36E77620B0001-0005001.pdf

PDF Posted

Attached to
Upgrade Switchgear and Distribution - Baltimore Federal contract opportunity
Solicitation number
36E77620B0001
Issued by
Department of Veterans Affairs Headquarters

About this file

This document provides information about an upcoming federal contract opportunity with the Department of Veterans Affairs to upgrade switchgear and distribution at the Baltimore VA Medical Center. The solicitation will be issued as an Invitation for Bid and awarded as a firm-fixed-price contract to a Service-Disabled Veteran-Owned Small Business. The project scope involves construction of a new electrical room, installation of a new enclosed paralleling switchgear on the roof, and associated electrical, structural, HVAC, fire protection and plumbing work. The pre-solicitation notice estimates the construction value between $5-10 million. The period of performance is approximately 540 calendar days from notice to proceed. Questions must be submitted in writing by a specified date. The solicitation is expected to be issued on or around January 8, 2020.

36E77620B0001 0005 Technical Questions - FINAL #2 - Baltimore Switchgear 3-11-2020.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Switchgear and Distribution - Baltimore, newest first.
File Type Posted
36E77620B0001-0007000.docx DOCX document
36E77620B0001-0006000.docx DOCX document
36E77620B0001-0005000.docx DOCX document
36E77620B0001-0004004.pdf PDF
36E77620B0001-0004002.pdf PDF
36E77620B0001-0004000.docx DOCX document
36E77620B0001-0004003.pdf PDF
36E77620B0001-0004001.pdf PDF
36E77620B0001-0003001.pdf PDF
36E77620B0001-0003000.docx DOCX document
36E77620B0001-0002000.docx DOCX document
36E77620B0001-0001001.pdf PDF
36E77620B0001-0001000.docx DOCX document
36E77620B0001-011.pdf PDF
36E77620B0001-008.pdf PDF
36E77620B0001-009.pdf PDF
36E77620B0001-012.docx DOCX document
36E77620B0001-010.xls XLS spreadsheet
36E77620B0001-007.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION # 36E77620B0001 UPGRADE SWITCHGEAR & DISTRIBUTION - BALTIMORE

TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 2-6-20 2/25/2020 The spec notes experiences with high voltage, what is considered high voltage?

The voltages for this project will not exceed 480 VAC. Experience should reference projects at this voltage.

2. 2-6-20 2/25/2020 The spec notes requirement of Contractor to have means of temporary emergency power to supply the hospital power in case the outage is beyond the allowable time.

Please specify what capacity/size the generator must be.

Current load for the hospital is 1.1MW.

Temporary Emergency Generator should be sized to handle this load. It is recommended that a 1.5MW generator be utilized to provide a sufficient safety factor.

3. 1-26-20 2-20-2020 Per specification 26 23 00 2.1.A.1, Low Voltage Switchgear - will the VA accept SAI Advanced Power Solutions UL1558 rated front accessible switchgear as an approved equal? Reference attached document titled “SAI Advanced Power Solutions UL1558 - Specifications” to assist with your determination.

Any switchgear proposed must meet the ratings, physical space, and clearance requirements indicated in the bid documents.

4. 1-31-20 2-20-2020 Per specification 26 23 00 2.1.A.1, Low Voltage Switchgear - will the VA accept ESS Metron UL1558 rated front accessible switchgear as an approved equal?

Reference attached document titled “ESS Metron UL1558 - Specifications” to assist with your determination.

Any switchgear proposed must meet the ratings, physical space, and clearance requirements indicated in the bid documents.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

5. 2-3-20 2-20-2020 Per specification 26 23 00 2.1.A.1, Low Voltage Switchgear - will the VA accept DET-890 AKD-20 rear access UL1558 GE switchgear as an approved equal?

This opens up competition since more manufacturers are able to provide this product. This would require repositioning the switchgear in the electrical room.

Possible location is south of the existing substation transformers and switches. Overall width of the switchgear will be reduced. Reference attached document titled “DET-890 AKD-20 Rear Access UL1558 - GE Specifications” to assist with your determination.

Any switchgear proposed must meet the ratings, components, physical space, and clearance requirements indicated in the bid documents.

Alternate positioning of the switchgear as needed can be considered at the contractor’s risk. Any alternates would need to be submitted with coordination drawings to prove compliance. The area to the plan south of the medium voltage switchgear and transformers is not permitted to be used.

6. 2-6-20 2-20-2020 One Vendor for the SWGR, ABB, has a good suggestion to revise the design and relocate the SWGR so that it can be manufactured by more vendors to afford the customer better pricing. The suggestion is to move the SWGR to an open area and maintain code clearances and have rear and from access. This will eliminate the front access requirement on the current design as well as reduce the overall foot print required to be front access only.

Reference attached document titled “Alternate Design Suggestion - E103” to assist with your determination.

Any switchgear proposed must meet the ratings, components, physical space, and clearance requirements indicated in the bid documents.

Alternate positioning of the switchgear as needed can be considered at the contractor’s risk. Any alternates would need to be submitted with coordination drawings to prove compliance. The area to the plan south of the medium voltage switchgear and transformers is not permitted to be used.

7. 2-3-20 2-20-2020 Specification Section 26 23 00, 2.1, A, Low Voltage Switchgear lists the Government approved LV Switchgear manufacturers. Square D Power-Zone 4 by Schneider Electric also offers a LV Draw-out Switchgear rated UL1558 with front access only. Would it be possible to be added to the approved list for the “New Normal Switchgear D”? Reference attached document titled “Square D Power-Zone 4 UL1558 - Specifications” to assist with your determination.

