traditional project.
• 50% or more off-site fabrication.
• See overall reduction in gross sq. ft. cost compared to traditional project. See large reduction in last minute changes.
Builder / Contractor Track quantity and impact of RFIs and provide competitive feedback to the project team.
MEP Contractors
Track percentage of off-site fabrication. Inform team on benefits and challenges encountered.
Owner / Operator Track and report to the team overall costs. Provide this in comparison to historic cost data.
2. BIM Uses
After careful consideration the team has decided on a number of BIM uses on the project. These uses are based on what stage of the project they are to be completely implemented.
Maturity
BIM Uses
LO
D
-1
(P re -d es ig n)
D
-2
(S ch em at ic
D es ig n
LO
D
-3
(D es ig n De ve lo pm en t)
-3
(C on st ru ct io n
Do cu m en ts
LO
D
-4
(F ab ric at io n
Co ns tr uc tio n)
-5
(C lo se ou
-5
(O pe ra tio n
M an ag em en
Visualization Programming X X
Site Analysis X X
Design Reviews
X X X
Phase Planning (for presentations) X X X X
Documentation Existing Conditions Modeling X X X X X X X
Design Authoring
Cost Estimation (Quantity takeoff)
X
Record Modeling
X X
COBie X X X X X X
BIM Requirements for FM
Model-Based Analysis
Space Management and Tracking
Engineering Analysis
a. Energy Analysis
b. Structural Analysis
c. Lighting Analysis
d. Mechanical Analysis
e. Other Engineering Analysis
Sustainability (LEED) Evaluation
Disaster Planning
Cost Estimation (Estimating) X X X X X X X
Phase Planning (4D modeling)
Site Utilization Planning
Integrated Analyses
3D Coordination
Construction System Design
3D Control and Planning (Digital Layout)
Digital Fabrication (Supply chain management)
Building (Preventative) Maintenance Scheduling
Building System Analysis
Asset Management
Automation & Optimization
Code Validation
Digital Fabrication (Off-site fabrication)
SECTION E: COLLABORATION PROCEDURES
1. Collaboration Strategy:
ePM
• weekly model share between A+E, Revit, CAD, and Navisworks files
• bi-monthly model share with GSA and CMS
Navisworks for visual and interference checks.
2. Meeting Procedures:
The following are examples of meetings that should be considered.
Meeting Type Project Stage Frequency Participants Location
BIM BEP kick-off Concept 1 A+E Team, GSA, CMS
VTC
BIM execution plan demonstration
Concept + Major BEP Revisions
1 + As Needed A+E Team, GSA, CMS
VTC
Design coordination Concept CD Bi-Monthly A+E Team (GSA + CMS as needed)
VTC
3. Model Delivery Schedule of Information Exchange for Submission and Approval:
Document the information exchanges and file transfers that will occur on the project.
Information Exchange
File
Sender
File
Receiver
One-Time Or Frequency
Due Or Start Date
Model File
Model Software
Native File Type
File Exchange Type
Design authoring – 3D coordination
Architect ePM Weekly 09/03/2021 A Revit .rvt .rvt
.nwd
Design authoring –
MEP ePM Weekly 9/03/2021 M, E, P, Revit .rvt .rvt
.nwd
4. Electronic Communication Procedures:
(Note: File Naming and Folder Structure will be discussed in Section H: Model Structure).
The following document management issues should be resolved and a procedure should be defined for each:
Permissions / access, File Locations, FTP Site Location(s), File Transfer Protocol, File / Folder Maintenance, etc.
File Location File Structure / Name File Type
Password Protect
File Maintainer Updated
TBD TBD TBD Don Semple Bi-Weekly
SECTION F: QUALITY CONTROL
1. Overall Strategy for Quality Control:
Lead QC and BIM managers will confirm the use of general BIM best practices by entire team. Quality control checks will be done in accordance with the following schedule.
2. Quality Control Checks:
The following checks should be performed to assure quality.
Checks Definition Responsible Party
Software Program(s)
Frequenc y
VISUAL CHECK Verify that there are no unintended model components and the design intent has been followed
A+E Navisworks Bi-Monthly
INTERFERENCE
CHECK
Detect problems in the model where two building components are clashing including soft and hard
A+E Navisworks Bi-Monthly
STANDARDS
CHECK
Verify that the BIM and AEC CADD Standard have been followed (fonts, dimensions, line styles, levels/layers, model partitioning, common coordinate system and model origin, and any required object enablers)
A+E Revit Monthly
BIM GUIDE
CHECK
Verify that the GSA BIM Guides have been followed (Spatial Program Validation, Circulation and Security Validation, etc.)
A+E Revit Monthly
4D SCHEDULING
CHECK
Describe the utilization of 4D scheduling and construction sequencing technology
CMc
MODEL
INTEGRITY
CHECKS/COBie2
CHECK
Describe the QC validation process used to ensure that the Project Facility Data set has no undefined, incorrectly defined or duplicated elements and the reporting process on non-compliant elements and corrective action plans
A+E BIM
Interoperability Tools for Revit:
Classification Manager + Model Checker
Monthly
SECTION G: TECHNOLOGICAL INFRASTRUCTURE NEEDS
1. Software:
List software used to deliver BIM. (On larger projects the team should consider completing a more comprehensive Data Format Matrix ).
