This Addendum No. 1, dated June 5, 2026, modifies the bidding documents for the Yardley Borough Sewer Authority's Joint Use Sanitary Sewer Improvements project with Lower Makefield Township, Pennsylvania. The project encompasses two contracts: Contract No. 26-01 for Longshore Bypass and Buck Creek Bypass Section #1, and Contract No. 26-02 for Buck Creek Bypass Section #2 and Brock Creek Replacement. Contract No. 26-01 includes approximately 600 linear feet of 10-inch gravity sewer, 1,700 linear feet of 15-inch gravity sewer, 25 linear feet of 16-inch gravity sewer, 850 linear feet of 18-inch gravity sewer, and approximately 650 linear feet of 20-inch gravity sewers with associated manholes and three trenchless installation locations. Contract No. 26-02 consists of approximately 50 linear feet of 8-inch gravity sewer and approximately 2,800 linear feet of 15-inch and 16-inch gravity sewers with associated manholes. Sealed bids are due online by 10:00 A.M. on Wednesday, July 1, 2026. Work includes pre-construction audio/video assessments, pipe installation, excavation, trenching, shoring, jack and bore operations, backfill and compaction, erosion control, traffic control, and all related sanitary sewer installation activities.
The addendum specifies that prospective bidders must acknowledge receipt of Addendum No. 1 by signature and submit it with their bid. A revised Bid Form (BT-12AT) for Contract No. 26-01 has been uploaded for use. For Contract No. 26-02, Item No. 1 Mobilization has been revised, with bidders required to enter a fixed amount of $100,000. The addendum clarifies that both excel pricing sections are identical across contracts. Bidders are directed to use the updated bid forms and acknowledge this addendum as a condition of bid submission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-2026-05 ESC Plan Set.pdf | ||
| 1-YBSA JUF SANITARY PLANS-ISSUED FOR BIDDING.pdf | ||
| 3-2026.06.04 YBSA JII IFB Project Manual.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
-1-
JOINT USE SANITARY SEWER IMPROVEMENTS WITH LOWER MAKEFIELD TOWNSHIP
YARDLEY BOROUGH SEWER AUTHORITY
CONTRACT NO. 26-01: LONGSHORE BYPASS AND BUCK CREEK BYPASS SECTION #1
CONTRACT NO. 26-02: BUCK CREEK BYPASS SECTION #2 AND BROCK CREEK REPLACEMENT
ADDENDUM NO. 1
Date: June 5, 2026 To: All Prospective Bidders From: Chris Tufaro-Savino – Gilmore & Associates, Inc.
Bidders are advised of the following information and modifications relative to the Bidding Documents as prepared by Gilmore & Associates, Inc. for Yardley Borough Sewer Authority’s Contract No. 26-01: Longshore Bypass And Buck Creek Bypass Section #1 and Contract No.
26-02: Buck Creek Bypass Section #2 And Brock Creek Replacement. Bidder shall acknowledge receipt of this Addendum by placing his signature on the designated line at the bottom of this page and submitting this document along with their bid.
Contract No. 26-01 Bid Form (BT-12AT):
1. Revised Bid Form has been uploaded and shall be used for bidding.
Contract No. 26-02 Bid Form (BT-28GH):
1. Item No. 1 Mobilization has been revised to Mobilization (Bidder shall enter $100,000).
Questions/Responses:
1. Both excel pricing sections are the same.
Contract 26-01 Bid Form (BT-12AT) has been revised per Addendum #1.
Bidder’s Acknowledgement of Receipt – Addendum No. 1 Dated 06.05.2026
END OF ADDENDUM