Any switchgear proposed must meet the ratings, components, physical space, and clearance requirements indicated in the bid documents.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

8. 2-5-20 2-20-2020 Per specification 26 23 00 2.1.A.1, Low Voltage Switchgear - will the VA accept Siemens front connected switchgear as an approved equal? Reference attached document titled “Siemens Front-Connected Switchgear” to assist with your determination.

Any switchgear proposed must meet the ratings, components, physical space, and clearance requirements indicated in the bid documents.

9. 2-6-20 2-20-2020 Can we substitute Cummins 3.3 Engine control panels for the specified CAT ECMP4.3 on the Generators?

Reference attached document titled “Cummins 3.3 Engine Control Panels - Specifications” to assist with your determination.

Alternate generator controls are acceptable so long as they will properly function with the existing Onan generators to meet the performance requirements in the contract documents. Any additional modifications to the generators beyond those indicated in the contract documents to accommodate an alternate controller would need to be included.

10. 1-23-20 2-20-2020 We are having some difficulty with vendors trying to quote building the gear for this job. Is there going to be more specifications/drawings provided on the switch gear details and design? If so, will they be posted with this amendment?

Basis of Design is noted on drawings. No additional design of the switchgear is anticipated.

11. 2-6-20 2/24/2020 During the site walk we did not see the freight elevator.

Can you provide the dimensions of the elevator doorway (height x width), the inside dimensions (width x depth x height), the maximum capacity, and the floors it accesses?

There is no freight elevator, the elevators used during the site walk can be used, however those elevators used by patients. The dimension of the elevator cab is 7.5’x6.5’x8.5’ (LxWxH); the door way dimension is 7’x4’ (HxW). The weight capacity per the name plate is 5,000lb.

12. 1-28-20 2/24/2020 Could you tell me whether a third-party firm will be required for construction materials testing/special inspections, and if so, if these services will be hired by the VA or the GC?

GC to hire third party inspector as required in the specifications.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

13. 1-30-20 2-20-2020 Installation of the support steel for the load bank beneath the 8th deck involves penetration through the elevator room fire rated GWB partition above the GBW ceiling currently in place. Do we have access to the architectural & MEP drawings of that area of the 7th floor showing what is involved with accessing the area above the suspended ceiling?

Steel wide flanges may be cut and spliced to fit between existing ceiling pipes and cutwork. After installation of column or beam, replace 2 hour fire rated gypsum board to tight fit around steel web and flange. Caulk edges with HILTI Fire Caulk rated at 2 hours.

No additional drawings are available.

14. 1-30-20 2-20-2020 The site visit revealed multiple levels of piping and conduit in the 7th floor ceiling below the 8th floor deck to receive new steel framing which will require installation of scaffold to access the new steel installation location. We will need to revisit the area to determine how to install the scaffold. Can we schedule a second site visit to that area?

See comment above No. 13. Spliced steel should be lengths and weights to be compatible with elevator size and capacity.

The VA is not conducting additional site visits.

15. 1-30-20 2-20-2020 Please provide a plan of the 7th floor (including the exterior roof area) to allow us to evaluate fall protection options for the 8th floor exterior work.

No fall protection provided. If added at doorway, coordinate with window washing equipment. See E105 (which is mislabeled as it is actually the 8th floor).

16. 1-30-20 2-20-2020 Please identify the existing spray applied fireproofing material utilized on the 8th floor deck steel framing so we may patch it where removed for the new steel connections.

It will be the Contractor’s responsibility for on-site assessment of the existing fire-proofing applied to the existing steel framing to ensure proper repair and remediation should any of the fire-proofing be removed from the face of steel.

Repair qualifications shall meet current AISC code requirements. Replace and repair in kind fire proofing.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

17. 1-30-20 2-20-2020 Please confirm that Note 1 on drawing S101 is identifying the two beams running north and south as part of the rooftop switchgear enclosure framing.

Confirmed. The two new beams are intended to frame directly below the two long-direction curbs of the switchgear. Beams may be spliced to accommodate delivery of beams to the roof via freight elevator.

18. 1-30-20 2-20-2020 Detail 1/A202 Switchgear Enclosure Canopy is depicting 1.5B22 Deck to be installed vertically and fastened to the canopy structural framing. What is this deck to span between as the only canopy framing is a tube steel column located in front of the personnel door?

Span is 3’-11-1/2” per Detail 2-A100.

Use Centria SRS2 decking in 18” widths.

See A101 Detail 6, 7 & 8. There is a lower beam support (4 sides) that is supported by steel columns and raked rafter beams. Decking sits on the later. Assume intermediate perlins as part of raked system as Z channels spanning about 4’.

Support against the existing 8th floor outside wall facing the Switchgear Enclosure is a double channel fastened through the outer wall.

Reference “Exhibit B” attachment posted with this amendment.

19. 1-30-20 2-20-2020 Please confirm the dimensions of P1 electrical room.

Drawings A101 and E102 dimensions are different.

The current design of the room will need to be increased to 12’-6” x 15’8” clear interior dimension. Reference “Exhibit B” attachment posted with this amendment.

