4-PENNBID QUESTIONS-ANSWERS.PREBID MEETING MINUTES.pdf

PDF 366 KB Posted

Attached to
2025-24 Oyster Point Reservoir Sediment Removal Project
Solicitation number
US.248926
Issued by
Lancaster County, Pennsylvania

About this file

This file consists of pre-bid meeting minutes and a public question-and-answer document for the City of Lancaster, Pennsylvania's Oyster Point Reservoir Sediment Removal Project (GovTribe ID: 6af347c94b5b6c8f5f03da32). The project involves removal of sediment from the bottom of a 320-foot by 320-foot potable water reservoir using remotely operated vehicles, divers, or alternative methods approved by the Pennsylvania Department of Environmental Protection (PADEP). The reservoir operates at a depth of 15 to 18 feet with a total height of 24 feet. The City of Lancaster required bidders to conduct mandatory site visits between 8:00 AM and 4:00 PM Monday through Friday by scheduling with the Utility Engineer. A non-mandatory virtual pre-bid conference was held on August 27, 2026, via Microsoft Teams. Bid submissions were originally due September 11, 2026, at 11:00 AM but were revised to September 25, 2026, at 11:00 AM. Substantial completion is required by March 31, 2027, with final completion by June 1, 2027. The City indicated that contract award would occur as soon as possible following the bid submission deadline. Addendum No. 1 was issued providing access to design plans, inspection videos, and photographs via a shared DropBox.

The project is structured as a lump-sum contract with payment based on a schedule of values submitted during pre-construction and agreed upon by the contractor, owner, and engineer. No prevailing wage requirement applies as this is classified as maintenance work. The City of Lancaster is tax-exempt and will provide tax-exempt certification to the successful bidder. Bidders must submit five similar projects completed within the past three years on Schedule B along with three references and cost breakdowns. The bid bond requirement was removed by addendum. Critical permitting and regulatory uncertainties exist, as the City awaited PADEP response regarding temporary discharge permits for filtered water and sediment disposal classifications at the time of the pre-bid meeting. The contractor bears primary responsibility for obtaining necessary PADEP permits with City assistance limited to coordination. Dewatering sediment volume was estimated at approximately 2,600 to 2,800 cubic yards of wet material, with dewatered volume dependent on contractor methodology. The City provided no preferred disposal facility but indicated use of Denali Sludge Disposal for its water treatment plant sludge. The contract includes a force majeure clause (Section 3.6 of the Agreement) allowing time extensions without liquidated damages for delays beyond the contractor's control, with specific application anticipated for permitting delays.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Generated on Sep 03, 2026 4:12 PM EDT - Nancy Miller

Contents PennBid Public Q&A

City of Lancaster Pre-Bid Meeting Minutes

PennBid Public Q&A Various Questions

Coastal Engineering LLC, Aug 27, 2026 3:42 PM EDT, Not Public - Pending

1. Please provide the most recent reservoir inspection report, including all available inspection videos, photographs, and sediment surveys.

Bidders may contract Kyle Quinn - kyle@mbatanks.com to receive a DropBox link.

2. Please provide the reservoir dimensions and configuration, including column spacing, access-hatch locations and dimensions, operating water depth, and anticipated freeboard during cleaning operations.

The operating depth is maintained between 15 and 18 feet. The total height of the tank is 24 feet.

The dimensions of the tank are 320 feet by 320 feet. The columns are 19 feet apart. Please see the attached schematic plan in the contract documents.

3. Has a staging area been designated for equipment, filtration/dewatering operations, temporary sediment storage, and loading of material for disposal? If so, please identify the available area and any access or use restrictions.

No, there has been no staging area identified. Currently, the area to the north of the fence is being used as a pipe yard for another city project. This area is not to be used, The area inside of the fence could be used as staging areas. The soybeans are going to be harvested shortly, at that point the farmed land is available to be used. If this is needed, coordination between the farmer and the city would be required.

4. What flow rates and water velocities should the contractor anticipate within the reservoir during cleaning operations?

The Susquehanna Treatment plant averages 13 mgd. The flow rate is fairly steady.

5. Will the City provide the required lockout/tagout procedures and identify all applicable equipment and isolation points?

There are four access points on the tank. Please see attached plans.

mailto:kyle@mbatanks.com

6. Please clarify the contractor’s permitting responsibilities, including all required permits, applications, fees, sampling, testing, reporting, and closeout documentation.

The PADEP has not responded to the City’s questions. However, in previous conversations, the

City had planned a temporary discharge to the ephemeral steam at 200 to 600 GPM.

Dechlorination was required with a discharge limit of non-detect in the discharge pH between 6 to

9 Standard Units.

7. Is there a nearby disposal facility that the City has previously used or recommends for the sediment generated by this work?

The City has no information on where the sediment was disposed of for the last reservoir cleaning.

8. Please provide prior sediment characterization or analytical testing results.

Attached is the last analysis. There has been no changes in treatment processes or chemicals.

9. Will dichlorination of filtered water be required before discharge? If so, please provide the applicable discharge and water-quality criteria.

Yes. De-chlorination will be required. Discharge of chlorine is non-detect.

10. May filtered water be discharged onsite, or must all filtered water be transported offsite for disposal?

Yes, as long as it meets the limits set by the PADEP.

11. The bid documents contain conflicting completion dates. The Instructions to Bidders identify substantial completion by March 31, 2027, and final completion by June 1, 2027, while the draft

Agreement identifies substantial completion by November 30, 2026, and final completion by

December 31, 2026. Please confirm the governing contract dates.

The correct dates are March 31, 2027, and final completion by June 1, 2027, which will be corrected and included in an addendum.

Discharge after material separation

U.S. Submergent Technologies, LLC, Sep 02, 2026 12:41 PM EDT, Not Public - Pending

1. Can we discharge water on the ground or sanitary sewer after material separation?

Any water discharge needs to be permitted by the PADEP.

Local sewer discharge is regulated by the Lancaster Area Sewer Authority. The City made no arrangements for discharge to the sewer system.

Lab Reports

U.S. Submergent Technologies, LLC, Sep 02, 2026 12:42 PM EDT, Not Public - Pending

2. Is there a lab report for the material or do we need to obtain one?

Yes, a report from 2020 is in the attachments. There have been no treatment changes so this should be representative of what is there now.

Temporary Storage and Discharge

U.S. Submergent Technologies, LLC, Sep 02, 2026 12:43 PM EDT, Not Public - Pending

3. Based on lab analysis and residuals, are there allowances for material to be stored inside a silt pan for labeled temporary storage if we meet dechlorination and pollution prevention thresholds?

There will be no allowances for temporary storage, this should be included in the bid.

Weekend work

U.S. Submergent Technologies, LLC, Sep 02, 2026 12:43 PM EDT, Not Public - Pending

4. Can we work weekends and if so, what are the allowed weekend hours?

Yes, as long as work is in compliance with local ordinances. This site is in both West Hempfield and East Hempfield townships.

PADEP Determination

U.S. Submergent Technologies, LLC, Sep 02, 2026 12:53 PM EDT, Not Public - Pending

5. We understand City of Lancaster is awaiting response from PADEP regarding discharge of the potable water, which will address the above questions. What is the estimated response time once

PADEP answers and for addenda to be issued?

The City is still waiting for an answer about the discharge permit.

Documenting removal of bid bond requirement.

U.S. Submergent Technologies, LLC, Sep 02, 2026 12:54 PM EDT, Not Public - Pending

6. Will the bid bond requirement be removed by Addendum? Yes

Potential Staging area

JF Brennan, Sep 03, 2026 8:13 AM EDT, Not Public - Pending

Is the area north of the reservoir, which is currently being used for storage, available for contractor staging and dewatering activities during the project?

See previously answered question.

access point to the reservoir

JF Brennan, Sep 03, 2026 8:14 AM EDT, Not Public - Pending

Could you please provide the exact dimensions and configuration of the “Largest Entry Point” cover/hatch? Also, please clarify what the access opening looks like below the cover, including whether there is a ladder, confined-space retrieval anchor point, platform, or any other features that would be important for diver or ROV access and setup.

Please see the drop box request to see plans and pictures.

Overhanging trees

JF Brennan, Sep 03, 2026 8:16 AM EDT, Not Public - Pending

Due to the trees near the gate and driveway and the overhead height limitations they impose, will the city all the area on the map noted as “potential staging area” be used in conjunction with opening the fence as equipment access to the tank area? If the city allows this area to be used and the fence to be opened, they won’t have to cut back the trees. we are not sure if they are on private property or not.

If needed the city can accommodate trees needing to be cut back.

Metal Staircase

JF Brennan, Sep 03, 2026 8:17 AM EDT, Not Public – Pending

Is the metal staircase in adequate condition for frequent contractor personnel use throughout the project? Are there any load or access restrictions the City wants to impose on it?

The stairs were replaced about 5 years ago. They are meant for people access. The City would need to approve if they are to be used for equipment.

weight restictions

JF Brennan, Sep 03, 2026 8:18 AM EDT, Not Public - Pending

Are there any weight restrictions on the access roads or parking/staging areas for heavy equipment such as vacuum trucks, dewatering equipment, or cranes?

The only restrictions for parking and staging area would be at the steel pipes. The city can denote the location of these pipes.

Are there any weight or equipment restrictions on top of the reservoir, and if so, what are the allowable load limits?

Yes. The City does not allow anything heavier than a lawn mower.

Utilities

JF Brennan, Sep 03, 2026 8:19 AM EDT, Not Public - Pending

What utilities are available at or near the site (electrical power, potable water, sewer connection)?

Can the contractor access them, and at what cost?

There is electric power on-site. Contractor needs to determine if existing service is adequate.

There is no sewer connection on site. There is no public water connection on the site.

Sediment / Sludge Characterization

JF Brennan, Sep 03, 2026 8:19 AM EDT, Not Public - Pending

Has any sediment characterization or analytical testing been performed on material within the reservoir (e.g., metals, organics, pH, solids content)? If so, please provide all available test results.

Yes. Test results are available.

JF Brennan, Sep 03, 2026 8:20 AM EDT, Not Public - Pending

Has PADEP confirmed or pre-determined the classification of the sediment (residual waste vs.

hazardous waste)? What Chapter 299 classification does the City anticipate?

Based on previous test results, the sediment would not be defined as a hazardous waste.

Refer to 287.2 (C) on water treatment sludges:

(c) Management of the following types of waste is subject to this article instead of Article VIII, and shall be regulated as if the waste is residual waste, regardless of whether the waste is municipal waste or residual waste:

(1) Water supply treatment plant sludges.

(2) Waste oil that is not hazardous waste.

(3) Waste tires and autofluff.

(4) Contaminated soil.

(5) Used asphalt.

(6) Dredged material.

JF Brennan, Sep 03, 2026 8:20 AM EDT, Not Public - Pending

What is the estimated volume of dewatered sludge that will require off-site disposal? (The specs state average sediment depth of 9.5 inches across a 320'×320' tank — approximately 2,600–2,800

CY wet volume, but the dewatered/cake volume will depend on solids content.)

The city has not estimated this volume, it would depend on the contractor’s method of dewatering.

Discharge of Filtered / Separated Water

JF Brennan, Sep 03, 2026 8:21 AM EDT, Not Public - Pending

Where is the intended discharge point for the filtered/separated water generated during the dredging and dewatering process? (Street storm drain, sanitary sewer, stream, on-site infiltration?) Please identify the location on a map or describe it.

For the temporary discharge permit that was approved in 2020, water was to be placed in the ephemeral stream just to the south of the fence area.

JF Brennan, Sep 03, 2026 8:22 AM EDT, Not Public - Pending

What effluent quality standards must the discharged water meet (turbidity, TSS, pH, metals, etc.)?

Has the City or its engineer prepared a list of required parameters?

This would need to be discussed with the PADEP for their discharge permit.

Will the discharge go to a municipal sewer — and if so, has the sewer authority (Lancaster Area

Sewer Authority or similar) been contacted regarding industrial pretreatment requirements or surcharge rates?

This is up to the contractor. The city did investigate discharge into the LASA system. The contractor can check with LASA to determine their requirements and rates.

The spec states the Contractor is responsible for obtaining a temporary PADEP discharge permit

"with assistance from City and/or consultant." What specific assistance will the City provide? Will the City prepare or co-sign the permit application?

The City will provide the necessary assistance to obtain the permit. The City can help with coordination of permitting between the contractor and the PADEP, however this should be controlled by the contractor, unless the City gets different direction from the PADEP, depending on the method chosen by the Contractor to remove the solids.

