40-51600-24-05645_ITB Jacks Creek Fish Barrier Part 1 ITB Final(2).pdf.PDF
PDF 9 MB Posted
- Attached to
- JACKS CREEK FISH BARRIER
- Solicitation number
- 40-51600-24-05645
- Issued by
- San Miguel County, New Mexico
About this file
This document is an Invitation to Bid (ITB) issued by the New Mexico Department of Game and Fish (NMDGF) for the Jacks Creek Fish Barrier project in San Miguel County, New Mexico. The project involves the construction of an in-stream concrete fish barrier structure, upstream and downstream erosion protection, and revegetation of disturbed areas. The work will require a temporary stream diversion around the work area. A mandatory pre-bid meeting will be held on July 18, 2024, and bids are due by 2:00 PM on August 5, 2024. The anticipated notice to proceed is August 27, 2024. The ITB provides detailed technical specifications for the work, including excavation, concrete construction, backfilling, and revegetation requirements. Preference will be given to in-state/veteran businesses, veterans, Native American, and Native American veteran contractors who obtain the required certification from the New Mexico Department of Taxation & Revenue. The contract does not involve federal funds.
The ITB includes a bid form with several lump sum bid items, including mobilization/demobilization, clearing and grubbing, water management, and the various components of the barrier construction. Payment will be based on the lump sum amounts provided in the bid form. The successful bidder will be required to provide performance and payment bonds. No incumbent contractor information is provided, and the funding source is not explicitly stated.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADVERTISEMENT FOR BIDS
Project Number: JCB-2024
Procurement Number 40-51600-24-05645 The New Mexico Department of Game and Fish is soliciting bids for:
Jacks Creek Fish Barrier
The work shall consist of:
Construction of an in-stream fish barrier structure in Jacks Creek. The project includes construction of a channel crossing cast in place concrete structure, upstream and downstream erosion protection, and revegetation of disturbed areas. The work will require a temporary stream diversion around the work area. All work shall be completed in accordance with the construction plans, specifications & bid documents, and as directed by the project engineer.
Anticipated Notice to Proceed is August 27, 2024.
Bid Opening will be at 2:00 pm August 5, 2024 at the State Purchasing Division at the Montoya Building, 1100 St. Francis Drive, Santa Fe, NM 87505. PLEASE NOTE that all bids must be submitted electronically, and bidders can only attend the bid opening by video conference call. See Instructions to Bidders.
There will be a mandatory pre-bid meeting on July 18, 2024, 11:00 AM MST, at the Project Site. Interested bidders will meet at the project site.
Directions: The project site is accessed from the town of Pecos, New Mexico. Head North on NM-63 from the intersection of NM-50/NM-63 for 20 miles. Parking will be along NM-63 just past where Jacks Creek crosses the road.
STATE PURCHASING DIVISION (GSD)
(505) 827-0472
BIDDER:
Name:
Address:
Phone:
Fax:
E-mail:
INVITATION TO BID
CONSTRUCTION CONTRACT
PROCUREMENT NUMBER: 40-51600-24-05645
Sealed bid opening FORMAL
NM STATE PURCHASING DIVISION
PROJECT NAME:
Jacks Creek Fish Barrier
PROJECT NO.: JCB-2024
BID DUE DATE: August 5, 2024 TIME: 2:00pm Procurement Specialist: James Ortega Contact Number: 505-795-2516 Contact Email: james.ortega@gsd.nm.gov
ARCHITECT/ENGINEER OF RECORD:
Pioneer Technical Services, Inc.
106 Pronghorn Trail Bozeman, MT 59718 Attention: Jon Jupka (406)723-1986
IMPORTANT
Only Electronically submitted bids will be accepted. No hand-carried, mailed, carrier delivered, emailed, or faxed bids will be accepted.
AGENCY (OWNER)/POINT OF CONTACT:
Bryan Bakevich New Mexico Department of Game and Fish 1 Wildlife Way Santa Fe, NM 87507 (505)476-8055
Bids must be submitted electronically, via eProNM only. Please see Bid Submission Instructions on page 2.
Bids are subject to the “Terms and Conditions,” shown on the attached pages of this document, and any additional bidding instructions or requirements.
The Terms and Conditions shall not be modified or supplemented.
NOTE: if you decide not to bid, do not return this document.
A business eligible for a New Mexico/Native American Resident Preference (Preference) must obtain a Preference certificate from the NM Taxation & Revenue Department. In order for the appropriate Preference to be applied to this solicitation, the expenditure for this solicitation cannot involve federal funds, and Bidder must submit a copy of its Preference certificate along with its response to the solicitation. Applicable Preferences will be applied to monetary values only, in accordance with §13-1-21 NMSA 1978, not percentage discounts or other non-monetary values. Additionally, only one submitted Preference will be applied per solicitation, not multiple. Applications are available for download at:
http://www.tax.newmexico.gov/Businesses/in-state-veteran-preference-certification.aspx
Technical Online Bidding Questions:
(505) 795-1894 or (800) 233-1121 or you can contact the buyer listed on the ITB front page.
Bidder Instructions for Invitation to Bid (ITB)
Viewing ITB:
1. Bidders can access active procurements at the following sites:
• https://www.generalservices.state.nm.us/statepurchasing/active-procurements.aspx
• https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=StateOfNewMexico
2. Complete bid documents as required by the ITB Specifications, and submit any required documentation, supporting materials, certificates, etc. in addition to the bid documents.
Submitting Bids:
Complete bid documents as required by the ITB Specifications, and submit any required documentation, supporting materials, certificates, etc. in addition to the bid documents.
• Electronic submissions through eProNM at the following site:
https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=StateOfNewMexico Bids will be time-stamped in the system when Bidder clicks “OK” after “Review and Submit.” Such electronic submissions will be considered sealed bids in accordance with statute.
If an amendment is processed after bid is submitted, Bidders must resubmit their bid in order for it to be considered fully submitted. Note: It is the responsibility of the Bidder to ensure bids are correct and accurate before submission.