20. 2-3-20 2-20-2020 We are unable to find a drawing that identifies floor slab elevations to determine the 8th floor slab height from grade or the 7th floor slab to 8th floor dimension. The engineer had indicated that he thought the information had been included in the drawing set? Could those dimensions be identified for us? (Need sidewalk, 7th floor & 8th floor elevations)

8Th floor to roof is 16’-10 1/2” 7th floor to 8th floor is 28’ – 1 1/2” Reference “Exhibit C” attachment posted with this amendment for all floors.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

21. 2-3-20 2-20-2020 Contract Drawing E403, Note 7, referencing the two meters on the Main Breakers in the “New Normal Switchgear D”. The note indicates that the Meters shall be network capable to connect to existing VA metering network. Can you share information regarding the existing VA metering network? Is there a Power Monitoring System? Who is the manufacturer?

Also, specification 26 23 00, 2.5, A, references 25 10 10 Advanced Utility Metering specification. Can you please provide a copy of this specification?

Meters shall have network connectivity capabilities using Modbus/IP for future integration into VA Utility Monitoring and Control System. No other features are required at this time.

The current system is owned and maintained by VEnergy. The manufacturer is Schneider.

To bring a new meter online, the contractor would need to hook up the CTs and install the meter in the switchgear. They would then need to cable over to the nearest existing Schneider Remote Terminal Unit (RTU). The RTUs communicate with Master Comm system which is located on the 7th floor. Data is then transmitted back to the Schneider server in St. Louis. After the meter is connected to the RTU, the contractor would just need to contact Venergy, who would complete the final integration piece. POC: Josh Cross 925-914- 9212.

22. 2-3-20 2-20-2020 Contract Drawing E405 shows 1500kVA existing transformers feeding the Mains in the “New Normal Switchgear D”. The Mains are rated 3200AF/2500AT according to the drawing however, the 1500KVA Transformers are only rated 1804 amps. Are the Mains sized for a future transformer replacement that have a larger KVA rating? If not, then why include such large Main-Tie-Main Breakers and bus? The Mains and bus could be sized much smaller and save cost to the project.

Please advise.

Provide the sizing indicated in the construction documents.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

23. 2-3-20 2-20-2020 There are lots of references to intercepting existing ABB (GE) Armorclad busway. Square D by Schneider Electric makes adaptors to connect to the existing GE Armorclad busway and allow for the cable tapboxes referenced on the drawings. Would it be acceptable if we provide a solution?

If an acceptable listed fitting is available from other manufacturer’s for transitioning from Armorclad busway which meets the specifications, it would be considered.

24. 2-3-20 2-20-2020 Will it be the responsibility of the General Contractor/Electrical Contractor to phase the project and provide temporary power to the hospital?

General Contractor should follow the installation phasing as noted in the design drawings. Detailed Phasing coordination will be the responsibility of the General Contractor.

25. 2-6-20 2-20-2020 May we use GPR (Ground Penetrating Radar) instead of x-ray for slab inspections?

Use of either non-destructive mechanism is acceptable as long as in-slab utilities can be identified.

26. 2-6-20 2-20-2020 What size conductors are we to use for the Lightning protection on 8th floor structure?

Per specification 26 41 00 2.1 – The structure requires a Class II system. Wiring should be sized accordingly for a Class II system.

27. 2-6-20 2-20-2020 Is there space allotted for the temporary Generator to be used to provide temporary power.

Please refer to E001, Detail 4.

28. 2-6-20 2/24/2020 Due to the complexity of this project for my subcontractors and suppliers, can the bid due date to be extended 2 weeks at the minimum to allow sufficient time for proper pricing?

A bid extension was granted. See Amendment 0003 posted to https://beta.sam.gov/ Also, the General Information contained on this website, concerning bid due date times, cites an erroneous time of 11:59 PM EDT. It is the responsibility of prospective vendors to read the Amendment thoroughly concerning the bid due date and time, which is dictated by the Amendment and not the General Information contained on the website.

https://beta.sam.gov/

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

29. 2-6-20 2-20-2020 Is the structure for the Emergency Paralleling Gear on the 8th Floor required to be pre-fabricated or can it be built on site?

The paralleling gear housing shall be prefabricated with the switchgear and tested prior to arrival on site.

30. 2-6-20 2-20-2020 Automatic Transfer Switches are in various Load Shed

Levels requiring load shed to be at the ATS Level. Are existing transfer switches equipped with communications and control capability so they can be controlled via the paralleling controls? If not then the load shed levels can’t be accomplished as indicated.

Hardwired ATS controls are provided to each existing ATS switch and are currently controlled by the existing paralleling gear and provide engine start signals to the paralleling gear.

Integration of these controls to the new paralleling switchgear will be required.

31. 2-6-20 2-20-2020 Drawings E406 through E409 show the one lines and transfer switches. Emergency Switchboard B shows two feeders (BE2 & BE3, each feeding an ATS #6. From the Sequence of Operations (E003) Load Shed Mode description, it appears that BE2 is ATS#6 and that BE3 is actually ATS#20. Please confirm.

Correct. ATS#6 connected to BE3 is ATS#20.

32. 2-6-20 2-20-2020 Drawing E107, Keynote 10, calls for extension of existing SLC Loop, etc. As it applies to the enclosure itself, it is our interpretation that what this requires is that the switchgear enclosure be provided with mounting provisions (junction box) for the Emergency Strobe currently in the paralleling switchgear room, on the north wall of the room, above and to the right of the entry door.

All wiring and conduit to be provided by others. Please confirm or clarify if otherwise.

The note is indicating where and how the extension of the SLC and NAC circuits should be routed to the new outdoor enclosure. All fire alarm equipment, wiring, conduit, devices, programming, power supplies, and testing is the responsibility of the contractor to provide fully functional fire alarm initiating and notification devices as indicated.

33. 2-6-20 2/24/2020 What is the height restriction for a vehicle carrying switchgear from the Building Entry/Exit to the P1 Level Area D electrical room?