PADEP Permitting & Regulatory Status

JF Brennan, Sep 03, 2026 8:23 AM EDT, Not Public - Pending

Has the City or its engineer (Mumford-Bjorkman Associates) held any pre-application meetings or informal consultations with PADEP (Bureau of Clean Water or Bureau of Waste Management) regarding this project? If so, what guidance was received?

The City has not met recently with either bureau on the project.

JF Brennan, Sep 03, 2026 8:23 AM EDT, Not Public - Pending

Does the City anticipate the discharge permit will be an individual NPDES permit or a coverage under a general permit (e.g., PAG-10 for water treatment residuals)? What is the expected permitting timeline?

This will depend on the contractor’s method of cleaning. The PADEP was willing to grant a temporary permit and a NPDES permit was not required. necessary. No NPDES permit is needed from the conservation district as there was no earth disturbance. The expected permitting timeline would be up to the regulators. If PADEP requires a NPDES permit for discharge, contract timelines will be adjusted accordingly.

JF Brennan, Sep 03, 2026 8:24 AM EDT, Not Public - Pending

Has PADEP provided any written guidance or determination regarding the applicable regulations for removing and disposing of sediment from a potable water reservoir?

The City did not investigate land applying the sediment. The disposal of sediment is part of the project and will be determined by the contractor. A form has been added to ask contractors where they are planning to take the sediment.

JF Brennan, Sep 03, 2026 8:24 AM EDT, Not Public - Pending

Are there any existing PADEP permits or authorizations associated with the Oyster Point Reservoir

(operating permit, source water protection plan, etc.) that the Contractor must coordinate with or comply with?

This is a working reservoir and a part of the City’s distribution system, and it needs to be treated as such. The City has an operating permit for the Susquehanna Water Treatment Plant.

JF Brennan, Sep 03, 2026 8:25 AM EDT, Not Public - Pending

If the permitting timeline extends beyond the project completion date, how will the City handle the schedule impact? Will a time extension be granted without liquidated damages?

There is a force majeure clause in the contract documents (3.6 in the agreement) that will allow the city to authorize a time extension without liquidated damages when the cause of the delay is beyond the contractor control.

Sludge Disposal

Does the City have a preferred or pre-approved disposal facility for the dewatered sludge? If so, has that facility reviewed preliminary sediment data and provided a conditional acceptance letter?

No.

Does the City have any leads on beneficial reuse options for the material (e.g., land application, composting, use as fill) that could reduce disposal costs?

The City’s water treatment plant sludge is removed by Denali

JF Brennan, Sep 03, 2026 8:26 AM EDT, Not Public - Pending

The spec references Pennsylvania Code Chapter 299 (Residual Waste Storage and

Transportation). Has the City obtained a waste determination or profile from a disposal facility confirming the material will be accepted under Chapter 299?

See answer above regarding waste.

Staging, Storage & Property

JF Brennan, Sep 03, 2026 8:27 AM EDT, Not Public - Pending

The spec identifies the Susquehanna Water Treatment Plant (900 South 15th Street, Columbia, PA) as the primary staging/storage location. What are the available hours of access? What security is in place? Is power available for equipment?

This has been changed in the contract documents to identify the Oyster Point Reservoir as the primary staging/storage location.

JF Brennan, Sep 03, 2026 8:27 AM EDT, Not Public - Pending

Is there any property adjacent to or near the Oyster Point Reservoir site that could be used for closer staging or dewatering operations, reducing trucking to Columbia? Is there any City-owned land or an agreement with neighboring property owners?

See answer above, staging and dewatering operations should occur at the Oyster Point Reservoir.

JF Brennan, Sep 03, 2026 8:28 AM EDT, Not Public - Pending

May the Contractor use the "Potential Staging Area" north of the reservoir for dewatering equipment such as a belt press, centrifuge, or dewatering boxes/geotextile tubes? Will the City provide any containment or pad?

The area to the north will not be able to be used as the City has another project that is expected to be complete in September 2027. The city would not provide a containment or pad. Any facilities would be on the contractor to provide.

JF Brennan, Sep 03, 2026 8:28 AM EDT, Not Public - Pending

Are there any restrictions on the type or size of dewatering equipment that can be placed on top of or adjacent to the buried reservoir (due to structural load limits)?