By bidding electronically, you acknowledge any and all amendments and it is your responsibility to ensure your bid corresponds with any amendments.
It is the Bidder’s responsibility to ensure all documents are completely uploaded and submitted electronically via the eProNM system by the deadline set forth in this ITB. The eProNM system will automatically cease uploading data at the date and time of the deadline. Please ensure that you, as the Bidder, allow adequate time for large uploads and to fully complete your submittal by the deadline. A submission that is not both: (1) fully complete; and (2) received, via the eProNM system by the deadline, will be deemed late. Further, a submission that is not fully complete and received via the eProNM system by the deadline because the response was captured, blocked, filtered, quarantined or otherwise prevented from reaching the proper destination server by any anti-virus or other security software will be deemed late. In accordance with statute and rule, NO LATE BID CAN BE ACCEPTED.
Bid Opening:
Sealed bids will be publicly opened online via Microsoft Teams. Bids are subject to the “Terms and Conditions,” shown on the subsequent pages of this document, and any additional bidding instructions or requirements. NOTE: if you decide not to bid, do not return this ITB document.
https://teams.microsoft.com/l/meetup-join/19%3ameeting_Y2IyZTlhMjEtYWZlYS00Nzc4LThjOWQtMGI3MWQxMWNlMzhk%40thread.v2/0?context=%7b% 22Tid%22%3a%2204aa6bf4-d436-426f-bfa4-04b7a70e60ff%22%2c%22Oid%22%3a%2251de2250-9e0b-4237-b5ee-d3e9e1e586fc%22%7d Meeting ID: 210 089 867 732
Passcode: 4W2kXN Download Teams | Join on the web Or call in (audio only) +1 505-312-4308,,45609571# United States, Albuquerque Phone Conference ID: 456 095 71# https://www.generalservices.state.nm.us/statepurchasing/active-procurements.aspx https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=StateOfNewMexico https://teams.microsoft.com/l/meetup-join/19%3ameeting_Y2IyZTlhMjEtYWZlYS00Nzc4LThjOWQtMGI3MWQxMWNlMzhk%40thread.v2/0?context=%7b%22Tid%22%3a%2204aa6bf4-d436-426f-bfa4-04b7a70e60ff%22%2c%22Oid%22%3a%2251de2250-9e0b-4237-b5ee-d3e9e1e586fc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_Y2IyZTlhMjEtYWZlYS00Nzc4LThjOWQtMGI3MWQxMWNlMzhk%40thread.v2/0?context=%7b%22Tid%22%3a%2204aa6bf4-d436-426f-bfa4-04b7a70e60ff%22%2c%22Oid%22%3a%2251de2250-9e0b-4237-b5ee-d3e9e1e586fc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_Y2IyZTlhMjEtYWZlYS00Nzc4LThjOWQtMGI3MWQxMWNlMzhk%40thread.v2/0?context=%7b%22Tid%22%3a%2204aa6bf4-d436-426f-bfa4-04b7a70e60ff%22%2c%22Oid%22%3a%2251de2250-9e0b-4237-b5ee-d3e9e1e586fc%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_Y2IyZTlhMjEtYWZlYS00Nzc4LThjOWQtMGI3MWQxMWNlMzhk%40thread.v2/0?context=%7b%22Tid%22%3a%2204aa6bf4-d436-426f-bfa4-04b7a70e60ff%22%2c%22Oid%22%3a%2251de2250-9e0b-4237-b5ee-d3e9e1e586fc%22%7d https://www.microsoft.com/en-us/microsoft-teams/download-app https://www.microsoft.com/microsoft-teams/join-a-meeting tel:+15053124308,,45609571
THIS BID IS SUBJECT TO THE REQUIREMENTS OF THE BIDDING DOCUMENTS AS DEFINED IN THE
"INSTRUCTIONS TO BIDDERS.”
THE BID PROPOSAL FORM MUST BE ACCOMPANIED BY A SURETY BOND, SUBCONTRACTOR LISTING
FORM, AND DOCUMENTS SPECIFIED IN THE "INSTRUCTIONS TO BIDDERS."
INVITATION TO BID Section 2
Bidding Documents: Bidding documents, plans, specifications, drawings etc. may be obtained on the State Purchasing Website (add site).
The Bidding Documents contain a time for completion of the work and further impose liquidated damages for failure to complete the work within that time period.
Bids shall be presented in the form of a total Base Bid proposal under a Lump Sum Contract plus any additive or deductive alternates that are selected by the Owner. A bid must be submitted on all bid items and alternates;
segregated bids will not be accepted.
NOTE: Base Bid price shall not include state gross receipts or local options taxes. Taxes will be included in the Contracted Amount at prevailing rates as a separate item to be paid by Owner.
In submitting this bid, each Bidder must satisfy all terms and conditions of the Bidding Documents. No Bidder may withdraw his bid for 120 DAYS after the actual date of the opening thereof.
Wage Rates & Workforce Solutions Registration: Pursuant to the Public Works Minimum Wage Act, Section 13-4-10 to 13-4-17 NMSA 1978, all work covered by this Invitation to Bid shall be in accordance with applicable state laws and, if the bid amount is sixty thousand dollars ($60,000) or more, is subject to the minimum wage rate determination issued by the New Mexico Department of Workforce Solutions, Labor Relations Division, Public Works Unit. Section 13-4-13.1 requires Contractors when their bid is over $60,000 and subcontractors of all tiers when their portion of the work is over $60,000, to be registered with the Labor Relations Division of the Department of Workforce Solutions. This registration is available under the “Contractor Registration” section at the following website:
http://www.dws.state.nm.us/LaborRelations/LaborInformation/PublicWorks
There may be some administrative delay in processing your registration. Pursuant to Section 13-4-13.1 NMSA 1978, the State Purchasing Division cannot accept your bid if you are not registered at the time of bid opening.
