38101 (SPC-TB 38) UPDD FQ3 ACG 20R0.pdf
PDF 845 KB Posted
- Attached to
- DRYDOCK REPAIRS ON HULL 38101 CG ANT KODIAK
- Solicitation number
- 70Z040-20-QP45759
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JOTFOC 38101 mishap.pdf | ||
| FAR CLAUSES SERVICES P45759.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG 38101 (SPC-TB 38)
SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS
FY2020
Developed By: Anthony C Gonzales
(Rev-0, 19 February 2020)
USCG 38101 (SPC-TB -38) UNPLANNED AVAILABILITY FY2020
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .................................................................................. v Consolidated List of Critical Inspection Items ............................................................................................. vi Principal Characteristics ............................................................................................................................. vii General Requirements WORK ITEM 1: General Welding, Provide WORK ITEM 2: Diesel Fuel Tank Clean And Inspect WORK ITEM 3: U/W Body Preserve (100%) WORK ITEM 4: Exterior And Interior Non-Skid Pads, Renew WORK ITEM 5: Marine Chemist Services, Provide WORK ITEM 6: Drydock
USCG 38101 (SPC-TB-38) UNPLANNED AVAILABILITY FY2020
iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 38 SPC-TB 100-001, Hull-Deck Assembly
Coast Guard Drawing 38 SPC-TB 260-001, Rev -, Fuel Service System
Coast Guard Drawing 38 SPC-TB 630-001, Rev -, Non-Skid Layout
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction(COMDTINS) M10360.3 (series), Coatings and Color Manual
Coast Guard Technical Publication (TP) 4934, SWBS 074, Mar 2015, Small Boat Diagrams for Hotwork
Coast Guard Technical Publication (TP) 4993, 3M Nonskid Pads, Peel and Stick Catalog
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2018, Drydocking
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), Apr
2015, Solvent Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-WJ-2/NACE WJ-2, Mar 2012 Water Jet Cleaning of Metals-Very Thorough
Cleaning v (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
This section is not applicable to this package.
vi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
3 U/W Body Preserve (100%) vii (Rev-0)
PRINCIPAL CHARACTERISTICS
38 SPC-TB
PHYSICAL
Length overall (loa) 44 feet 4 inches
Beam, overall 13 feet 10 inches
Draft 2 feet 8 inches
Max fixed height above waterline
(radar dome)
15 feet 6 inches
Max weight, fully loaded 16,590 pounds
HULL
Hull 5086 Aluminum
MACHINERY
Engine details (2) Mercury Verado 300
Propulsion (2) Outboard Engines
Maximum speed at sea state 0 30 Knots
Range at cruise, sea state 0 2260 Miles @ 30 Knots
TANKS
Fuel capacity 100% (Gasoline &
Diesel)
380 gal.(Gasoline), 28 gal. (Diesel)
Ref: Boat Information Book
1 (Rev-0)
00000_1219_FLT
REC_00000_FLT_Boats @ Commercial Facility (0914)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction(COMDTINS) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy.
3.6.1 Coast Guard turn-over preparation. The Contractor shall be aware that, upon arrival, after haul out, and prior to departing the Contractor’s facility, the Coast Guard crew shall be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:
3.6.1.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.
3.6.1.2 The Contractor may commence/continue work during these time frames.
3.6.1.3 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.
3.6.1.4 The Unit will contact the servicing ESD or ESU to setup removal/installation of the transducer if Unit personnel are unable to accomplish this task.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2018 Edition Standard Specifications and supersede published content:
None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
4 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
5 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
6 (Rev-0)
QA-3A - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
7 (Rev-0)
QA-3B - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading
(mils)
Mean Reading (mils) IAW ASTM DD4417).
8 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
9 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic
Pull-Off (Type I/Banana) Gauge Is
Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
10 (Rev-0)
07400_AKP_0418_BOAT_FLT
WORK ITEM 1: General Welding, Provide
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to provide general welding listed in Table 1. For internal framings, crop and renew the contractor shall provide weld repair plan to the
COR/PE to be reviewed by USCG Naval Architect. All mooring, towing and anchoring fittings shall be tested IAW the Naval Engineering Manual, COMDTINST M9000.6, Chapter 570. Submit CFR/CR for any work not listed in Table 1.