Lowest point is 6’2”

34. 2-6-20 2-20-2020 What are the finished floor elevations, or the distances between floors, for levels P1, B, 1, 2, 3, 4, 5, 6, 7 & 8?

amendment.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

35. 2-6-20 2-20-2020 What is the distance in elevation from level 8, where the Paralleling Switchgear will be located, to the grade of W.

Baltimore street?

36. 2-6-20 2-20-2020 Drawing E407 shows Em Switchboard B with (3) internal ATSs. Two of them are labeled ATS 6, please provide corrected IDs.

Refer to item 31 above.

37. 2-6-20 2-20-2020 Is Generator & ATS Control wiring allowed to be spliced? If splicing is not permitted, the location of each ATS needs to be provided to calculate lengths.

The existing to remain ATS wiring shall be permitted to be terminated in a junction box with terminal blocks as required for the number of conductors. Label box as ATS controls.

38. 2-6-20 2-20-2020 Drawing E407 Note 4 calls for replacement Unit Pricing (Material & Labor) for each individual ATS in the event it does not operate properly. Not enough electrical information is provided in the documents to provide accurate pricing. Please provide additional information or advise.

All ATS switches are shown on the single line for poles, voltage, and amp rating. Switches shall be suitable for 42kA withstand at 480V minimum.

Unit pricing shall include extending existing wiring, conduit, terminations, and additional labor needed to replace an existing transfer switch one for one. Switches shown on the one line within switchboards shall include the ATS components without a housing. No bypass would be required as none are installed on the existing switches.

Switches will need to include remote control capability by the generator paralleling controls, and interface to the new remote annunciators. All other options shall match the new ATS specifications.

39. 2-6-20 2-20-2020 If the Alternate for the load bank is accepted, can the permanent load bank be utilized for the final Generator load bank testing?

Yes it may be used to supplement part of the loading.

40. 2-6-20 2-20-2020 Is there a pathway or access (besides stairway) between the 7th and 8th floors to move large pieces of equipment?

or will Crain lifts be required?

The common freight elevator may be used depending on the size and weight. These elevators are also used by patients.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

41. 2-6-20 2/24/2020 Can an additional walk thru be done before the bid date? No additional walk thru will be facilitated.

42. 2-6-20 2/24/2020 What is the weight capacity of the Elevator reaching the

7th floor?

The weight capacity per the name plate is 5,000lb.

43. 2-6-20 2/24/2020 After going through the 319 page “Total” tab and all the other tabs in the Asbestos Data Table, I am unclear if there is actually any Asbestos Containing Materials that will be encountered on this project. Is there anywhere where it is known that we will encounter and have to remove Asbestos Containing Materials?

The contractor must be familiar with, and certain, that any material they will encounter and/or disturb is non asbestos containing. Should the contractor encounter a building material that is not represented by sampling data provided on the 319 page tab, then contractor shall stop work, notify the VA for further sampling to determine the presence of asbestos. The VA recommends that the contractor inventory the materials to be disturbed, in the course of their work, and compare with existing data table to determine if further sampling will be necessary

44. 2-6-20 2/24/2020 An asbestos table was posted on the beta.sam site. There is no mention of any asbestos to be removed on drawings or within specifications. Can you clarify if we will need to remove any asbestos and if so please provide a specification and quantities?

Roofing and fire doors in the Baltimore VAMC have been assumed to contain asbestos, since destructive testing would ruin the protective integrity of the materials. It is the duty of the contractor to determine if they will disturb any fire doors or roofing materials. If disturbance of material is anticipated, then further testing would be necessary to determine the presence of asbestos. If asbestos is found. then abatement must occur prior to their work. Per VHA Directive: Sampling must be provided by a third party hired through the VA. The contractor is responsible for abatement.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

45. 2-6-20 2/24/2020 Many of my subcontractors and I are concerned that there is not have enough time to bid this project due to some of the complexities and need more time to ask questions as well. Please allow us an additional 2 weeks for submitting our proposal and for additional RFI’s.

Reference Government response to question #28.

46. 2-6-20 2/24/2020 Which elevator will be available to get large equipment in between the 7th and 8th floors? What are the dimensions and weight limit of this elevator?

There are two elevators which can be used, however these elevators are also used by patients and used to transport patients. The dimension of the elevator is 7.5’x6.5’x8.5’ (LxWxH); door dimensions are 7’x4’ (HxW). The weight capacity is 5,000lb per the name plate.

47. 2-6-20 2/24/2020 What is the head room for a truck delivering equipment from the Parking Garage entrance to the electrical room?

Lowest point is 6’2”

48. 2-6-20 2-20-2020 There are 10 existing GE busways that get a cable tap box installed on them. Does the contractor have to test the existing busways before installing the cable tap boxes?

Yes, the busway shall be tested in accordance with NETA ATS.

49. 2-6-20 2-20-2020 Drawing E407, phasing 2 note 4, states that unit pricing to replace existing transfer switches should be provided.

We see no unit pricing requirements on the bid form.

The ATS switches should be part of the base bid pricing.

50. 2-6-20 2-20-2020 Drawing E407, phasing note 5, states the contractor shall have a spare 800A transfer switch with by-pass available should an existing transfer switch fail. If the transfer switch gets turned over to the VA will it remain onsite or will we be required to deliver it to somewhere else?

The ATS shall remain on site for the government.

Store within former paralleling switchgear room.