Please direct all questions concerning registration to DWS at (505) 841-4400.
A completed Subcontractor Listing Form must accompany each bid.
INVITATION TO BID Section 3
Bonds: Bid Security in the form of a surety bond executed by a surety company authorized to do business in the state of New Mexico in the amount of five percent (5%) of the total bid, or the equivalent in cash by means of a cashier's check or in a form satisfactory to the Owner, must accompany each bid in accordance with the Instructions to Bidders.
A 100% Performance Bond and a 100% Payment and Materials Bond for the total contract amount, including appropriate New Mexico Gross Receipts Tax, executed by a surety company authorized to do business in the state of New Mexico shall be required from the successful Bidder prior to award of contract. A subcontractor http://www.dws.state.nm.us/LaborRelations/LaborInformation/PublicWorks shall provide performance and payment bonds if the subcontractor’s contract (to the Contractor) for work to be performed is $125,000 or more. Failure of a subcontractor to provide the required bonds shall not subject owner to any increase in cost due to approved substitution of subcontractor.
Preferences: Applicants for in‐state / veteran preferences for all resident businesses, veterans, Native American, Native American veteran and contractors will have to obtain preference numbers from the New Mexico Department of Taxation & Revenue. Vendor must submit a copy of their preference certificate with each solicitation in order to receive the preference. Applications are available for download at the following website:
Attention of the Bidder who normally qualifies for a preference is particularly directed to the provisions of Sections 13-4-1 through 13-4-4 NMSA 1978 as they shall not apply to federal aid construction projects or when the expenditure of federal funds designated for a specific contract is involved. All contracts executed in violation of this act shall be void and of no effect. No federal funds will be used for this project. Preference points will apply.
INVITATION TO BID Section 4
A Mandatory Pre-Bid Meeting will be held as follows:
DATE: July 18, 2024
TIME: 11:00 AM
LOCATION: Project Location (Jacks Creek)
DIRECTIONS: The project site is accessed from the town of Pecos, New Mexico. Head North on NM-63 from the intersection of NM-50/NM-63 for 20 miles. Parking will be along NM-63 just past where Jacks Creek crosses the road.
POINT OF CONTACT:
Bryan Bakevich (505)476-8055 Bryan.bakevich@dgf.nm.gov
Additional Deadlines:
Questions Deadline: July 22, 2024 Answers Deadline: July 26, 2024
END OF INVITATION TO BID
mailto:Bryan.bakevich@dgf.nm.gov
Jacks Creek Fish Barrier Project
San Miguel County, New Mexico
Prepared by:
Pioneer Technical Services, Inc.
106 Pronghorn Trail, Suite A Bozeman, MT 59718
December 22, 2023
Prepared for:
New Mexico Department of Game & Fish
1 Wildlife Way Santa Fe New Mexico 87507
Issued for Construction
TECHNICAL SPECIFICATIONS
These technical specifications address all anticipated construction and excavation activities to be completed during the Jacks Creek Fish Barrier installation.
INDEX TO TECHNICAL SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01000 SUMMARY OF WORK...............................................................01000-1
SECTION 01010 GENERAL PROCEDURES.........................................................01010-1
SECTION 01570 TEMPORARY TRAFFIC CONTROL ........................................01570-1
DIVISION 2 - SITEWORK
SECTION 02110 SITE CLEARING ........................................................................02110-1
SECTION 02140 CONSTRUCTION DEWATERING ...........................................02140-1
SECTION 02200 EXCAVATION ...........................................................................02200-1
SECTION 02210 FILL MATERIALS AND PLACEMENT REQUIREMENTS....02210-1
SECTION 02220 TRENCH EXCAVATION AND BACKFILL (Not Used)…..…02220-1
SECTION 02270 STREAM CHANNELS AND DIVERSIONS……………….....02270-1
SECTION 02710 GEOSYNTHETIC MATERIALS ...............................................02710-1
SECTION 02910 SEEDING ....................................................................................02910-1
DIVISION 3 - CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE..................................................03300-1
DIVISION 5 - METALS
SECTION 05120 MISCELLANEOUS METALS (Not Used).................................05120-1
APPENDIX LISTING
Appendix A……………………………..…….……..Technical Drawings
Appendix B………………………………….……...…………Wage Rate
Appendix C……………………………………...………………Bid Form
Appendix D…………………………….....…….…. Instruction to bidders
Appendix E……………………….…………….…. Debarred Contractors
Appendix F……………………....….….DFA Agency Certification Form
Appendix G…….....…. New Mexico Health Coverage Verification Form
Appendix H………………………………….…. Sub-Contractors Listing
Appendix I…………......Contract for Construction Agreement (Example)
Appendix J……………...…General Conditions of Construction Contract
Appendix K……………………….......….. Bonds Certificate and Notices
Appendix L…………….. Supplemental Conditions/Change Order Forms
01000-1
SECTION 01000
SUMMARY OF WORK
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Related Documents B. Summary Scope of Work
1.02 RELATED DOCUMENTS
A. Drawings included in Appendix A
Sheet No. Drawing Title 1 Cover Sheet and Index 2 Legends and Abbreviations 3 Site Plan 4 Water Management Plan 5 Stream Diversion Details 6 Excavation Plan 7 Alternate 1 Excavation Plan 8 Structure Plan 9 Profile and Cross Section 10 Structural Details 11 Structural Details 12 Backfill Plan 13 Backfill Plan Typical Sections and Details
1.03 SUMMARY SCOPE OF WORK
The scope of work addressed by these plans and specifications consists of installation of a concrete fish barrier wall, downstream and upstream erosion protection on the Jacks Creek for the New Mexico Department of Game and Fish (NMDGF). Jacks Creek is a tributary to the upper Pecos River located in San Miguel County. The project is located approximately 6.2 miles north of Tererro, New Mexico and is accessed by New Mexico Highway 63.