TABLE 1- GENERAL WELDING
ITEM DESCRIPTION LOCATION
Crop and renew upper and lower bow hull plating on port and starboard sides extending approximately 9’ (81 Sq. Ft.) aft of bow centerline to include chine plate.
Bow Area
Crop and renew damaged deck plate approximately 8’ (64 Sq.
Ft.) from bow aft. Replace damaged bow cleats and tow eye.
Bow Area
Fabricate and install new bow handrails to match original design.
Bow Area
Crop and renew internal framing as necessary (The contractor shall provide repair plan to be reviewed by USCG Naval Architect).
Bow Area
Renew/repair foam bumper channels approximately 15 feet total. Install USCG provided foam bumper on entire vessel.
Chalk test and if necessary, replace Freeman flush deck
11 (Rev-0) hatch.
Fabricate new bow eye Bow
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 38 SPC-TB 100-001, Hull-Deck Assembly
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 4934, SWBS 074, Mar 2015, Small Boat Diagrams for
Hotwork
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
12 (Rev-0)
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Requirement. The Contractor shall provide general welding, including but not limited to, fabrication, brazing, inspection, plate renewal, crack repair, overlay, and associated processes on Coast Guard vessels and equipment in accordance with TP 4934 and SFLC Std Spec 0740.
3.3 Bidding. The Contractor shall ensure for bidding purposes this specification will be broke down by the following:
One linear foot of welding/brazing.
Four square inches of clad/overlay welding.
One hour of fabrication.
One square foot of plate renewal.
TABLE 1 – PLATE TYPE
STEEL PLATE ALUMINUM PLATE
THICKNESS WEIGHT
PER SQFT.
TYPE/GRADE THICKNESS WEIGHT
PER SQFT
TYPE/ALLOY
3/16 (.1875) 7.66 lb
1/4 (.250) 10.21 lb 1/4 (.250) 3.53 lb
5/16 (.3125) 12.76 lb 5/16 (.3125) 4.41 lb
3/8 (.375) 15.31 lb 3/8 (.375) 5.29 lb
1/2 (.500) 20.42 lb 1/2 (.500) 7.06 lb
3.4 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std
Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)
4. NOTES
This section is not applicable to this work item.
13 (Rev-0)
WORK ITEM 2: Fuel Tanks Clean And Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the vessel's diesel fuel tank listed in Table-1.
TABLE 1- FUEL TANK
TYPE OF TANK LOCATION CAPACITY – 95% (GALLONS)
Gasoline Fuel Centerline, between frames 9 & 12 in the Tank Compartment.
Diesel Fuel Between frames 9 & 12 28
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 38 SPC-TB 260-001, Rev -, Fuel Service System
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
3.1.2 Tech Rep.
14 (Rev-0)
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Insulation
Piping
Electrical Wiring
3.1.4.1 The Contractor shall remove up to a total of 380 gallons of gasoline fuel and 28 gallons of diesel fuel. Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery in accordance with paragraph 3.1.3.1 (Protective measures-environmental).
3.1.4.2 Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations.
NOTE
Coast Guard personnel will operate all vessel machinery and equipment.
3.1.5 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast Guard
Personnel perform an initial operational test of Tank Level Indicator, to demonstrate existing operational condition. Submit a CFR.
NOTE
Vessel may come in with less tank fluid contents than specified above.
3.2 Cleaning requirements. The Contractor shall clean and inspect the gasoline and Diesel fuel tanks using Coast Guard Drawing 38 SPC-TB 260-001, SFLC Std Spec 0000 and SFLC Std Spec 0740 as guidance.
3.2.1 Clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth. Remove cleaning media and residues continuously during the washing process. Remove any residual wash media.
3.3 Tank content and waste disposal. The Contractor shall dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Contractor shall follow the Environmental Protective Measures referenced in paragraph
3.1.3.1.
3.4 Inspection. The Contractor shall visually inspect the internal and external areas of the fuel tank.
Submit a CFR. Internal inspection shall be completed using a borescope through the top mounted inspection plug. Inspection shall include but not be limited to the following:
15 (Rev-0)
All interior surfaces, bulkheads, base and overhead plating, structural members and baffles.
Tank structural condition.
Tank welds.
