Responses_to_Industry's_RFIs_4-17-2018.pdf

PDF 88 KB Posted

Attached to
290 Broadway Elevator Modernization Phase 2
Solicitation number
47PC0318R0004(GS-02-P-18-DT-C-ELEV)
Issued by

About this file

Responses to Industry RFI 4/17/2018

View the file

Other files

File Type Posted
Responses_to_Industry's_RFIs_5-10-2018.pdf PDF
Responses_to_Industry's_RFIs_5-9-2018.pdf PDF
SF30__Amendment_0006_47PC0318R0004_0006_Signed_LZ.pdf PDF
1228.15.00_-_VT-101_LOW-MID_RISE_ELEV-Layout1.pdf PDF
1228.15.00_-_M-002_MECH_SCHEDULES-Layout1.pdf PDF
1228.15.00_-_SP-201_17th_FL_SPRK_PLAN-Layout1.pdf PDF
Responses_to_Industry's_RFIs_5-4-2018.pdf PDF
Reps_and_Certs_C301.pdf PDF
Responses_to_Industry's_RFIs_4-26-2018.pdf PDF
Proposal_Preparation_Instructions_4-26-2018.doc DOC document
Revised_GC_Solicitation_290_Broadway_4-26-_2018.pdf PDF
Solicitation_Amendment_SF_30_47PC0318R0004_0005_Signed.pdf PDF
47PC0318R0004__Form_SF_1442_4-26-2018.pdf PDF
Second_Site_Visit_Attendees_List.pdf PDF
Solicitation_Amendment_47PC0318R0004_0004.pdf PDF
Revised_Additional_Information__-_RFP_47PC0318R0004.pdf PDF
Revised_47PC0318R0004__Form.pdf PDF
Responses_to_Industry's_RFIs_4-19-2018.pdf PDF
Solicitation_Amendment_47PC0318R0004_0003.pdf PDF
290_Photo_Set.pdf PDF
Site_Visit_Attendees_list.pdf PDF
Responses_to_Industry's_RFIs_4-11-2018.pdf PDF
Solicitation_Amendment_47PC0318R0004_0002.pdf PDF
Revised_GC_Solicitation_290_Broadway_4-4-2018.pdf PDF
Revised_GC_Solicitation_290_Broadway.pdf PDF
Revised_47PC0318R0004__Form_1442.pdf PDF
Solicitation_Amendment_47PC0318R0004_0001.pdf PDF
Revised_ATTACHMENT_A1.pdf PDF
Proposal_Preparation_Instructions.pdf PDF
GSA527-15b.pdf PDF
C101_-_GC_Agreement_(1)_(1).pdf PDF
00200_-_Wage_Determination.pdf PDF
01050_-_Partnering.pdf PDF
RFP_Attachments.pdf PDF
47PC0318R0004__Form.pdf PDF
C201_GC_Solicitation_290_Broadway.pdf PDF
New_York_State_Tax_Notice.pdf PDF
SF24-16_(1).pdf PDF
Additional_Information__-_RFP_47PC0318R0004.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Elevator Modernization Project at Ted Weiss Federal Office Building at 290 Broadway

47PC0318R0004

RFI Responses as of 4/17/18

For RFI Responses 1-7, please see Amendment 0002 to the solicitation.

RFI7: Regarding the rigging for the Rooftop unit, going to the top of an elevator shaft. Can the unit, which weighs 2300 lbs, Length 7’7”, Width 4’9”, Height 8’1” be moved through existing openings in the building and utilizing freight elevators to the desired location on the roof, or will it require an external rig to put the unit on the roof?

Response7: It is the contractor’s responsibility to determine “Means and Methods” of the construction.

He may have to disassemble the units into smaller pieces to carry in and reassemble in field. An exterior rig should not be required.

RFI8: If an external rig is required, how high up does the unit need to go, what is the setback for the unit placement and which street would be closed for the rig be set up on?

Response8: Exterior rigging is not recommended. However, it is the contractor’s responsibility to determine “Means and Methods” of the construction, including all required permits from the city.

RFI9: For the unit being removed, what is the weight and dimensions of the unit, and what is the tonnage (Cooling capacity) so that we know how much refrigerant needs to be reclaimed and legally disposed of.

Response9: Unit is 10 tons. Weight, dimensions, and refrigerant charge have to be field verified by potential bidders. A second site visit will be held on April 19, 2018.

RFI10: Copy of the nameplate on the existing switch DP-ELEV-LR? We are replacing switches feeding the elevators and need one new for panel PP-17-EMR .

Response10: Please see attached photographs for nameplate.

File details come from the government source that posted it.