The Contractor or Contractors shall perform the following work per these specifications:
A. Install one fish barrier structure with associated erosion protection.
1.04 ADDITIONAL RESPONSIBILITES
01000-2
A. The Contractor is obligated to immediately notify the Engineer and the NMDGF in the event of construction problems in order to facilitate practical, functional and cost-effective project modifications. These problems may be associated with differing site conditions, construction staking and measurements, conflicts between plan drawings and specifications, defective materials or other issues.
1.05 MEASUREMENT AND PAYMENT
A. Work items for which specific unit prices are established will be measured to the nearest unit applicable. Payment for each pay item will be made at the agreed-to unit price for that item. For established lump sum work items, payment will be made at the lump sum price. Such payment will constitute full compensation for all materials, labor, equipment, tools and all other items necessary and incidental to completion of the work.
B. Compensation for any item of work shown on the Drawings or described in these specifications will be considered incidental to and included in the pay items listed on the bid schedule.
Bid Item 1-3Mobilization/Demobilization/Bonding & Insurance
Mobilization shall include all activities and associated costs for transportation of Contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the Contractor's operations at the site; premiums paid for performance and payment bonds, including coinsurance and reinsurance agreements as applicable.
Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal and site clean-up, of offices, buildings and other facilities assembled on the site specifically for this contract.
This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the Contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
Work under this Item Include:
• Mobilize and demobilize to and from the project area with all necessary equipment to complete the Work.
• Provide insurance and bonding for the Contract.
• Obtain all required permits and provide copies to Engineer.
• Prepare and submit all preconstruction submittals to Engineer for approval.
01000-3
• Provide and remove temporary offices, storage and sanitation facilities.
• Provide site security.
• Dispose of all trash and debris generated by Contractor at a state-licensed solid waste management facility.
• Dispose of non-vegetative debris, per specifications.
• Provide all labor, tools, equipment, materials, and incidentals necessary to complete the Work as specified.
• Construct and maintain all access roads as required.
• Traffic Control as required.
Measurement Bid Item 1-3 No measurement will be made for Bid Item 1-3.
Payment Bid Item 1-3 Payment for Bid Item 1-3 will be based on the lump sum amount as shown on the Bid Proposal Form. Fifty percent (50%) payment for this Bid Item will be allowed once Contractor submits Bond and Insurance Certificates, fully mobilizes to the project area, and obtains approval on all submittals required prior to beginning Work. Full payment for this item will be allowed after Contractor completes the Work for the remainder of the Contract, completes final cleanup work, and fully demobilizes equipment and materials from the project area.
Bid Item 4 Clearing and Grubbing
All costs including clearing, grubbing, and disposal of vegetation. All construction staking costs shall be included.
Work under this item includes:
• Clear and grub.
• Separate large woody debris from Type D Cover Soil,
• Salvage and stockpile woody debris, dispose of per Specifications,
• Provide all labor, tools, equipment, materials, and incidentals necessary to complete the Work as specified,
• Construction staking,
• Dust control.
Measurement Bid Item 4 No measurement will be made for Bid Item 4.
Payment Bid Item 4 Payment for Bid Item 4 will be based on the lump sum amount as shown on the Bid Proposal Form.
Bid Item 4- Water Management
01000-4
Contractor shall perform all dewatering and water management throughout the Contract necessary to complete the excavation, construction of the fish barrier and backfilling of the barrier. Contractor shall provide and operate all pumps necessary to remove groundwater and surface water from Work area. Contractor shall perform all stream diversion, dewatering and material handling, necessary to facilitate the construction of the fish barrier. Contractor shall prepare and submit to Engineer for review and approval a dewatering and water management plan detailing Contractor’s proposed approach.
Work under this item includes:
• Work under this item includes: Completing all stream diversion, dewatering, pumping, and water management activities.
• Provide all labor, tools, equipment, materials, and incidentals necessary to complete the Work as specified.
Measurement Bid Item 5 No measurement will be made for Bid Item 5.
Payment Bid Item 5 Payment for Bid Item 5 will be based on the lump sum amount as shown on the Bid Proposal Form.
Bid Item 6-16 Barrier Construction
The Contractor shall perform all work required to construct the fish barrier per the Drawings and these specifications. The work includes but is not limited to excavation, construction of a concrete fish barrier, structural backfill and placement of riprap.
Work under this item includes:
• Obtain all required materials,
• Survey/Construction staking,
• Excavate channel/floodplain for placement of barrier,
• Construction of all reinforced, formed concrete work to construct the fish barrier,
• Placement of Type A, Type B Fill, and Type C Fill,
• Placement of Riprap,
• Placement of Type A Geotextiles,
• All testing,
• Provide all labor, tools, equipment, materials, and incidentals necessary to complete the Work as specified.
Measurement Bid Item 6-16 No measurement will be made for Bid Item 6-16.
Payment Bid Item 6-16 Payment for Bid Item 6-16 will be based on the lump sum amount as shown on the Bid Proposal Form.
01000-5
Bid Item 17-18 Final Grading and Revegetation
Contractor shall perform all final grading and revegetation as shown on the Drawings and per these specifications.
Work includes:
• Obtaining all required materials,
• Placing and grading Type D Cover Soil,
• Seeding,
• Placing erosion control fabric,
• Spread small woody debris in adjacent USFS property as directed by Engineer,
• Survey/Construction Staking,
• Provide all labor, tools, equipment, materials, and incidentals necessary to complete the Work as specified.
Measurement Bid Item 17-18 No measurement will be made for Bid Item 17-18.
Payment Bid Item 17-18 Payment for Bid Item 17-18 will be based on the lump sum amount as shown on the Bid Proposal Form.