Tank level indicator (TLI) and/or float switch condition, as applicable.
Sounding/vent tube and striker plate condition, as applicable.
Suction and discharge piping condition.
Fastener material and condition (correct fastener material is stainless steel).
Fuel Tank Rollover Brackets.
Tank isolators.
NOTE
Coast Guard personnel will operate all vessel machinery and equipment.
3.5 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the Tank Level Indicator, to be in satisfactory operating condition. Submit a CFR.
16 (Rev-0)
63130_AKP_0818_42SPCNLB
WORK ITEM 3: U/W Body Preserve (100%)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve the U/W body surfaces and fender channel.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP
1), Apr 2015, Solvent Cleaning
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
3.2.3 Clean and inspect.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against
17 (Rev-0) contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.1 Apply protective measures as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection) to the following components, spaces and equipment:
Fathometer transducer surface.
Sea water intakes.
Zinc anodes (unless anodes are being renewed).
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Generator sea water pickups.
3.2 Preservation requirements. The Contractor shall prepare and preserve the U/W body in accordance with SFLC Std Spec 6310.
3.2.1 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.
3.2.2 Surface preparation. The Contractor shall prepare the surface in accordance with the surface preparation method stated in Table I- Paint Schedule 38 SPC-TB and SFLC Std Spec 6310.
3.2.3 Clean and inspect. Upon completion of surface preparation and prior to coating application the
Contractor shall clean and inspect the prepared U/W body aluminum substrate. Submit A CIR.
3.2.3.1 The Contractor shall perform a visual inspection of the prepared U/W body aluminum substrate.
3.2.3.2 The Contractor shall solvent clean the prepared surfaces in accordance with SSPC-SP 1. Capture, contain, and dispose of all wastes from solvent cleaning, in accordance with all Federal, state and local regulations.
TABLE 1- PAINT SCHEDULE 38 SPC-TB (REF SFLC STD SPEC 6310 APPENDIX 9- U/W
BODY & BOOT TOP, ALUMINUM HULL, HIGH SPEED (>30 KNOTS)
EXTERIOR
SURFACES TO
BE
PRESERVED
SURFACE PREPARATION COATING SYSTEM DFT
(MILS)
COLOR
Underwater
Body
NEAR WHITE BLAST PER
SSPC-SP10 WITH CLEAN, FINE
ALUMINUM OXIDE, GARNET
OR EQUIVALENT INERT
MATERIAL CONFORMING TO
CID A-A-59316, TYPE I & IV
WITH A 1.5-2.5 MIL ANCHOR
PROFILE
1) SEAGUARD 5000 HS
2) SEAGUARD 5000 HS
3) SEAVOYAGE COPPER
FREE AF – (MUST BE
APPLIED WHILE EPOXY IS
STILL TACKY)
4) SEAVOYAGE COPPER
5.0-6.0
Red
Grey
Black
18 (Rev-0)
FREE AF
5) SEAVOYAGE COPPER
FREE AF
Black
Fender channel
Brush blast to bare metal with clean, fine aluminum oxide, garnet or equivalent inert material conforming to A-A-
59316, Type I & IV with a
1.5-2.5 mil anchor profile
1) SEAGUARD 5000 HS
2) SEAGUARD 5000 HS
Grey
3.2.4 Preservation. The Contractor shall preserve the U/W hull using the coating system in Table 1- Paint
Schedule 38 SPC-TB and in accordance with SFLC Std Spec 6310.
NOTE
Surfaces being preserved are considered “critical-coated surfaces”.
3.3 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
4. NOTES
4.1 Definitions.
4.1.1 U/W Body. The underwater body is defined as the aluminum hull surfaces from the bottom of the keel to the waterline, as shown on Coast Guard Drawing 38 SPC-TB 260-001.
19 (Rev-0)
63400_AKP_0818_42SPCNLB
WORK ITEM 4: Exterior And Interior Non-Skid Pads, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the exterior and interior nonskid (slip resistant) pads listed in table 1. Submit CFR/CR for any additional work.