51. 2-6-20 2-20-2020 Drawing E107 keynote 14 and drawing E409 indicates the outdoor load-bank is optional. Spec 26 32 13 2.7 has the same requirement. We see no optional pricing requirements on the bid form.

The load bank should be part of the base bid pricing.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

52. 2-6-20 2/24/2020 Spec 01 35 36 requires all employees shall have a pre-placement tuberculin screening within 90 days of being onsite. Is it acceptable if the screening was performed within 12 months of being onsite?

The ICRA states the following:

Is there a risk to the Construction Worker to have contact with or have shared airspace with a patient with TB disease or a clinical specimen that might contain Mycobacterium tuberculosis? ☐ Yes ☐ No

If YES, what PPE is required:

If YES, has the contractor provided written certification that all contract employees assigned to the worksite have had a TB screening test within 90 days prior to assignment to the worksite and if the TB screening test was positive do not have respiratory symptoms suggestive of active pulmonary TB? ☐ Yes ☐ No

The only time it requires the 90 day certification is if the worker will potentially be exposed, to a TB patient while working here. We would want baseline information on the worker in that instance.

53. 2-6-20 2-20-2020 Drawing E501 the existing 800A feeder busway has a keynote 3 at the top. This doesn’t seem correct shouldn’t it be keynote 8?

The referenced keynote should be revised to keynote 8.

54. 2-6-20 2-20-2020 Spec 26 32 13 3.2 C. and F. requires the engine generator to be tested with a load-bank using 100% resistive load.

The existing generators are rated 600KW can the new load-bank be used for these tests?

The new load bank may be used for supplementing load for the required testing.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

55. 2-6-20 2-20-2020 If the new 600KW load-bank can be used for the testing, as required in spec 26 31 13, and is optional, and the option is not taken. The contractor will have to rent a portable load-bank for the testing so how can the contractor determine if it should be included in their bid?

The load bank has been included as part of the base bid.

56. 2-6-20 2-20-2020 Spec 26 32 13 3.2 I. requires multiple load-banks including reactive power recordings. Paragraph 2. b.

states “Increase the load in steps until each engine generator is loaded to its service load”. This will take a 4MW resistive-reactive load bank to do this test. The cost of placing and removing this load-bank on the roof to perform the test is very expensive. Did you consider installing a 4MW permanent load-bank on the roof in lieu of the 600KW load-bank? Have you considered the weight (approx. 36,000 lbs.) of the portable load-bank on the roof for the test?

The generator plant must be tested as indicated.

The locations, methods and equipment used for the test can be provided in a variety of ways at the contractor’s discretion. We would not recommend a single 4.5 MVA load bank due to structural constraints. Suggest multiple smaller load banks spaced above beams on the roof at the gear or on the penthouse roof. Testing plans shall be submitted for review and approval.

57. 2-6-20 2-20-2020 Can delivery of the outdoor walk-in enclosure and paralleling switchgear on the penthouse roof take place during the week during normal business hours?

At this time the VA has no issue with normal business hours; coordination and permits with Baltimore are required.

58. 2-6-20 2-20-2020 Will the contractor be given storage in the P1 level for new equipment and materials?

No space is available.

59. 2-6-20 2-20-2020 Spec 01 00 00 allows the contractor to use the facility elevators if they are protected. Are there any times when the contractor is restricted from use?

Preferred hours are before 6am and after 5pm.

60. 2-6-20 2-20-2020 Drawing E105 Note 2 states that the slab to underside of slab is approximately 28 feet. Is this typical for all floors? There are no drawings that indicate what the approximate dimensions are for each floor which we need for the DE2-1 new bus riser.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

61. 2-6-20 2-20-2020 The new 1000A busway for DE2-1 riser is to be installed thru the stacked electrical rooms. The drawings indicate that the busway is installed straight vertically from the P1 level thru to the 6th floor without any elbows or offsets. Confirm this is correct?

The contractor will need to field coordinate the busway selected based on the routing. Although most interferences with the busway stack risers have been addressed, some adjustments may be required.

62. 2-6-20 2/24/2020 Can the work to modify the existing fire alarm system be done during the day during normal hours?

Off hours is preferred.

63. 2-6-20 2-20-2020 Drawing E407; PHASE 2 NOTES: note 2 states:

Outages shall be scheduled for each feeder and transferred in groups as permitted by the VA per outage.

There are 15 feeders that feed 28 associated transfer switches. Approximately how many feeders will the VA allow to be done during a given outage?

Worst cast planning should be applied anticipating a maximum of 1 feeder per outing.

64. 2-6-20 2/24/2020 General note #21 says for the Contractor to provide all fire watch personnel per AHJ standards. Please clarify amount of fire watch personnel acceptable to the AHJ.

If at any time during the scheduled work, if the fire alarm or fire sprinkler system is going to be affected within the area of work for more than 4 hours in a 24 hour period, the contractor will have to provide fire watch. Depending on the area(s) of impairments will determine how many personnel will be required to conduct fire watch.

65. 2-6-20 2-20-2020 Please provide existing fire alarm system manufacturer. The existing fire alarm system is a Siemens

XLSV

66. 2-6-20 2-20-2020 Drawing E107 note #10 requires Contractor to adjust NAC circuit wiring power supply to support additional devices. Please provide current load on NAC circuit and number of free circuits in existing panel, if any.

Information is not available. Assume the need for a new transformer will be required.

67. 2-6-20 2-20-2020 Drawing E106 note #14 requires Contractor to extend existing SLC loop to tie in new devices and match conduit size and wiring. Please provide existing conduit size, wiring, and confirm that free addresses exist to support new devices.