END OF SECTION 01000
sferguson Sticky Note Cancelled set by sferguson
01010-1
SECTION 01010
GENERAL PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. PROGRESS SCHEDULES
B. TEMPORARY FACILITIES AND SITE CONTROL
C. CONSTRUCTION SURVEYING
D. SUBMITTALS
E. TRAFFIC CONTROL AND SITE SAFETY
F. EROSION AND SEDIMENT CONTROL
G. CONSTRUCTION SEQUENCING AND OTHER CONTRACTORS
H. EXISTING STRUCTURES
I. RECORD KEEPING REQUIREMENTS
1.02 PROGRESS SCHEDULES
Contractor shall prepare an initial project schedule and shall update and maintain the schedule appropriately. Copies of all initial schedules and updates shall be provided to the Engineer upon request.
1.03 TEMPORARY FACILITIES AND SITE CONTROL
Contractor shall notify and coordinate with all appropriate utility companies and NMDGF before conducting work proximate to overhead or buried utilities.
1.04 CONSTRUCTION SURVEYING
Contractor shall provide all construction surveying needed to complete the work.
1.05 SUBMITTALS
Contractor shall provide to the Engineer complete product information and shop
01010-2 drawings where required for all materials and equipment proposed for incorporation into the project. Information shall include manufacturer, model or catalog designation, reference standards, complete installation instructions, and shop drawings that show dimensions and location of all parts. Information shall be submitted prior to ordering, and in a timely manner to provide the Engineer time for review and approval.
1.06 TRAFFIC CONTROL AND SITE SAFETY
Contractor shall provide all necessary temporary traffic control to complete the Work. Contractor shall develop a site-specific Traffic Control Plan in accordance with Section 01570 of these Technical Specifications.
1.07 EROSION AND SEDIMENT CONTROL
A. Temporary diversions for storm runoff or Jacks Creek flows shall be constructed as specified and as needed to direct flows around the work area.
These diversions shall be designed, implemented and maintained by the Contractor in accordance with Best Management Practices (BMPs) to control erosion and sediment release into Jacks Creek. BMPs may include, but are not limited to, temporary berms, cofferdams, sediment basins, ditches, straw bales, straw mulch, and erosion control matting.
B. The Contractor shall plan and execute work to control and minimize surface runoff from cuts, fills, and other disturbed areas. The Contractor shall prevent sediment and/or sediment-laden water from entering Jacks Creek to the extent practicable.
C. Keep heavy equipment clean and well maintained to prevent leaks.
D. Dewatering is anticipated for this project. All dewatering flows collected from open sumps, trenches or excavations shall be routed through sediment retention structure prior to discharge to Jacks Creek. The Contractor shall comply with the dewatering requirements of Section 02140. All storm runoff flows from work areas also shall be routed through sediment retention structures prior to discharge.
E. Best Management Practices (BMP) measures shall be installed along Jacks
Creek prior to any earthwork which could release sediment to Jacks Creek.
BMP shall remain in place until vegetation is established, as approved by NMDGF and the USFS. The methods implemented by the Contractor will be monitored by NMDGF and USFS to assure compliance with BMP’s.
1.08 CONSTRUCTION SEQUENCING AND OTHER CONTRACTORS
01010-3
Contractor shall coordinate his construction activities with those of any and all other contractors that may be working on the site or adjacent sites. Contractor's work shall be conducted in a manner that will not impede the progress of other concurrent construction activities.
1.09 EXISTING STRUCTURES
A. The Contractor shall notify and coordinate with all appropriate utility companies and with the Engineer to field-locate overhead or buried utilities, wells, and other existing structures prior to construction. Location, depth, size, and material of existing buried utilities within excavation limits shall be verified prior to beginning construction.
B. The Contractor shall be responsible for protecting existing structures within and external to the construction area. Any damage to existing structures, whether above or below ground level, shall be repaired to the owner’s satisfaction by the Contractor at no additional cost to NMDGF.
END OF SECTION 01010
01570-1
SECTION 01570
TEMPORARY TRAFFIC CONTROL
This section covers all labor, supplies, materials, equipment, and incidentals necessary for traffic control consisting of furnishing, installing, maintaining, and relocating traffic signs, barricades, lights, signals, pavement markings, and other traffic control devices necessary to ensure the safety of the general public and Project personnel in compliance with the Contract Documents. Work shall include flagging for the guidance of traffic through the Site and for public roadways.
REFERENCES
Publications listed below are incorporated into this specification by reference.
American Association Of State Highway And Transportation Officials (AASHTO)
AASHTO The Green Book (2011) A Policy on Geometric Design of Highways and Streets, 6th Edition
U.S. Federal Highway Administration (FHWA)
MUTCD (2009) Manual on Uniform Traffic Control Devices
(MUTCD)
1.02 SUBMITTALS
A. Prepare and submit a Traffic Control Plan for any Work involving public roadways no later than ten (10) days prior to the start of Work. The Traffic Control Plan will be subject to review and approval by the appropriate county for roads under county jurisdiction, and by any other public entity having jurisdiction over other public roadways (e.g., U.S. Forest Service, city, etc.).
These approvals will be in addition to that provided by Engineer in accordance with the Submittals Section. No Work may commence until all approvals of the Traffic Control Plan have been secured.
PART 2 PRODUCTS
A. All traffic control devices and materials shall be in accordance with the most current editions of MUTCD for Streets and Highways.
01570-2
PART 3 EXECUTION
3.01 GENERAL
A. Provide traffic control signage and flaggers as necessary to safely complete the Work while accommodating public traffic. Traffic control shall conform to the standards set forth in MUTCD, current edition.
B. Schedule operations to minimize interruptions of the streets, roads, and highways involved and keep all roads, streets, and highways open during normal working hours during the Work. Provide uninterrupted two-way traffic at all times during overnight and weekend periods. . If any of the roads are to be closed during construction operations, give at least 14 days advance notice. Unless otherwise provided, when construction activity is in progress and total closure has not been provided for herein, delays may not exceed 10 minutes, in order to reasonably accommodate traffic.
C. Schedule construction operations in a manner to ensure that: 1) the safety and convenience of motorists, bicyclists, and pedestrians, and the safety of all personnel, are adequately met at all times; and 2) the Project is completed in a manner most beneficial to the Project as a whole.
