This document is an Addendum to Invitation for Bid 40622 issued by the St. Johns River Water Management District in Florida. The IFB is for the fabrication and installation of six manatee screens upstream of the Burrell Dam water control structure in Polk County, Florida. The addendum provides clarifications in response to questions from potential respondents, including that diving is required both pre-installation to clear the tracks and post-installation to ensure the screens are fully installed with no gaps. The completion date for the installation has been revised to March 31, 2025.
The IFB requires that all dive operations meet the requirements and qualifications of OSHA's commercial dive operations standard. No alternatives to diving, such as verification measurements, will be accepted. The submittal deadline remains 2:00 p.m. on November 21, 2024, and respondents must acknowledge receipt of this Addendum in their bid.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 40622 - Addendum 1.pdf | ||
| Manatee Screens Fabrication and Installation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE: November 20, 2024
TO: Interested Firms
FROM: Breanna Pierce, Procurement Specialist
SUBJECT: Addendum 2 to Invitation for Bid 40622 – Burrell Dam Manatee Screens Fabrication and Installation
As a result of questions received from potential respondents, please be advised of the following changes to the subject Invitation for Bid:
1. The time and date for the submittal of responses remains the same: 2:00 p.m., Thursday, November 21,
2. Question: Will any diving required for the installation of the screens or if everything regarding the install will be done on dry land and lifted or set into place?
Diving is required for pre-installation to ensure the tracks are cleared.
3. Question: Will there be a need for any diving inspections prior to or after the installation?
Diving is required for post-installation to ensure the screens are fully installed with no gaps.
4. Question: Has the completion date been revised?
Yes, STATEMENT OF WORK, section V. TIME FRAMES AND DELIVERABLES: delete and replace with the following:
V. TIME FRAMES AND DELIVERABLES
Deliverables include the fabrication and installation of six manatee screens in accordance with the approved shop drawings. Installation is to be completed by March 31, 2025.
5. Question: Could verification measurements of the dam and screens be used in-lieu of a diver to ensure that the screens are properly seated in the concrete channels?
No, verification measurements of the dam and screens cannot be used in-lieu of a diver.
6. Question: If a diver is required for verification, are they only doing a visual inspection, or is there additional documentation required?
Diving is required pre-installation to ensure the tracks are cleared and post-installation to ensure the screens are fully installed with no gaps.
7. Question: Is a commercial diver required to perform the inspection?
All dive operations shall meet the requirements and qualifications of OSHA 29 CFR 1910 Subpart T Commercial Dive Operations.
NOTE: Please acknowledge receipt of this Addendum in your submittal.