Contractor shall assume 1” conduit and #12 AWG wiring. Addresses are available.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

68. 2-6-20 2-20-2020 Drawing E106 note #18 requires Contractor to extend existing SLC loop to tie in flame sensor and match conduit size and wiring. Please provide existing conduit size, wiring, and confirm that free addresses exist to support new devices.

Contractor shall assume 1” conduit and #12 AWG wiring. Addresses are available.

69. 2-6-20 2-20-2020 Drawing E102 note #11 requires Contractor to extend existing SLC loop to tie in smoke detector and match conduit size and wiring. Please provide existing conduit size, wiring, and confirm that free addresses exist to support new devices

Contractor shall assume 1” conduit and #12 AWG wiring. Addresses are available.

70. 2-6-20 2-20-2020 Drawing E105 note #11 - Please provide approximate distance or location of nearest 120/208 panel serving control room equipment.

Approx. within 150 feet.

71. 2-6-20 2-20-2020 Is there a maximum weight for the new paralleling switchgear and enclosure to be installed on the roof?

Maximum weight limit should not exceed 40,000 lbs. inclusive of slab, however final confirmation will require approval of EOR.

72. 2-6-20 2-20-2020 To meet the paralleling switchgear dimensions of 251”L x 143”W the switchgear manufacturer may have to install the master control cabinet inside the 8th floor penthouse switchgear room. Is this acceptable?

It is acceptable to locate control cabinet in the existing 8th floor switchgear room, pending approval of the equipment and adequate access to the controls is provided in the space.

73. 2-6-20 2-20-2020 What type of load shed signal do the existing transfer switches accept?

Contractor will need to verify. Control wiring exists between the existing switchgear and each ATS. The existing ATS switches are ONAN CNCU or CTCU with OTCU control type with a Load Shed package (neutral position). Schematic Attached from original O&M shown in “Exhibit C” attachment posted with this amendment.

74. 2-6-20 2-20-2020 Spec 26 23 00 para 2.5 A. Metering; refers to section 25 10 10, ADVANCED UTILITY METERING. There is no spec section 25 10 10 in the project documents? Please provide missing section or advise.

Advance Utility Metering has been removed and is not part of this contract.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

75. 2-6-20 2-20-2020 The specifications call out for a schedule of values using the VA Form 10-6001a, or the AIA Form G702 & G703 for invoicing purposes. The project schedule specification calls out for cost loading of activities also for the purpose of invoicing. Would it be allowable to eliminate the cost loading of the schedule and utilize one of the two forms called out for the Schedule of Values and invoicing?

Provide a cost loaded schedule.

76. 2-6-20 2/24/2020 The advertisement calls out the project as a Design/Build project. However, it appears from the specifications that this is a Construction project only. Please confirm.

The advertisement clearly states Design-Bid- Build, which means Construction only.

77. 2-6-20 2-20-2020 What is the fire rating if any for the 8th floor canopy; the 8th floor railings, the 7th floor steel canopy supports; and the standing seam canopy roof? And what material is needed to fire proof these items?

Suggest intumescent paint rated at 2 hours for structural members. Roof deck and covering does not require fireproofing only supporting structure

78. 2-6-20 2-20-2020 Is there any intrumesent paint applied to the structural steel on the 7th and 8th floor steel beams and columns?

All interior beams and columns should be fire proofed with CAFCO spray-on cementitious coating – 2 hour protection. Intumenscent paint is an option but cementitious is less expensive.

79. 2-6-20 2-20-2020 Does the steel tube railing columns get concrete infill? No concrete fill, but top rail must resist 250 lb. horizontal load.

80. 2-6-20 2-20-2020 Do we remove all the stones on the 8th floor roof deck and what if any reroofing material required /applied to the roof deck for roof to certify roof warrantees?

Remove all roofing material scarify sub-straight and reapply same of compatible roofing material.

Note adjacency with raised slab for new switchgear room.

81. 2-6-20 2/24/2020 Who is the roofing contractor bonded under warrantee for this project?

The Garland Company, Inc. was the contractor selected to replace the roofs previously.

82. 2-6-20 2-20-2020 On the 8th floor canopy slab do we need to scarify / grind the deck to provide better adhesion for the roofing material / thoroseal application?

Yes, for both reroofing and treatment to raised slab.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

83. 2-6-20 2-20-2020 The floor opening on the 8th floor for the conduit is there a cover for this opening?

Nothing penetrates the 8th floor in the paralleling room. All conduit is overhead on the 8th floor.

All conduit is within an interior space.

84. 2-6-20 2-20-2020 The painting specifications 09-91-00 states all existing material (walls; piping; conduit; equipment, ceiling) to be painted? This is in conflict with plan notes and finish schedule on A101 which defines areas of painted materials. Question is the specifications correct (it is an open undefined specification) or is the plan notes and finish schedule correct? And if so, what are the boundaries for painting is the interpretation all equipment and materials of the 7th floor; 8th floor; and basement floor. Where does the painting start and where does the painting end?

Plan notes and finish schedule shall prevail.

85. 2-6-20 2-20-2020 Is specification note on 09-91-00 correct that states all conduit greater that 600 volts be painted?

Voltages for this project will not exceed 480V.

Therefore, this portion of the specification does not apply.

86. 2-6-20 2-20-2020 Does the canopy standing seam roof support get painted? Yes, per specification.

87. 2-6-20 2/24/2020 How much storage space can we have in the basement level?

None

88. 2-6-20 2-20-2020 For the bid drop off can we drop the bid off at the VA hospital in Baltimore or in their headquarters in Maryland. Or can we write on the bid folder the $ price add or deduct up to bid time.