D. Observe posted speed limits on the roads leading to the Site as well as all other public roadways. All vehicles used in the Work shall strictly comply with these limits. Observe legal and posted weight limits for roadways and bridges in all hauling activities.
E. All construction and Project-related traffic shall come to a complete and full stop when exiting the Site and yield the right-of-way to traffic on the public roadways, unless flagging protection is approved and implemented.
3.02 TRAFFIC CONTROL PLAN
A. Prepare a Traffic Control Plan including, but not limited to, the following:
1. Itemization of signs, including: type, size, shape, color and location.
2. Channelization (e.g., cones, barrels, barricades).
3. Flagging and location(s).
4. Lighting.
5. Communication.
6. Road closures and time of road closures.
01570-3
7. Special traffic patterns (e.g., pilot cars, one-way traffic lanes, detours).
8. Signs during non-work hours.
9. Designated entrances to the Project area.
10. Map and descriptions of the anticipated routes.
11. Description of the anticipated haul equipment.
12. Traffic control measures for all public roads, haul routes, and Site access points.
13. Locations of all signs, markers, barricades, and other traffic control devices to be used.
14. Routing of any detours required.
3.03 CONSTRUCTION REQUIREMENTS
A. Provide traffic control in full compliance with MUTCD during materials hauling and equipment operation or transport along public roadways.
B. Store or park construction equipment, vehicles, materials, and debris a minimum of 30 feet from the edge of the travelled way or behind guardrail.
When it is not feasible to park equipment or store materials a minimum of 30 feet from the edge of the travelled way or behind guardrail, utilize adequate warning devices and protective measures.
C. Maintain at least one-way traffic at all times with continuous passage for emergency vehicles from either direction. Delay to the public shall be no longer than 10 minutes.
D. At the conclusion of daily construction activities, ensure that necessary traffic control measures remain in effect overnight and through the weekend, including barricades around any open excavations or other hazards.
TRAFFIC CONTROL DEVICES
A. Before placement for any stage of construction, all traffic control devices required for that stage shall be on-hand at the Site. Properly place, install, and operate all traffic control devices necessary for construction. Obtain approval of the placement and operation from Engineer before starting construction.
01570-4
B. Properly maintain, clean, and operate traffic control devices during the entire length of use.
C. Immediately remove all traffic devices no longer needed for traffic control.
D. For operations completed in stages, place only signage applicable to the present stage of construction. Remove, turn, or cover with opaque material any signage not applicable to the existing conditions, during shutdowns longer than two (2) hours, at night, when not needed on weather days, holidays, and weekends so as not to be readable to oncoming traffic.
E. Set, size, and locate signs in a manner that they are visible to the equipment operators and other vehicles as necessary.
F. All traffic control devices furnished by CONTRACTOR shall remain the property of CONTRACTOR. Repair or replace traffic control devices when damaged or destroyed by traffic or other activities, or when traffic control devices fail to function properly at no cost to NMDGF.
END OF SECTION 01570
02110-1
SECTION 02110
SITE CLEARING
A. Removal of surface debris.
B. Clearing and grubbing of all vegetation including trees, shrubs, and grass.
Not Used.
3.01 PROTECTION
A. Locate, identify, and protect existing utilities from damage.
B. Protect benchmarks and existing structures from damage or displacement.
3.02 CLEARING
A. Clear all surface debris and vegetation, including the root zone, from all areas impacted by the Work and as required for access to site and execution of Work as shown on the Drawings, and as directed by NMDGF.
B. Remove identified trees, shrubs, stumps, roots, brush, rubbish, and other objectionable material within work areas and from the surfaces of all borrow areas and stockpile sites.
3.03 REMOVAL
A. Removed trees with diameters greater than 2-inches shall be cut into 6-foot lengths and stockpiled on site as directed by the Engineer or USFS.
B. Remove debris, rock, and extracted vegetation and dispose of materials by spreading debris in adjacent forest as directed by the Engineer or USFS.
END OF SECTION 02110
02140-1
SECTION 02140
CONSTRUCTION DEWATERING
A. This Section specifies dewatering requirements and procedures necessary during installation and use of dewatering pumps and appurtenances, groundwater collection trenches/sumps, and dewatering wells and/or wellpoints.
1.02 RELATED SECTIONS
Section 02200 - Unclassified Excavation
1.03 SUBMITTALS
A. The Contractor shall submit a Construction Dewatering Plan to the Engineer prior to executing the work for review and approval by the Engineer and NMDGF. The Construction Dewatering Plan shall be a written procedure for implementing the construction dewatering requirements specified herein.
The plan shall describe the layout, materials, and equipment, and the operation and maintenance procedures proposed. The Construction Dewatering Plan shall meet any criteria set forth in the 401/404 permit.
1.04 DESCRIPTION OF SITE CONDITIONS
A. The site condition description provided herein is based on surface observations conducted by the Engineer. No subsurface exploration was conducted.
1. General: Within the project area, Jacks Creek flows in a southerly direction and straight and fairly uniform throughout the project area.
It is anticipated that dewatering will be necessary for this project. The seasonal (August to October) average baseflow is estimated between 1
- 10 cfs. The fish barrier site is approximately 65-feet downstream of the natural waterfall and is bounded by exposed bedrock on both the east and west boundaries. At the downstream end of the site, the bedrock on the east boundary dips and the stream corridor widens to the east providing a broad floodplain. The area on either side of the proposed structure appears to be competent bedrock but the extent of the bedrock below the ground surface is unknown.
2. Groundwater: No groundwater discharge points were observed during the field work. Therefore it is anticipated that local
02140-2 groundwater levels are at or below the stream channel water surface elevations. The subsurface conditions at the site may lead to unstable excavations if groundwater is encountered and proper dewatering controls are not implemented and maintained during construction.
