36E77619R0071-002.pdf

PDF 130 KB Posted

Attached to
Repair Station Air Control and Install VFD's Design-Build - Overton Brooks VAMC
Solicitation number
36E77619R0071
Issued by

About this file

36E77619R0071 Final SOW - 5-31-2019.pdf

View the file

Other files

File Type Posted
36E77619R0071-003.docx DOCX document
36E77619R0071-009.pdf PDF
36E77619R0071-008.pdf PDF
36E77619R0071-006.zip ZIP file
36E77619R0071-005.zip ZIP file
36E77619R0071-004.docx DOCX document
36E77619R0071-001.docx DOCX document
36E77619R0071-007.pdf PDF
36E77619R0071-010.docx DOCX document
36E77619R0071-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Repair Station Control Air System & Install VFD’s

Project #667-19-104

Contractor shall provide all labor, materials, tools, equipment and supervision necessary to design and build (Design/Build) a project to repair station control air system and replace or install various variable frequency drives (VFD’s) at Overton Brooks VAMC, Shreveport, LA.

1. REPLACEMENT: Replacement shall include all new variable frequency drives, controls, conduit, wiring, demolition, and metering devices indicated below. When deemed necessary the contractor shall replace disconnects, alarms, and associated controls, programming and any other appurtenances to provide a complete and functional system for these items. All modified systems are to be commissioned, tested, and balanced as part of this project. Items to be addressed are outlined as follows:

A. Cooling Tower #1- Main

1. Three pump VFD

2. Two fan VFD

B. AHU-3N

1. One DX-9100 Metasys Module (in new location and/or external enclosure)

C. Chilled Water Pumps – 2AE-101

1. Three pump motor VFD

D. AHU- 2AE-101

1. Two supply fan motor VFD

E. Cooling Tower #1 condenser water flow meter

1. Replace with a device that meets or exceeds F-3500 electromagnetic flow meter

F. Flow Pak Water Distribution-SB Room#4

1. Two pump motor VFD

2. INSTALLMENT: Installment shall include all new soft starters, disconnects, electrical switches/wiring, alarms, controls, conduit & wiring, piping, demolition, and any associated controls programming and any other appurtenances to provide a complete and functional system. All modified systems are to be commissioned, tested, and balanced as part of this project. Items to be addressed are outlined as follows:

A. Facility Fresh Air Supply – 11th floor

1. One fan motor soft start B. Facility Main Exhaust – 11th floor

1. One fan motor soft start C. Update/repair graphic control points and associated mapping for the following areas:

1. Check 1W rooms to match drawing to room numbers on doors

2. Bldg. 57

A. Add monitoring for dental vac pumps B. Rooms 124&224 humidity operation C. Add vacuum pump and compressor system to Metasys D. Bldg. 57 not on graphic at front end of page

3. All ambulatory care VAV controls

4. 3N20 VAV not controlling

5. AHU’s 2-1, 2-2, 2-3 change front end to add RF to the unit names

6. AHU #1 Life Support to white team (rename at frontend)

7. 11th floor exhaust fan shows local command at front end

8. Parking garage not on graphics

9. Need to map N2 in 8N8 FCU new Tstat

10. Add exhaust fan summary tab under mechanical system tab at front end

11. Red Team VAV’s graphic (most all show offline)

3. PHASING & CONSTRUCTION REQUIREMENTS:

For this project, any required utility system outages needed in order to perform work will be scheduled at the convenience of the VA and may require work to be performed during hours where government staffing is available. This may be either during business hours or after-hours work, depending on the nature of the outage and VA staffing availability. All utility outages will be coordinated two weeks in advance with the project COR.

To complete the design and construction of the cooling tower and flow meter, the facility will transfer the primary cooling tower system load to the secondary cooling system. The contractor must ensure the outside air temperature is below 80 degrees Fahrenheit before starting this task; otherwise the cooling tower will not support the system demand. The work needed for the flow meter and Cooling Tower #1 will be completed simultaneously.

