FY 2017 September 2017
NAC CONSOLIDATION SCHEDULE
| September 2017 NAC Consolidation Milestone |
| Date |
| Requirements/Requests due to the NAC |
| 9/29/2017 |
| Pre-Solicitation Notice |
| 11/22/2017 |
| Post Requirements (RFQ) to FBO |
| 12/19/2017 |
| Deadline for Vendors to submit questions to NAC |
| 1/2/2018 |
| Deadline for NAC to respond to Vendor Questions |
| 1/16/2018 |
| Deadline for Vendor to submit quotes to NAC |
| 1/30/2018 |
| Deadline for Customers to receive vendor quotes via the shared drive |
| 2/8/2018 |
| Deadline for Customers to submit Best Value Selections |
| 3/15/2018 |
| Deadline for NAC to complete review of Selection Justifications |
| 4/12/2018 |
| Goal to award all Delivery Orders |
| 5/24/2018 |