2.01 EQUIPMENT
A. The Contractor shall provide, and maintain on site, all equipment, piping, fittings, and appurtenances necessary to collect, pump, and convey discharge water to adequately dewater all open excavations, including spare fittings, pumps and other materials necessary to maintain a continuously operating dewatering system.
B. The Contractor shall provide and maintain primary and backup power supplies and power distribution systems as necessary to operate the dewatering system without significant interruption. All grounding shall be provided per the NEC. The power plants and their appurtenances shall be protected from weather and other potentially detrimental conditions at the site (e.g., dust, impacts, etc.)
C. The Contractor shall provide all necessary equipment and materials to collect and pump dewatering flows.
PART 3 EXECUTIONS
3.01 DEWATERING
A. The Contractor shall fully implement all measures and precautions necessary to ensure the safety of workers, and the protection of the Work (including maintenance of integrity against rupture and/or heave of the bottom of the excavation) during excavation and dewatering, including, but not limited to, full implementation of the requirements of this Section 02140.
B. The Contractor shall provide backup and spare equipment (as specified in
Part 2.01), immediately available for installation and/or operation to minimize any interruption in the required pumping. In the event of pump failure for reasons beyond the Contractor’s ability to control, all excavation shall cease, and the Contractor shall implement repairs and resume pumping as soon as possible.
02140-3
C. Maintain excavation dewatering sufficiently to allow for visual inspection, quality assurance, and as-built surveying, to be conducted by Engineer at their discretion.
END OF SECTION 02140
02200-1
SECTION 02200
EXCAVATION
SECTION INCLUDES
A. Work under this Section includes unclassified excavation associated with the installation of the Jacks Creek Fish Barrier and roadway excavation.
Section 02110 - Clearing and Grubbing Section 02140 - Construction Dewatering Section 02210 - Fill Materials and Placement
1.03 REGULATORY REQUIREMENTS
A. Sheeting, Shoring, and Bracing: Except where trench banks are cut back on a stable slope, provide and maintain all sheeting, shoring, and bracing necessary to protect workers, and to protect adjoining grades and structures from caving, sliding, erosion or other damage in accordance with Occupational Safety and Health Standards (29 CFR Part 1926 - Construction Standards for Excavations), the Site Specific Health and Safety Plan, and other applicable codes and governing authorities.
1.04 FIELD MEASUREMENTS
A. Verify that survey coordinates and elevations indicated on the Drawings are accurate as indicated. Notify Engineer of any discrepancies prior to construction.
PART 2 PRODUCTS (Not used)
3.01 PREPARATION
A. Identify required lines, levels, contours, and datum.
B. Accurately locate, identify, and protect from damage all utilities, benchmarks, monitoring wells and other structures not designated for demolition. The Contractor is responsible for verifying that all utilities through the work area have been accurately located prior to excavation, and that no conflicts exist.
02200-2
C. If temporary diversions for storm runoff or base flows are deemed necessary by the Contractor, they shall be designed, implemented and maintained by the Contractor as specified in Section 01010, Part 1.06.
3.02 EXCAVATION
A. Excavation shall conform to the boundaries, elevations, and excavation slopes shown on the Drawings. Limits of excavation shall be the minimum required to complete the Work.
B. Remove loose material, lumped subsoil, boulders, and loose rock from excavations leaving excavation surface exposed and clean.
C. Graded areas shall be sloped to promote surface drainage and discourage ponding.
D. Stockpile excavated materials suitable for backfill along the excavation at a safe distance in accordance with Occupational Safety and Health Regulations, and other applicable codes and governing authorities.
Excavated materials not suitable for backfilling shall be wasted on site as directed by the Engineer.
3.03 PROTECTION
A. Protect excavations as required to prevent cave-in or loose soil from falling into excavation.
3.04 TOLERANCES
A. Excavate to within ± 0.2 feet of elevation and location as shown on the Drawings.
B. Maintain excavation dewatering sufficiently to allow for visual inspection and as-built surveying, to be conducted by the Engineer at their discretion.
C. Any areas of over-excavation shall be filled with Type A Fill or Type B Fill, as directed by the Engineer and at no additional cost to NMDGF.
3.05 FIELD QUALITY CONTROL
A. Provide for access, visual inspection, and construction surveying of excavation surfaces as required by the Engineer.
END OF SECTION 02200
02210-1
SECTION 02210
FILL MATERIALS AND PLACEMENT REQUIREMENTS
This section specifies fill materials, borrow areas/sources of fill materials, and fill placement requirements for the following:
1. General Site Backfill;
2. Road Fill;
3. Road Surfacing Aggregate
Section 03300 – Cast In Place Concrete Section 02270 – Stream Channels and Diversions
Submit data sheets and test results from compliance testing of materials provided by Contractor to the Engineer for review and approval.
1.04 REFERENCES
A. Sampling and Preparation
1. ASTM D75 - Standard Practice for Sampling Aggregates.
2. ASTM D420 - Recommended Practice for Investigating and Sampling Soil and Rock.
B. Classification
1. ASTM D421 - Standard Practice for Dry Preparation of Soil Samples for Particle-Size Analysis and Determination of Soil Constants.
2. ASTM D422 - Standard Method for Particle-Size Analysis of Soils.
3. ASTM D2487 - Classification of Soils for Engineering Purposes.
4. ASTM D2488 - Standard Practice for Description and Identification of Soils (Visual-Manual Procedure).
02210-2
5. ASTM D4318 - Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils.
C. Density and Moisture Content: Field
1. ASTM D1556 - Test Method for Density of Soil in Place by the Sand-Cone Method.
2. ASTM D2922 - Test Methods for Density of Soil and Soil- Aggregate in Place by Nuclear Methods (Shallow Depth).
3. ASTM D3017 - Test Methods for Moisture Content of Soil and Soil-Aggregate Mixtures.
D. Density and Moisture Content: Laboratory
1. ASTM D698 or AASHTO T99 - Test Methods for Moisture-Density
Relations of Soils and Soil-Aggregate Mixtures, Using 5.5 lb (2.49 Kg) Rammer and 12 inch (304.8 mm) Drop.