Please reference Section 2.8 Bid Submission (pg.

10) of the solicitation for clarification/instructions to this question. No bids should be dropped off at the Baltimore VA Medical Center.

89. 2-6-20 2/24/2020 Can we store in a warehouse and let the COR inspect the materials and still bill for the items as stored materials?

Yes, documents such as insurance verification would be required

90. 2-6-20 2/24/2020 What is the CORs / EOR stated definitions for Asbestos issue on project. What is his summary sheet as a course of action in our work area?

15 USC Ch. 53 § II §2642 (4) Asbestos-containing material - The term ‘‘asbestos-containing material’’ means any material which contains more than 1 percent asbestos by weight.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

91. 2-6-20 2/24/2020 What are EORs and CORs plan of action for infection control protection on the VA hospital? Is it just the elevator area or our work area as a defined infection control?

All work done for this project/contract is subject to infection control protection.

92. 2-6-20 2-20-2020 Permits for Baltimore City for street closures and crane lifts is there any other VA stipulations as to area for crane lifts / street closures and roadway shut down that meets VA standards or requirements?

Follow City of Baltimore standard guidelines for street closures related to lifting equipment to be used for project.

Contractor is responsible for timeframe for obtaining all permits within construction schedule.

93. 2-6-20 2-20-2020 Who is the existing Fire Alarm Manufacturer and/or Installer at the Baltimore VAMC?

Refer to Item 65

94. 2-6-20 2-20-2020 What is the make and series of the existing FA system? Refer to Item 65

95. 2-6-20 2/24/2020 Who is the building’s approved FA tie-in contractor? BFPE

96. 2-6-20 2-20-2020 Please confirm the desired finish/color for the canopy roof will be the manufacturer’ standard color/finish.

Per A101, Centria 9921 – Charcoal Gray. This is a Peachtree provided color. The material is .040 aluminum per standard Centria standing seam material.

97. 2-6-20 2-20-2020 What color is the desired “Centria” standing seam metal roof on the roof canopy?

See note 96 above.

98. 2-6-20 2-20-2020 Please confirm that the roof is standard 22-gauge metal. Centria SRS-2, ribbed standing seam, .040 Contractor to verify at the time of demolition;

existing drawings appear to indicate as such

99. 2-6-20 2-20-2020 Per drawing E303; “Extend existing control wiring for ATS switched from existing switchgear to new. Assume 3-2” conduits with 10-#12 awg conductors per transfer switch (Typ of 28).” Please confirm that the above is accurate, as this would involve 84-2” conduits, just for the controls. Could we install 1” in lue of 2”?

The conduit quantity refers to the overall required conduit. The wiring would be typical of 28. The contractor may use conduit sizes and types as necessary within the NFPA 70 limitations.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

100. 2-6-20 2-20-2020 Please provide specific shop order numbers or pictures of the existing bus duct to ensure proper transition, extension and compatibility.

Pictures attached of some the types installed for information only. Reference “Exhibit A” attachment posted with this amendment.

Contractor must field verify all busway for proper fittings.

101. 2-6-20 2-20-2020 Please provide generator model number, DOM, for coordinated paralleling SWGR manufacture.

Pictures provided of some of the generator nameplates for information only. Contractor must field verify all generator components for proper interface and upgraded components shown in “Exhibit A” posted with this amendment.

102. 2-6-20 2-20-2020 Please provide floor to floor height dimensions for bus duct runs as well as floor thickness for floor penetrations.

Reference “Exhibit C” attachment posted with this amendment showing floor heights.

103. 2-6-20 2/24/2020 Please provide the current site plan for the crane and rigging setup for the SWGR installation.

A site layout can be provided after issuance of

NTP.

104. 2-6-20 2-20-2020 I am trying to estimate and price out the above referenced Exterior Switchgear enclosure but there is no section through the Roof Structure plan on sheet S101 indicating the relationship between the existing building roof (8th floor???) and the new, proposed enclosure.

Please advise.

The new switchgear enclosure is identified on E- 106, which is the 8th floor. Column line G is where the 8th floor penthouse ends and the 8th floor roof begins. Connections from the 7th floor are shown at E105 near Stair #8. General note 2 gives guidance on the 7th floor to deck height.

105. 2-6-20 2-20-2020 Detail 1-A202 and 3-A202, pointing at the floor, are calling out for a ROOF support tube system for metal decking and a standing seam roof system above it to be fastened to an 8”x 8” steel plate with nelson studs attached to a 6” housekeeping slab. Is this directly installed on the existing roof?

This question does not provide sufficient information to provide an answer.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

106. 2-6-20 2-20-2020 Normally Nelson Studs are welded to the top of a floor beam through a structurally designed composite steel deck system to achieve a designed composite floor design; this is not the case here. There is no roof framing plan, no clear details or sections, no detail of the 8”x 8” plate and its relationship to the roof framing system.

Please advise.

This question does not provide sufficient information to provide an answer.

107. 2-6-20 2-20-2020 The Switchgear Enclosure elevation/profile 5-A101 is showing a 10’-8” tall height profile at the same height as the enclosure canopy roof on 15” WF Dunnage. Please advise.

Detail 5-A101 does not show Switchgear Enclosure (SE) but canopy that is between existing wall and SE. Height of bottom of canopy shall be 8” above personnel door of the SE.

108. 2-6-20 2-20-2020 What comprises the exterior, ribbed aluminum sheet metal enclosure walls and how is it fastened to the enclosure building structure; I see no details or clarity;

please explain.