Yes, there are load restrictions on the top of the reservoir as noted earlier. There are no load limits at the bottom of the reservoir.

Potable Water Protection & Confined Space

JF Brennan, Sep 03, 2026 8:29 AM EDT, Not Public - Pending

What decontamination protocols are required for all equipment and personnel entering the reservoir (divers, ROV, tools, hardware)? Does the City have a written standard, or will it be based on AWWA or state guidance?

This would be controlled by the AWWA standards. For equipment it would be C652 section 4.4.

What turbidity or water quality limits will trigger a work stoppage? Will the City have a water quality monitor or engineer on site during in-tank operations?

Due to the nature of the bid, this will need to be discussed at the pre-construction meeting. This will be determined based on the contractor’s method of cleaning.

Who is responsible for issuing the confined space entry permit — the City or the Contractor? Will the City provide a confined space attendant, or is that the Contractor's responsibility?

The Contractor is responsible for the confined space entry permit.

It is the contractor’s responsibility to provide the confined space attendant and any necessary equipment for confined space entry.

JF Brennan, Sep 03, 2026 8:30 AM EDT, Not Public - Pending

Are there any restrictions on lighting, electrical equipment, or communication systems that may be used inside the tank?

As long as the equipment does not interfere with the operations of the reservoir and are allowed by the AWWA regulations, there are no additional restrictions by the City.

JF Brennan, Sep 03, 2026 8:30 AM EDT, Not Public - Pending

What is the emergency protocol if a water quality event occurs during work (e.g., turbidity spike, equipment failure inside the tank)? Who has authority to direct an emergency shutdown?

The city and the engineer (Mumford-Bjorkman Associates) have the authority to shutdown work.

Due to the nature of the bid, this will need to be discussed at the pre-construction meeting. This will be determined based on the contractor’s method of cleaning.

Schedule & Completion Date

JF Brennan, Sep 03, 2026 8:31 AM EDT, Not Public - Pending

The Scope of Work states substantial completion by March 31, 2027, while Agreement Article 2.1 states November 30, 2026. Which date is correct and governs the contract?

Substantial completion is March 31, 2027.

Given that permitting with PADEP may take 60–120+ days, and the contractor cannot begin work until permits are in place, is the completion date achievable? Will the City grant a time extension

Yes, the City can grant a time extension for events outside of the Contractor's control.

Is there flexibility in the 7:00 AM–5:00 PM Monday–Friday work hours? Weekend or extended-hour work may help recover schedule — what is the process for requesting alternate hours?

Weekend or extended hours will be discussed with the bidder awarded the contract. Both are possible within the noise ordinance hours of the township.

Project Administration

JF Brennan, Sep 03, 2026 8:32 AM EDT, Not Public - Pending

Who is the City's representative / project engineer of record? Is MBA (Mumford-Bjorkman

Associates) the resident engineer throughout construction, or only during the design phase?

MBA is the resident engineer.

JF Brennan, Sep 03, 2026 8:32 AM EDT, Not Public - Pending

Will the City provide any existing as-built drawings, structural reports, or design data for the reservoir (dimensions, interior baffles, inlet/outlet locations, column layout)? The bid documents do not include any structural drawings.

Drawings to be provided on the dropbox.

JF Brennan, Sep 03, 2026 8:33 AM EDT, Not Public - Pending

How will the volume of sediment removed be measured for payment verification — pre- and post-dredge bathymetric survey, weigh tickets, or another method?

This is a lump sum contract. Payment is made by a schedule of values submitted during pre-construction and is evaluated and agreed upon by the contractor, owner, and engineer. It is not based on sediment removal weight or volume.

Experience

Coastal Engineering LLC, Sep 03, 2026 12:35 PM EDT, Not Public - Pending

Please clarify the experience and project history requirements for the bid submission. The

Executive Summary instructions require five similar projects completed within the past three years on Schedule B, plus three references with a breakdown of costs. The Experience Questionnaire on page 30, however, states that Schedule B must include a minimum of ten projects.

Please confirm:

Whether Schedule B should include five or ten projects.

Whether the three references are separate from the projects listed on Schedule B.

Where and in what format the three references and associated cost breakdowns should be provided.

There are five projects required in the past 3 years. Schedule B is just a form that gives space for

10 projects.

The references can be from the required projects.