BIM Use Discipline (if applicable) Software Version Design Authoring Arch REVIT Ver 2020
2. Modeling Content and Reference Information Identify items such as families, workspaces, and databases.
BIM USE DISCIPLINE
(if applicable)
MODELING CONTENT /
REFERENCE INFORMATION
VERSION
DESIGN AUTHORING ARCH TBD 2020
https://sites.google.com/a/gsa.gov/gsa-region-5-bim-standards/downloads/documents
SECTION H: MODEL STRUCTURE
1. File Naming Structure:
FILE NAMES
ARCHITECTURAL MODELS MD0415HC_AI_CLL_C1_C2.rvt, MD0415HC_AI_SLL_C.rvt
MECHANICAL MODEL MD0415HC_WSP_M.rvt
PLUMBING MODEL MD0415HC_WSP_P.rvt
ELECTRICAL MODEL MD0415HC_WSP_E.rvt
FIRE PROTECTION MODEL MD0415HC_WSP_FP.rvt
TELECOMUNICATIONSMODEL MD0415HC_WSP_T.rvt
2. Model Structure:
Models separated by building, and discipline.
3. Measurement and Coordinate Systems:
Measurement: Metric Coordinate System:
• Survey Coordinate System/Survey Point: TBD, need to attain additional survey information from GSA +
CMS
• Project Coordinate System/Project Base Point: 0,0,0 point from existing project CAD documentation will be used as the project base point. Specifically: hcfce21.dwg - Composite Exiting Plan at First Level x = 19'-2 1/2" y = 28'-10 7/8" from NE corner of South Building
• Project North: 33.569 clockwise from true north such that Center Building is orthogonal
4. BIM and CAD Standards:
Identify items such as the BIM and CAD standards, content reference information, and the version of IFC, etc.
Standard Version BIM Uses Applicable Organizations Applicable
PBS P-100 2018 Facility Standards All project participants
The National Business Space Assignment Policy (NBSAP)
2017 Assignment, classification, and space measurement standards
All project participants
GSA National BIM Guides 2, 7, & 8
Guide 2 – Version 2 Guide 7+8 – Version 1
Guide 2 – Space Validation Guide 7 – Building Elements Guide 8 – Facilities Management
All project participants
GSA PBS CAD
Standard
March 05, 2012 2D CAD Exports All project participants
5. Model Progression Matrix The Model Progression Matrix is attached to this document. This document is based on the AIA E202 document.
http://gsa.gov/portal/content/105075 http://gsa.gov/portal/content/105075 http://www.gsa.gov/portal/content/104697 http://www.gsa.gov/portal/content/104697 https://sites.google.com/a/gsa.gov/gsa-region-5-bim-standards/documents/level-of-detail
SECTION I: PROJECT DELIVERABLES
GSA BIM Standards require very specific BIM deliverables. The team should familiarize themselves with these requirements before any BIM work is commenced.
Item covered by the Standard Include:
• COBie / IFC data requirements
• Quality Control Report (QCR)
• Class Detection Report (CDR)
• Native format
• Minimum data attributes
• Specific versions of software
• Specific model structure requirements
These standards must be followed by all team members.
Project Stage / Milestone Description of Delivery Estimated Delivery Date
Project Stakeholders Involved
Design Stage
Design Model
Design concept phase
LOD 100-200
Not included in deliverables for concept phase.
09/03/2021 Architect and Mechanical Engineers
Design development phase
LOD 200-300
Preliminary submittal of IFC, COBie, Revit, and Navisworks data for review by GSA.
12/02/2021 Architect and Mechanical Engineers
Construction Documents Phase
LOD 300 Complete
Formal submittal of construction documents and BIM data. All 2D and 3D building data produed on the project in both native format, IFC, and COBie spreadsheets. All design level attribute data will be complete.
06/21/2022 All design team members
Construction Stage
As-built Model
Construction delivery Phase
LOD 400 Complete
Several progress sets of Native format, IFC, and COBie spreadsheets will be provided over the development of the project.
XX/XX/XXXX
XX/XX/XXXX
XX/XX/XXXX
Construction team
Project close-out phase
LOD 500 Complete
Final as-built and record data submittal.
This will include all data required by the Data Submittal Standards as well any extended data agreed to within this BEP.
XX/XX/XXXX All construction and design team
| Submitted Date: 02/24/2021 |
| Submitted By: |
| Table of Contents |
| SECTION A: BIM PROJECT EXECUTION PLAN OVERVIEW |
| SECTION B: PROJECT INFORMATION |
| 1. Project Basics: |
| 2. Project Numbers: |
| 3. Project Schedule/Phases/Milestones: |
| 4. Project Management System |
| SECTION C: KEY PROJECT CONTACTS AND ROLES |
| 1. BIM Roles and Responsibilities |
| 2. Project Contacts |
| Design Team |
| Construction Team |
| SECTION D: PROJECT GOALS/BIM USES |
| 1. Major BIM Goals / Objectives: |
| 1. Major BIM Goals / Objectives (Cont.): |
| 2. BIM Uses |
| SECTION E: COLLABORATION PROCEDURES |
| 1. Collaboration Strategy: |
| 2. Meeting Procedures: |
| 3. Model Delivery Schedule of Information Exchange for Submission and Approval: |
| 4. Electronic Communication Procedures: |
| SECTION F: QUALITY CONTROL |
| 1. Overall Strategy for Quality Control: |
| 2. Quality Control Checks: |
| SECTION G: TECHNOLOGICAL INFRASTRUCTURE NEEDS |
| 1. Software: |
| 2. Modeling Content and Reference Information |
| SECTION H: MODEL STRUCTURE |
| 1. File Naming Structure: |
| 2. Model Structure: |
| 3. Measurement and Coordinate Systems: |
| 4. BIM and CAD Standards: |
| 5. Model Progression Matrix |