4-Pricing Section BT-28EG-GHCANDO-Bore and Sanitary-Rebid.xlsx
XLSX spreadsheet 12 KB Posted
- Solicitation number
- US.258131
- Issued by
- Luzerne County, Pennsylvania
About this file
This pricing section document presents bid submissions for the Norfolk Southern Double Railroad Bore and Sanitary System Upgrade Project in Hazle Township, Luzerne County, Pennsylvania, administered by Greater Hazleton CAN DO Inc. The project encompasses labor, materials, tools, oversight, and permits for constructing a double railroad bore and sanitary system upgrade. Key work items include mobilization and closeout, soil erosion and pollution control, 24-inch PVC SDR-35 gravity sewer pipe installation (482 linear feet total), excavation and preparation of two bore pits (60' x 15' and 10' x 10'), three sanitary manhole installations, 290 linear feet of 48-inch steel pipe boring, and seeding and final restoration. Bids were due by 3:00 PM on October 30, 2026, with opening and evaluation following immediately thereafter. Four contractors submitted bids for consideration: Ankiewicz Enterprises Inc., Linde Corporation, Miller Soil Solutions LLC, and Wexcon Inc.
The total contract bids ranged from $1,848,645.00 (Wexcon Inc., the lowest) to $2,843,583.73 (Miller Soil Solutions LLC). The base bid component for each contractor was $1,843,645.00, $2,393,387.00, $2,838,583.73, and $2,433,854.00 respectively, with an additional $5,000.00 allowance for soil testing and compaction included uniformly across all bids. A bid bond in the amount of 10 percent of the total bid was required, along with performance and payment bonds to be provided prior to contract award. The most substantial line item across all bids was the 48-inch steel pipe boring at 290 linear feet, representing approximately 63 to 75 percent of each contractor's base bid cost. Funding source and any set-asides are not identified in this pricing document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3-20261016 ADDENDUM 001.pdf | ||
| 1-Contract Documents and Specifications-Rebid.pdf | ||
| 2-Plan Set-Rebid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1
| Greater Hazleton CAN DO Inc | ||||||||||
| Norfolk Southern Double Railroad Bore and Sanitary System Upgrade | Ankiewicz Enterprises Inc | Linde Corporation | Miller Soil Solutions, LLC. | Wexcon, Inc. | ||||||
| Total Contract | $2,438,854.00 | $2,398,387.00 | $2,843,583.73 | $1,848,645.00 |
| # | Items | Unit | Qty Req | Unit | |
| Price | Total | ||||
| Cost | Unit | ||||
| Price | Total | ||||
| Cost | Unit | ||||
| Price | Total | ||||
| Cost | Unit | ||||
| Price | Total |
Cost
| 1 | Base Bid | $2,433,854.00 | $2,393,387.00 | $2,838,583.73 | $1,843,645.00 | ||||||
| #1-1 | Mobilization and Closeout Complete | LS | 1 | $38,740.00 | $38,740.00 | $30,000.00 | $30,000.00 | $111,550.00 | $111,550.00 | $55,400.00 | $55,400.00 |
| #1-2 | Bid Bond | LS | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $42,500.00 | $42,500.00 | $650.00 | $650.00 |
| #1-3 | All required Soil Erosion and Pollution Control | LS | 1 | $12,500.00 | $12,500.00 | $45,000.00 | $45,000.00 | $142,486.00 | $142,486.00 | $25,585.00 | $25,585.00 |
| #1-4 | Tie in existing manhole 6 | LS | 1 | $6,877.00 | $6,877.00 | $12,500.00 | $12,500.00 | $14,000.00 | $14,000.00 | $16,570.00 | $16,570.00 |
| #1-5 | 24" PVC SDR-35 gravity sewer pipe and fitting w/ excavation, backfill, compaction. Does not include PVC piping through bore. | LF | 188 | $274.00 | $51,512.00 | $325.00 | $61,100.00 | $436.07 | $81,981.16 | $220.00 | $41,360.00 |
| #1-6 | 24" PVC SDR-35 Gravity Sewer Pipe and Fitting through boring, into manholes at both ends of borings | LF | 294 | $226.00 | $66,444.00 | $224.00 | $65,856.00 | $178.47 | $52,470.18 | $185.00 | $54,390.00 |
| #1-7 | Excavate and prepare 60' x 15' bore pit | LS | 1 | $141,000.00 | $141,000.00 | $72,000.00 | $72,000.00 | $82,830.02 | $82,830.02 | $14,065.00 | $14,065.00 |
| #1-8 | Excavate and prepare 10' x 10' bore pit | LS | 1 | $39,000.00 | $39,000.00 | $20,000.00 | $20,000.00 | $41,447.44 | $41,447.44 | $17,950.00 | $17,950.00 |
| #1-9 | Sanitary Manhole Installation Complete (Variable Depth) | EA | 3 | $18,900.00 | $56,700.00 | $18,000.00 | $54,000.00 | $19,691.01 | $59,073.03 | $11,365.00 | $34,095.00 |
| #1-10 | 48" Steel Pipe Boring | LF | 290 | $6,678.00 | $1,936,620.00 | $6,767.00 | $1,962,430.00 | $7,412.91 | $2,149,743.90 | $5,310.00 | $1,539,900.00 |
| #1-11 | Seeding & Final Restoration Complete including all access and staging areas | LS | 1 | $12,460.00 | $12,460.00 | $27,500.00 | $27,500.00 | $60,500.00 | $60,500.00 | $15,140.00 | $15,140.00 |
| #1-12 | Labor and Material Bond | LS | 1 | $48,000.00 | $48,000.00 | $31,000.00 | $31,000.00 | $1.00 | $1.00 | $14,270.00 | $14,270.00 |
| #1-13 | Completion Bond | LS | 1 | $24,000.00 | $24,000.00 | $12,000.00 | $12,000.00 | $1.00 | $1.00 | $14,270.00 | $14,270.00 |
| 2 | Allowance | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | ||||||
| #2-1 | Soil Testing and Compaction | LS | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |