Questions and Answers S21AS00165 updated to 11-20.pdf
PDF 164 KB Posted
- Opportunity number
- S21AS00165
About this file
Questions and Answers S21AS00165
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
S21AS00165
Question 1: In order to maximize R&D funding, BSEE and DOE indicate in the RFP an expectation that less than 10% of the funds will be utilized to manage the OESI 2.0 program. The
R&D program administration includes competitive and/or non-competitive solicitations, proposal evaluations, selections and award negotiation, for specific research projects pursuant to approved roadmaps. Please advise the details of what can be included in the 10% administration costs
Answer 1: The tasks associated with program administration at no more than 10% are as follows:
(A) Administer the research program in accordance with the approved annual plan;
(B) Issue research project solicitations;
(C) Make project awards to research performers;
(D) Disburse research funds to research performers;
(E) Oversee projects pursuant to individual project management plans.
Question 2: Please advise if there is a restriction on the eligibility of states from which we can look for potential partners.
Answer 2: There is no partner eligibility restriction.
Question 3: We’re wondering if there might be a way to facilitate our partnering by making our capabilities broadly known to potential applicants. Are you able to provide something like this via Q&A? Or do you have other recommendations on this front?
Answer 3: While partnerships with other organizations is encouraged, it would be up to your organization to seek out those partnerships.
Question 4: Can you please provide clarification on the 10% limit of Administrative
Costs? Does this limit applicant’s indirect cost charges?
Answer 4: See response to Question 1. This does not limit the applicant’s indirect rates.
Question 5: In looking over the Ocean Energy Safety Institute NOFO, our office was confused by some terminology. Section D2 mentions a Project Summary and then Project Narrative
(twice). Further down, the announcement goes on to state the requirements for the "Proposal
Text," but I didn't see a mention of Project Summary again. Under "Proposal Text," I noticed the first item is "Abstract." Is that the "Project Summary" or is a separate summary required? I noticed that the "Project Narrative" listed under the Application Checklist (in D8) seems to align with everything mentioned under "Proposal Text" prior to the budget information (i.e., items 1-7 of the Proposal Text in D2).
Answer 5: Please disregard the Project Summary heading in this section. The Project
Narrative was incorrectly listed twice. The Project Narrative section of your proposal should include a Cover Sheet and Proposal Text with items noted in Section D2.
Question 6: Are Federally Funded Research and Development Centers (FFRDC’s) eligible to respond and receive funding under the subject Funding Opportunity as a subrecipient to a
University?
Answer 6: Yes
Question 7: Effort distribution on energy technologies: Can DOE and BSEE specify an appropriate percent distribution of effort for R&D across the technical areas of Oil & Gas, Marine Wind Energy, and Marine Hydrokinetic energy development?
Answer 7: 50% Oil & Gas, 25% Offshore Wind, 25% MHK
Question 8: Joint Steering Committee:
a) The RFP mentions the establishment of a Joint Steering Committee. To clarify, will this committee be established by DOE and BSEE, or will it be established by the
Institute funded by this opportunity?
Answer 8 a): The Joint Steering Committee (JSC) will be established by DOE and BSEE.
b) If established BSEE and DOE, will both agencies be equally represented, or will the
JSC answer more to one agency?
Answer 8 b): There will be equal representation by BSEE and DOE.
c) If established by federal agencies, will industry members be included?
Answer 8 c): No. For FACA reasons, the JSC should be a federal-only body.
Added 11/20:
Question 9: Are “administrative costs” the allocable direct costs which are associated with managing tasks A-E below; OR, Are “administrative costs” the allocable direct costs plus associated allocable indirect costs (at applicant’s approved federally negotiated rate) associated with managing tasks A-E below?
(A) Administer the research program in accordance with the approved annual plan;
(B) Issue research project solicitations;
(C) Make project awards to research performers;
(D) Disburse research funds to research performers;
(E) Oversee projects pursuant to individual project management plans.
Answer 9: "Administrative Costs" would be allocable direct costs and associated allocable indirect costs (at applicant’s approved federally negotiated rate) associated with managing tasks of the Institute, in order to maximize research funding.
Question 10: Is the limit of “administrative costs” up to 10 percent of the entire Institute budget or up to 10 percent of the total R&D Program budget?
Answer 10: Up to 10% of the entire Institute budget related to management activities for
OESI.
File details come from the government source that posted it.