Existing conditions for the ribbed aluminum sheet is not specified by the structural EOR on this project. Contractor shall verify fastening system and any required repair work per the existing drawing as-built conditions and in-field observations. Reference “Exhibit B” attachment posted with this amendment.

109. 2-6-20 2-20-2020 What is the maximum size of the entrance to the P1 Area D Main Electrical Room (reference drawing E103)?

The double door indicated at the south end of the room is the largest entrance. Equipment entering this side would need to navigate around the medium voltage transformers and switches.

110. 2-8-20 2-20-2020 Does the whole lightning protection system have to be recertified?

No. Portions relative to the new installation should be installed per code.

111. 2-8-20 2-20-2020 Drawings show option, please confirm options are to be priced as part of the base bid.

Load Bank is to be part of the base bid.

112. 2-8-20 2/24/2020 Please confirm a third-party inspector is required. Yes

113. 2-8-20 2-20-2020 Electrical drawing E203, E204, & E501: Please provide the floor heights for area D electrical room in basement, 1st,2nd,3rd,4th ,5th & 6th floors so as to enable bidder to calculate the total length of the new DE2-1 Bus-way riser.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

114. 2-8-20 2-20-2020 Electrical drawing E407: Phase 2 Notes 4 states unit pricing for material & labor will be provided for replacement transfer switches for matching sizes & ratings for each switch in the event the existing transfer switch does not operate properly but this not shown as a line item in pricing schedule (page 6 of bid document).

Also please provide the existing ATS’s Make/model#.

Pricing for replacement ATS should be included as part of base bid. ATS Manufacturer Cummins.

See attached picture with ATS Schedule shown in “Exhibit C” posted with this amendment.

115. 2-8-20 2-20-2020 Electrical drawing E409: Phase 4 Note 2: New Load bank 800KW 480V 3 Phase in one line generator paralleling switchboard indicate as Optional but not shown as a line item in pricing schedule (page 6 of bid document).

Load Bank is to be part of the base bid.

116. 2-8-20 2-20-2020 Drawing E-409, Note 2 under PHASE 4 NOTES states:

"PROVIDE LOAD BANK CONNECITON

IF PROVIDED IN CONTRACT.” Is the load bank included? and is it to be in CLIN 002 pricing?

Load Bank is to be part of the base bid.

117. 2-8-20 2-20-2020 Drawing E-106 Note 4 states: "REFILL GENERATOR

FUEL TANKS AFTER COMPLETION OF ALL

TESTING." Are they referring to the 3-day tanks upstairs or a storage tank elsewhere?

Any fuel utilized for the load testing will be required to be replenished by the Contractor.

Contractor is responsible for topping refilling main tank for fuel that was used during testing.

118. 2-20-20 2-20-2020 Part 2 - Products, Section 2.1 General Requirements, paragraph A. “Lightning protection components shall conform to NFPA 780 and UL96, for use on class II structures. Aluminum Materials are not allowed. Can the specification be changed to read as “Aluminum Materials are allowed only where required by code due to dissimilar metals.”

Aluminum and copper are allowed by code.

When there are dissimilar metals in contact, aluminum materials shall be used.

ADDITIONAL QUESTIONS

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

119. 3-6-20 3-11-2020 Per addendum #4 RFI’s, Q/A #38 & #49 – The answer provided states the replacement ATS switches should be part of the base bid pricing… How are we suppose to provide unit pricing for replacement of these ATS’s, given the base bid is a lump sum price? Can the VA provide an additional bid forum so contractors can provide the necessary unit prices;

separate of the base bid?

Are we supposed to include replacing all 28 ATS’s in the base bid, or just 1 of each size/rating/mounting provision?

When replacing these ATS’s, will temporary power be necessary, due to critical downstream loads? These unit prices are better suited to be applied after award of the contract.

Drawing E407 - PHASE 2 NOTES (Item 4) States: Unit pricing for materials and labor will be provided for replacement transfer switches of matching size and ratings for each switch, in the event the existing transfer switch does not operate properly.

Please be advised that this note is referring to after an award has been made and if the existing transfer switch does not operate properly.

Offerors should not include pricing, concerning this note, with their offer.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

120. 3-9-20 3-11-2020 Reviewing the answers to questions, in amendment 4-1, the answer to questions 38 and 49 creates an ambiguity.

On drawing E407 phasing notes 4 and 5 state that the contractor shall provide unit pricing for replacing transfer switches in case they do not operate properly and one spare 800 amp transfer switch. VMAC has 28 transfer switches ranging in sizes from 100 amp to 800 amp. Specifically the sizes are 100, 200, 260, 400, 600 and 800 amps. There would be a cost difference to replace each size transfer switch, one price would not correlate with each size switch. The answer to question 49 directs us to include the cost of the transfer switches in the base bid. How does the contractor know how many switches to include, all 28?

We believe the best approach would be to have unit pricing on each size switch on the bid form separate from the base bid? At this time we don’t know what to include in the base bid; just the cost of the wiring to replace each of the 28 transfer switches (as in note 4 on drawing E407) or the cost of the wiring and a new transfer switch(the answer to question 49)?

Drawing E407 - PHASE 2 NOTES (Item 4) States: Unit pricing for materials and labor will be provided for replacement transfer switches of matching size and ratings for each switch, in the event the existing transfer switch does not operate properly.

Please be advised that this note is referring to after an award has been made and if the existing transfer switch does not operate properly.

Offerors should not include pricing, concerning this note, with their offer.