TABLE 1- EXTERIOR AND INTERIOR
ITEM DESCRIPTION LOCATION
Renew deck anti-skid pads Bow Deck Area
1.2 Government-furnished property.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 38 SPC-TB 630-001, Rev -, Non-Skid Layout
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 4993, 3M Nonskid Pads, Peel and Stick Catalog
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface
Preparation Standard SSPC-WJ-2/NACE WJ-2, Mar 2012 Water Jet Cleaning of Metals-
Very Thorough Cleaning
3. REQUIREMENTS
3.1 General.
20 (Rev-0)
3.1.1 CIR.
3.1.2 Tech Rep.
Not Applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Deck fittings (cleats, tow reels)
Handrails
Ladders
Seats and Pedestals
3.2 Renewal. The Contractor shall renew the exterior and interior nonskid pads in accordance with Coast
Guard Drawing 38 SPC-TB 630-001, TP 4993 and SFLC Std Spec 0000.
3.2.1 Removals. The Contractor shall remove the slip resistant sheets using one or a combination of the following procedures:
In accordance with TP 4993.
Hand tools
3.2.2 Disposal. The Contractor shall dispose of the slip resistant sheets, in accordance with all applicable
Federal, state, and local regulations.
3.2.3 Surface Preparation. The Contractor shall prepare the surfaces after removing the existing non-skid pads in accordance with SFLC Std Spec 6310 and the following procedures:
Remove any salt water corrosion
Ensure all surfaces are clean, dry, and smooth, at least 10°F above dew point and the surface temperature must be above 40°F.
Use appropriate cleaner or solvent to remove any waxes, oils, silicones, or other residue, which can impede adhesive bonding and long-term product durability.
Clean with water and allow surfaces to dry thoroughly.
Use primer as designated in TP 4993.
3.2.4 Substrate inspection. After completion of surface preparation and before non-skid pad application, the Contractor shall perform a visual inspection of the prepared substrate for damage to include but not limited to deformation and cracks. Submit a CFR.
21 (Rev-0)
3.3 Installations. The Contractor shall install slip resistant sheets using Contractor furnished primer and edge sealer compound, in accordance with TP 4993.
3.3.1 The Contractor shall install Non-Skid (slip resistant sheets) as shown in Coast Guard Drawing 38
SPC-TB 630-001.
3.3.2 The Contractor shall select material brands as specified in SFLC Std Spec 6310, Appendix C and
Coast Guard Drawing 38 SPC-TB 630-001.
3.3.3 The Contractor shall ensure the following:
Slip resistant sheet material is applied to within approximately ½ inch of deck fittings, protrusions, coamings and deck edges. Deck fittings include, but are not limited to, the following: pad eyes, vent pipes, stanchion sockets, foundations.
Separation of adjacent pieces does not exceed 1 inch on all work and traffic areas.
Sheets are not applied over raised weld seams, deck fittings and protruding components
(including, but not limited to: pad eyes, vent pipes, stanchion sockets, foundations).
22 (Rev-0)
86310_0518_BOAT_FLT
WORK ITEM 5: Marine Chemist Services, Provide
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to provide marine chemist services
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
23 (Rev-0)
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Provide Marine Chemist. The Contractor shall provide a certified marine chemist services in accordance with SFLC Standard Specification 0000 General Requirements paragraph 3.3.1.2.
3.2.1 The Contractor shall maintain safe conditions, in accordance with 29 CFR 1915.15; for the duration of the Contract.
24 (Rev-0)
86340_1119_FLT
REC 86340_FLT_42 SPC-NLB (ALL) (0818)
WORK ITEM 6: Drydock
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to drydock the vessel, undock the vessel, and perform various drydocking-related tasks.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2018, Drydocking
OTHER REFERENCES
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
None.
3.1.2 Tech Rep.
Not applicable.
25 (Rev-0)
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Anchor assembly
Load conditions
U/W body appendages
3.2 Key personnel. The Contractor shall determine key personnel and require their presence during all drydocking phases as required by SFLC Standard Spec 8634. Submit list of key personnel to the COR.
3.3 Docking and undocking. The Contractor shall perform drydock and undock in accordance with SFLC
Std Spec 8634.
3.4 Cutter conditions. The Contractor shall use the Full Load Condition values listed below all in inches, for purposes of performing Pre-Award calculations as described in Appendix A (Requirements for
Calculations) of SFLC Std Spec 8634.
