This document is a Post-Award Schedule attachment for a federal lease opportunity solicitation, Solicitation Number 3IL0588. The attachment details the post-award schedule for the project, which commences within 5 working days of lease award and outlines key activities and timeframes such as Lessor-Provided Design Intent Drawings (45 days), Government Review and Approval (35 days), Lessor Preparation and Submission of Construction Documents (30 days), Government Review (25 days), Lessor Pricing Proposal (25 days), Government Pricing Approval (50 days), Notice to Proceed (20 days), Lessor Construction (105 days), and Government Inspection and Acceptance (10 days), for a total of 345 working days from lease award to government acceptance. The related federal contract opportunity is a solicitation for Lease of Office Space within Region 5 using Request for Lease Proposals (RLP) #24-REG05 - Office Space – Des Plaines, Illinois, seeking 2,907 to 3,000 ABOA square feet of office space with a 10-year lease term, 8-year firm term, and specific requirements such as 24/7 access, 9 surface parking spaces, and 4 dual charging stations for electric vehicles.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 45

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents 30

Government Review of Construction Drawings 25

Lessor Preparation and Submission of the TI and BSAC Price Proposal

Government Reviews and Approves Pricing 50

Government Issues Notice to Proceed with Construction 20

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

Government Inspects and Accepts Finished Space 10

AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)

Total Work Days from Lease Award to Government Acceptance 345