Power

U.S. Submergent Technologies, LLC, Sep 04, 2026 12:57 PM EDT, Not Public - Pending

Will the City confirm what, if any, power is available at the site?

Handling/Disposal of Debris

Ballard Marine Construction, Sep 03, 2026 2:17 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Once stop logs and debris are removed from the channel and brought to the operating floor, will the Commission take ownership and responsibility for handling/disposal, or is the Contractor responsible for loading, hauling and o"-site disposal? If Contractor disposal is required, please provide characterization information for the existing materials.

Commencement of Work

Ballard Marine Construction, Sep 03, 2026 2:17 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please confirm that the requirement to commence work within seven days of Notice to Proceed may be satisfied by engineering, field verification, submittal preparation, procurement, or fabrication activities and does not require physical installation work to begin onsite within seven days.

Mobilization/Demobilization

Ballard Marine Construction, Sep 03, 2026 2:18 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Will Tasks 1 and 2 be scheduled consecutively so that the Contractor may perform the work under a single mobilization? If the Commission requires the Contractor to demobilize between tasks and return at a later date, please confirm that the additional mobilization/demobilization will be compensated.

Gas Powered Motors

Ballard Marine Construction, Sep 03, 2026 2:18 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Are gas-powered motors allowed on the reservoir?

Boat Ramp

Ballard Marine Construction, Sep 03, 2026 2:37 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

Is there a known depth of the boat ramp closest to the project or more information on the recent extension of the boat ramp?

Temporary Wedge Anchors

Ballard Marine Construction, Sep 03, 2026 2:37 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Can the contractor use temporary wedge anchors to hold the aluminum plate in place while drilling and epoxying in anchors?

Weight Limits

Ballard Marine Construction, Sep 03, 2026 2:38 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Is there a weight limit for the roof over the upper gate house? If so, can you provide the weight limit?

Reservoir Elevation Range

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please provide the anticipated reservoir elevation range during the planned construction period and confirm whether the Commission can control or maintain reservoir elevation during Task 1 installation.

Intake System Operation

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please confirm that the Commission will operate the intake system during installation and for the duration the closure plate remains installed such that no sustained di"erential head will develop across the closure plate. If a di"erential head develops requiring removal and subsequent reinstallation of the plate, please confirm that this work will be considered additional work and compensated accordingly. If there is hydrostatic pressure will there be a design change to account for the pressure to safely perform the work?

Lower Intake

Ballard Marine Construction, Sep 03, 2026 2:39 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please confirm that the Lower Intake will be completely shut down and isolated during all diving operations associated with Task 1, with no flow or suction through the intake. Please identify any other nearby intakes, gates, valves, pumps, or hydraulic systems that may create di"erential pressure, suction, or flow in the vicinity of the divers.

Unsuitable Conditions

Ballard Marine Construction, Sep 03, 2026 2:39 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please clarify how unforeseen deterioration, spalling, cracking, exposed reinforcing steel, irregular surfaces, embedded items, or other unsuitable conditions encountered at the proposed attachment locations are to be handled. Please confirm that repair or modification of existing concrete beyond the work specifically shown will be considered additional work.

Ballard Marine Construction, Sep 03, 2026 2:40 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

Has the Commission or Engineer performed a recent underwater inspection of the

Lower Intake opening? If so, please provide the inspection report, photographs, video, sonar data, or other documentation. Please confirm whether removal of sediment, debris, biological growth, abandoned materials, or other obstructions necessary to install the closure plate is included in Task 1 or will be compensated as additional work.

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Will there be equalized water pressure on both sides of the lower intake location where the aluminum plate is being installed? If not, how will the plate prevent failure due to hydrostatic pressure?

Overhead Crane

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please confirm whether the existing overhead crane and qualified Commission operator will be provided by the Commission at no cost to the Contractor for Task 2.

Please provide the crane manufacturer/model, rated capacity, available hook travel, current inspection/certification status, and any restrictions on Contractor use.

a. Please define the labor and equipment that will be furnished by Commission

Maintenance Personnel during Task 2. Specifically identify responsibility for crane operations, rigging above the hatch, handling of removed stop logs, transportation, disposal, housekeeping, and coordination of intake operations.

b. Is the crane CCO certified and if so will the commissions operator be CCO certified?