Displacement (lbs): 30,000
3.4.1 Blocking. The Contractor shall facilitate docking the vessel in designated block position by arranging keel and side blocks and ensuring minimum block heights as shown on the vessel's docking plan.
TABLE 1 – BLOCKING
POS. #
BLOCK HEIGHT ABOVE DOCKING
FACILITY DECK
STEEL
PLATE
SITUATION
AWARENESS
FIN
STABILIZERS ADDITIONAL MIN.
RUDDER
REMOVAL
PROPELLER
REMOVAL
SHAFT
REMOVAL
1 15” NA NA NA NA NA None
3.4.2 Cable, sling, or strap tension calculation. If the Contractor plans to use a vertical lift, crane, or travel/mobile lift to haul out the vessel, the Contractor shall submit the cable, sling, or strap tension calculation specified in Table A1 and paragraph A2.7.2.7 of SFLC Std Spec 8634 with the Pre-Award calculations, using the loading condition specified in paragraph 3.4.
3.5 Pre-award calculations. The Contractor shall provide to the KO a set of pre-award calculations, as described in SFLC Std Spec 8634 Appendix A.
26 (Rev-0)
3.5.1 Provide vertical side/bilge block offsets for any side blocks placed in a location where vertical offsets are not already defined by the docking plan.
3.5.2 Submit an alternate blocking arrangement, as part of the pre-award calculation submission, to compensate for any changes from the docking plan.
3.5.2.1 If the alternate blocking arrangement interferes with U/W hull plate inspection or 100% preservation of U/W body surfaces required under separate work items in this specification package, the
Contractor shall include a plan of how inspection/preservation will be accomplished. Plan shall include any modifications necessary to the prescribed docking plan including removing, shifting, repositioning blocks, or fleeting the vessel at no additional cost to the Government.
NOTE
1. The USCG has established several approved alternate docking plans for each vessel-class, to facilitate complete access to the entire U/W body structure, for periodic comprehensive inspection and/or 100% preservation.
This inspection and preservation pattern and periodicity is a configuration management concern that is a vital requirement of the contract. Intention to deviate from these plans (fewer blocks, block spacing, additional blocks, etc) is to be identified on pre-award calculations (Paragraph 3.5.2); an alternate docking plan and mitigation strategy will be provided to maintain preservation and inspection configuration.
2. Pre-award calculations may be deemed unsatisfactory - and may adversely affect contract award if they are submitted with the following detrimental factors:
a. No methods have been proposed that meet the requirements for the specified docking plan.
b. Proposed block shifting or fleeting risk-mitigating plan may result in delays in period of performance.
c. Proposed alternate docking plan violates USCG configuration management policies.
3.6 Unplanned availability: Underwater body cleaning-removal of marine growth. The Contractor shall accomplish the work in this paragraph in lieu of the work described in SFLC Std Spec 8634 paragraphs
3.5.4.1 and 3.5.4.2. Within four hours after the vessel has been docked, the Contractor shall start cleaning the entire underwater hull from the upper edge of the boot top down, including sea chest gratings, sea chest interiors, fairwaters, rope guards, rudder, shaft strut, z-drive, thruster tunnel, and zinc anodes, as applicable. The Contractor shall remove all marine growth, fouling, salt, and dirt from the underwater hull by High Pressure Fresh Water Wash, using a minimum pressure at the nozzle of 3,500 psi and maximum pressure of 7,000 psi. Complete the hull cleaning before marine growth hardens. Removal of gratings is not required.
WARNING
Do not use chemical additives in the freshwater wash. Take extreme care to avoid damaging or removing existing intact underwater body coating.
27 (Rev-0)
3.7 Fuel offloading. The Contractor shall be aware that fuel offloading is not mandatory to drydock the vessel.
3.8 Fleeting. At the Arrival Conference, the Contractor shall submit a second set of Drydocking calculations in accordance with SFLC Std Spec 8634, Appendix A for the alternate blocking position from that indicated in paragraph 3.4.1 Blocking position. Ensure the plans include any risk mitigating efforts necessary associated with other U/W body work items to ensure availability completion is not delayed.
4.1 Arrival conditions. The COR will advise the Contractor of the actual tank and draft readings when the vessel arrives, and will discuss with the Contractor any liquid loading changes necessary.
File details come from the government source that posted it. Updated .