To complete the design and construction of the facility fresh air supply and main exhaust, AHU-3N, and AHU-2AE101, some work will be conducted 4:30pm-6:30am, Mon-Fri, or on Sat and Sun, excluding federal holidays, unless otherwise coordinated with the COR.

To complete the design and construction of chilled water pumps and water distribution pumps, the contractor will coordinate work with the VA COR.

4. DESIGN & DESIGN SUBMITTALS: Reference specification provided for Request for Proposal to Design Build. Contractor’s designers (Design Build Team) shall provide a complete design to repair station control air system and replace or install various variable frequency drives per this scope of work. The designers shall develop 35%, 95% & 100% (Final) plans and specifications for review and approval by the VA in accordance with the A/E Submission Instructions for Minor and NRM Construction Programs; PG-18-15, Volume C. Design submission shall include load calculations stamped by a Profession Engineer. Design drawings shall include all demolition and new work, and in sufficient detail to provide for a thorough review by the VA.

NOTE: Contractor to verify ALL dimensions and equipment. Completed design documents shall be stamped by registered a Professional Engineer for each discipline. Design shall be in accordance with the VA Master Specifications (Table of Contents provided) and shall include all site investigation, site survey, calculations, testing and design for documents to construct the subject project. The following specification are provided with this solicitation and shall become a part of this contract and design documents:

a. 00 11 21 Request for Proposal to Design Build

b. 01 00 00 General Requirements

c. 01 32 16.17 Project Schedule

d. 01 33 23 Shop Drawings, Product Data & Samples

e. 01 35 26 Safety Requirements

f. 01 42 19 Reference Standards

g. 01 45 00 Quality Control

h. 01 57 19 Temporary Environmental Controls

NOTE: DB Team to develop all other project applicable specifications.

5. CONSTRUCTION & PRODUCT SUBMITTALS: Construction and product submittals shall be as outlined in the VA Master specifications and are to be submitted during the design phase and incorporated into the design once approved where possible/practical.

Provide submittals in accordance with the Shop Drawings, Product Data & Samples Specification provided.

6. VA REQUIREMENTS: Contractor to work in accordance with the Infection Control Risk Assessment provide and in accordance with the General Requirements, Safety Requirements and Construction Waste Management specifications provided. Contractor shall follow all applicable Federal, State & Local Codes.

7. INSTALLER QUALIFICATIONS & SYSTEM REQUIREMENTS: Contractor shall ensure that the new VFD and HVAC controls are installed in accordance with the manufacturer’s recommendation and by a certified manufacturer’s installer. Contractor shall provide written proof of certification prior to start of work. Installer shall have 10 years’ experience installing similar size units/systems and shall provide references of 3 installations within the past 5 years. Upon completion of the installation the contractor shall provide certification of the units. Contractor shall provide a 5-year manufacturer’s warranty on materials, panel installation, assembly and seals and a 3-year service warranty. All mechanical equipment shall be installed by a licensed mechanical contractor.

8. WORK HOURS: Unless otherwise stated, most of the work shall be accomplished between the hours of 7:00am to 4:30pm Monday through Friday (excluding federal holidays). The contractor may be required to accomplish some work after hours or on weekends to minimize disruption to hospital operations. All work shall be coordinated with the COR.

9. PERIOD OF PERFORMANCE: Performance period for this contract shall be 220 calendar days for design and construction from NTP date per the following breakdown:

1. Notice to proceed –D Day

2. SD Submission (35%) –D+31

3. SD Review by VA complete – D+45

4. DD Submission (95%) – D+71

5. DD Review by VA Complete – D+85

6. CD submission (100%) -D+92

7. CD Review by VA Complete -D+106

8. Documents Complete (CD Issue) – D+113

9. Mobilization Complete – D+128

10. Construction Complete – D+220

Submittals Required (at a minimum):

1. 35%, 95% & 100% (Final) design drawings & specifications

2. Manufactures data on VFD’s, flow meter and Metasys module.

3. All new equipment to be installed

4. Start-up and testing procedures

5. Manufacturer warranty/guarantee certificate