Stop Logs

Ballard Marine Construction, Sep 03, 2026 2:41 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please provide the approximate original/design weight of each stop log, including the steel frame and wood members, and any available information regarding anticipated waterlogged weight or accumulated debris.

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

If existing stop logs cannot be removed intact using the existing lifting points and overhead crane due to deterioration or failure, please confirm the extent of dismantling, cutting, rigging, or underwater demolition included in the Contractor's scope. Is there any limitation on the means and methods permitted for breaking down failed stop logs?

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

Please provide any available inspection reports, photographs, underwater video, maintenance records, or previous removal records documenting the current condition of the stop logs and vertical channels.

Detail 1-3/3

Ballard Marine Construction, Sep 03, 2026 2:41 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

Please clarify the weld detail for the closure detail 1-3/3.

Bid Bond

Ballard Marine Construction, Sep 03, 2026 2:56 PM EDT, Not Public – Pending

PLEASE DISREGARD THE QUESTIONS SUBMITTED ON 9/3 AS THEY WERE NOT FOR THIS

SOLICITATION AND WERE SUBMITTED IN ERROR.

At the pre-bid meeting it was clarified that there was NO bid bond required with bid submission.

Can you please confirm in writing that it is not needed.

City of Lancaster Pre-Bid Meeting Minutes Attendance

Christine Volkay Hilditch, Ben Perwien and Nancy Miller - City of Lancaster Andy Mumford & Nicolette Grannum, MBA

Bryant Parker and Matthew Robertson - Ballard Marine Construction

William Ebert, Hydra Dive Tech.

Kevin Reinhard; Coastal Engineering

Michael Kisling, Wendy Gomez and Aaron Hood- US Submergent Technologies

Carissa Myers; Coastal Engineering

Lorrie Rossiter, GFL Environmental Services Greg Pizer, SYNAGRO

Troy Gessner and Chris Schauer, Integrated Underwater Services

Justin Scherf, J.F. Brennan Co

Kevin Jackson, Rain for Rent

Introductions

Introductions were made of City Staff and the City’s engineer for this project, MBA

Agenda Items

1. General Procurement

Questions will be answered through PENNBID and must be submitted prior to September 8, 2026.

Requirements of the Bid Form Packages found in the documents on PENNBID

Last Addendum will be sent out September 10. (Now revised to September 18 due to the volume of questions received.)

Bid dates: September 11, 2026 (REVISED September 25, 2026 at 11:00 AM

Site visit required – see page 9 of the bid documents.

2. Prevailing Wage

Prevailing wage is not required. This is a maintenance work.

3. Timeframe to award

The contract will be awarded as soon as possible

4. Project Schedule

Substantial completion: March 31, 2027

Final Completion: June 1, 2027

5. Tax Status

Lancaster is tax exempt. A tax-exempt certification will be provided for the successful bidder.

6. Staging

Area to work next to the reservoir.

7. Submittals

Submittals will be reviewed and approved by MBA. See scope.

Questions and Answer from the Pre-bod meeting

Q1 – Is the ROV video available?

A1 – Yes, please contact Kyle Quinn - kyle@mbatanks.com to receive a DropBox link.

Q2 – What is in the material?

A2 – Analysis is attached.

Q3 – There is a major difference between using silt bags and discharge to the ground. What will PADEP require?

A3 -

Q4 – Is the intent to dewater the sediment and does it need to be removed?

A4 - The intent is for the water to be discharged to an ephemeral stream and sediment to be removed. PADEP was contacted.

Q5 - Can you verify the size of the access hatches?

A5-

Q6 – Is there an engineer’s estimate?

mailto:kyle@mbatanks.com

A6 – No

Q7- In the intro statement – remove the sediment and the water. Please clarify

A7-

Q8- What permitting is required from the contracts?

A8 – see the answer above

Q9 – What is the freeboard dimension?

A9 – This will fluctuate. The level will not go above 18 feet as there is an issue with the outlet structure.

Q10 – Will the overflow be fixed?

A10 – not at this time.

Q11- What is the response form

Q11 – bid is lump sum

Q11 – Can the form be modified? Any subs?

Q11 – not at this time. Lancaster is looking to award one prime contract. Sub-contractors are allowed and must be listed accordingly.

File details come from the government source that posted it. Updated .