2. ASTM D1557 or AASHTO T180 - Test Methods for
Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 10 lb (4.54 Kg) Rammer and 18 inch (457 mm) Drop.
3. ASTM D2216 - Laboratory Determination of Water (Moisture)
Content of Soil, Rock, and Soil Aggregate Mixtures.
4. ASTM D4253 - Maximum Index Density of Soils Using a Vibratory Table.
5. ASTM D4254 - Minimum Index Density of Soils and Calculation of
Relative Density.
6. ASTM D4643 - Determination of Water (Moisture) Content of Soil, Microwave Oven Method.
7. ASTM D4718 - Standard Practice for Correction of Unit Weight and
Water Content for Soils Containing Oversize Particles.
02210-3
2.01 SOIL MATERIALS
A. Type A Fill: General fill free of debris, deleterious or objectionable materials, and rocks larger than 6-inches. Type A Fill shall be a compactable, well-graded, granular material approved by Engineer. Type A fill may be used for temporary roads, berms, or dikes, or other temporary structures built for construction purposes and as granular backfill material to be used to backfill walls.
B. Type B Fill: Granular bedding material conforming to the following gradation criteria unless otherwise approved by the Engineer, to be used under the apron and other bedding as shown on the Drawings.
Particle Size % Finer Than 1-inch 100 3/4-inch 85-100 3/8-inch 30-60 #4 sieve 0-10
C. Type C Fill: Clean, naturally occurring backfill for excavated areas and for construction of berms or other structural fill features. Type C Fill shall a well-graded granular material conforming to the following gradation criteria and have a Plasticity Index less than 10, or otherwise approved by the Engineer:
Particle Size % Finer Than 6-inch 90-100 #200 sieve 0.5-20
D. Type D Cover Soil: Cover soil is defined as topsoil (A horizon material) and subsoil (B horizon material). Unless otherwise directed by the Engineer, cover soil shall be stripped from all proposed disturbed areas within the project limits to a depth of 1 foot measured from the top of ground surface following clearing and grubbing. Stripped cover soil shall be stockpiled on site in an area where it will not interfere with construction activities. The cover soil stockpile shall be of such uniformity and dimensions it can be conveniently measured by cross-section.
2.02 SOURCE QUALITY CONTROL
A. Tests and analyses of soil materials will be performed in accordance with applicable ASTM test methods, as listed under Part 1.04.
02210-4
B. If tests indicate materials do not meet specified requirements, change material and retest at no cost to NMDGF.
C. Compliance testing will be performed by Engineer at their discretion.
3.01 SOURCE OF MATERIALS
A. Contractor shall be responsible for locating suitable sources of Type A, B,C and E Fill.
B. Cover soil shall be salvaged on site as specified in Part 2.01 D
3.02 PREPARATION FOR PLACEMENT
A. Identify required lines, levels, contours, and datum.
B. Stake and flag locations of known utilities.
C. Locate, identify, and protect utilities that remain from damage, including all monitoring wells. Notify utility companies for utilities which may be affected by the work, or which cross the work area.
D. Protect bench marks and existing structures from excavating equipment and vehicular traffic.
E. Compact subgrade or existing underlying fill to a minimum depth of 12 inches to meet density requirements for subsequent fill materials as specified in Part 3.05.
F. Cut out soft areas of subgrade or existing underlying fill that cannot be compacted as specified in paragraph E, above. Backfill with material type specified for subsequent fill, and compact to minimum density requirements for subsequent fill material as specified in Part 3.05.
G. Dewater area as needed prior to fill placement. Fill may not be placed if groundwater is present.
3.03 PLACEMENT
A. General Backfilling of Excavated Areas and Other General Fill
1. Place fill in lifts not to exceed 3 feet in loose thickness. Thinner lifts must be used if required to achieve compaction criteria presented in
02210-5
Part 3.04 paragraph A, below.
2. Finish grade to within + 0.2 foot of line and + 0.1 % of grade shown on the Drawings.
3. Maintain positive surface drainage to minimize ponding of water on fill.
4. Material shall not be frozen when placed. Material shall not be placed on ice. Material shall not be placed on frozen material unless directed by Engineer. Frozen material shall be scarified, disked, or otherwise made suitable to receive subsequent fill and provide an acceptable bond between lifts, as approved by Engineer.
B. Backfilling of Structure
1. Place fill in lifts not to exceed 12 inches in loose thickness. Thinner lifts must be used if required to achieve compaction criteria presented in Part 3.04 paragraph B, below.
2. Finish grade to within + 0.3 feet of line
3. Material shall not be frozen when placed. Material shall not be placed on ice. Material shall not be placed on frozen material unless directed by Engineer. Frozen material shall be scarified, disked, or otherwise made suitable to receive subsequent fill and provide an acceptable bond between lifts, as approved by Engineer.
3.04 COMPACTION
A. General Backfilling of Excavated Areas and Other Non-Structural Fill Density: Materials shall be compacted sufficiently to support traffic by construction equipment, construction surveying, and inspection vehicles.
B. Type A and C material, berm and retaining wall backfill shall be compacted to a firm, unyielding surface as approved by Engineer.
C. Type B Apron Slab Subgrade: Place Type B material by dumping from a height no less than 1 foot and no greater than 5 feet. Spread material evenly with rake or shovel to ensure uniform distribution of material throughout area of backfill. Mechanically tamp a minimum of three passes with the tamper.
3.05 SITE GRADING
02210-6
Grade all areas including excavated, filled, and transition areas to obtain the finished surface shown on Drawings, to the tolerances specified in Part 3.04 above.
Finished surface shall be reasonably smooth, compacted, and free from irregular surface changes. Finished surfaces shall have positive drainage to minimize ponding of water.
3.06 FIELD QUALITY CONTROL
A. Observation of compaction control and gradation will be conducted by the Engineer.