ATTACHMENT 3 PRICE COMPONENT CONFIRMATION TABLE - Amendment 1.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- FY23 R2 NY Competitive Electric Buy
- Solicitation number
- 47PA0723R0006
- Issued by
- Not on record
About this file
This document is a price component confirmation table for a competitive electric buy solicitation by an unnamed federal agency. It details pricing terms for energy commodity costs, capacity costs, ancillary services, line losses, supplier fees, renewable energy certificates, and applicable taxes. Price components such as transmission costs and clean energy standard compliance costs are subject to economic price adjustments. The table also provides known New York renewable energy standards compliance percentages and costs that bidders should incorporate into their bids. Non-price related information like future compliance costs and offshore wind REC costs are excluded from bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment 47PA0723R0006_0001 SF30 QandA Revised Solicitation.pdf | ||
| Solicitation 47PA0723R0006 Exhibit 1 - Amendment 1.xlsx | XLSX spreadsheet | |
| Solicitation 47PA0723R0006 Exhibit 1.xlsx | XLSX spreadsheet | |
| RFP Solicitation No. 47PA0723R0006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PCT
| ATTACHMENT 3 PRICE COMPONENT CONFIRMATION TABLE | |||
| Price Component Confirm Table | |||
| Price Component | Treatment | Include in Bid Price? | Requires Individual Line Item Billing? |
| Energy Commodity Costs | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Minimum of +/- 20% annual bandwidth based on aggregated use of pricing group | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Capacity | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Ancillary Services & Independent System Operator (ISO) costs (including NYPA Transmission Adjustment Charge (NTAC), operating reserves and ISO administrative fees) | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Balancing & Congestion Costs | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Line Losses (including distribution losses to the end use meter) | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Enel X Fee of $0.0007 per kWh addressed in Section A.17 of this solicitation | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Renewable Energy Certificates(RECs) that comply with Section A.12 of this solicitation | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Scheduling | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Fuel Costs | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Supplier Margin | Fixed | Yes | N/A - Fixed in per kWh Award Price |
| Transmission Owner Transmission Solutions (TOTS) | Economic Price Adjusment | No | Yes |
| Public Policy Transmission (PPT) costs | Economic Price Adjusment | No | Yes |
| New York Renewable Energy Standards (RES) compliance costs | Economic Price Adjusment | No | Yes |
| Clean Energy Standard Compliance Costs including Zero Emission Credits (ZECs) | Economic Price Adjusment | No | Yes |
| Applicable taxes including NY Gross Receipts Taxes (GRT) | Pass Through At Cost | No | Yes |
000000INTERNAL#
RES
| Known NY Renewable Energy Standards (RES) compliance percentages and costs at the time of auction. Offerors are instructed to include applicable |
| costs based on the below known percentages or prices in bid prices. Any changes to these percentages or costs by the State of New York as well as |
| future year costs that are not listed below will be addressed under section A.14 ELECTRICITY REGULATORY CHANGES of this solicitation. |
| NYISO Tier 1 Compliance | |
| Compliance Year | Compliance % |
| 2022 | 3.25% |
| 2023 | 6.16% |
| 2024 | 6.45% |
| NYISO Tier II Compliance | |
| 2023 | $.004/MWh |
| NYISO LSE ZEC costs | |
| April 1, 2023 - March 31, 2024 | $3.36 / MWh |
| NYISO Tier IIII Costs |
| Unknown at this time, do not included in bid prices |
| Offshore Wind RECs (OREC) |
| Unknown at this time, do not include in bid prices |
000000INTERNAL#
File details come from the government source that posted it. Updated .