- Z2DA--523A4-CSI-288 3.0T MRI Site Prep - Design Build West Roxbury VA Medical Center (VAMC_ West Roxbury, MA
- Solicitation number
- 36C77627R0013
About this file
This is a database specifications document for the 3.0T MRI Site Preparation Design-Build project at West Roxbury VA Medical Center. The specifications outline the technical requirements for database infrastructure supporting the new MRI facility, including system architecture, data management protocols, security standards, and integration requirements with existing Veterans Affairs information systems. The document details specifications for database performance, capacity planning, backup and disaster recovery procedures, and compliance with federal healthcare data protection regulations including HIPAA and VA-specific security requirements. Database specifications address transaction processing capabilities, data redundancy, failover mechanisms, and audit logging to support clinical operations and ensure continuity of medical imaging services. The document establishes technical parameters for system interoperability with the facility's electronic health record systems and Picture Archiving and Communication Systems (PACS) infrastructure required for MRI imaging operations.
The specifications include requirements for database administrators, maintenance protocols, monitoring systems, and performance metrics necessary to support the 3.0T MRI equipment deployment. Infrastructure requirements address server specifications, storage capacity, network connectivity, and environmental controls to maintain optimal database functionality in a clinical setting. The document serves as a critical technical reference for contractors responding to the Design-Build solicitation, establishing baseline expectations for database systems that will support diagnostic imaging and patient care operations at the West Roxbury facility.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Boston Healthcare System
West Roxbury Division 1400 VFW Parkway
West Roxbury, MA 02132
Project #523A4-CSI-288
Project Title: 3T MRI Site Preparation
SPECIFICATIONS
TABLE OF CONTENTS
SECTION TITLE PAGE
01 00 00 GENERAL REQUIREMENTS 02
01 32 16 PROJECT SCHEDULES 51
01 33 23 SHOP DRAWINGS 74
01 35 26 SAFETY REQUIREMENTS 82
01 42 19 REFERENCE STANDARDS 120
01 45 00 QUALITY CONTROL PLAN REQUIREMENTS 129
01 45 29 TESTING LABORATORY SERVICES 132
01 45 35 SPECIAL INSPECTIONS 150
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS 166
01 58 16 TEMPORARY INTERIOR SIGNS 171
01 74 19 CONSTRUCTION WASTE MANAGEMENT 172
01 81 13 SUSTAINABLE CONSTRUCTION REQUIREMENTS 179
01 91 00 GENERAL COMMISSIONING REQUIREMENTS 192
10-01-17
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including any required demolition or selective demolition and removal of existing structures, and furnish labor and materials and perform work for 523A4-CSI-288 3.0T MRI Site Preparation.
1. It is the intent of this scope of work that a Design-Build
Contractor shall provide architect/Engineer professional services and construction services for site preparation for the installation of new equipment in Building 1, West Roxbury Division.
2. Strict noise and infection control measures shall be followed.
Existing life safety systems within Building 1 shall not be impaired at any time during the performance of the work.
B. Visits to the site by Contractors, subcontractors, suppliers / vendors will be coordinated with the VA Contracting Officer (CO).
C. Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the Contractor shall notify the
Contracting Officer (CO) in sufficient time to enable witnessing of the testing laboratory personnel taking and testing of specimens and field inspection. Such prior notice shall be not less than two (2) weeks unless otherwise designated by the Contracting Officer (CO).
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
E. Prior to commencing work, general contractor shall provide proof that an OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
F. Training:
01 00 00 -2
1. All employees of the general contractor or subcontractors shall have the 10-hour or 30-hour OSHA Construction Safety course and other relevant competency training, as determined by COR acting as the
Construction Safety Officer with input from the facility Construction
Safety Committee. The designated competent person representing the general contractor and subcontractors will have a minimum 30-hour OSHA certification.
2. Submit training records of all such employees for approval before the start of work.
H. VHA Directive 2011-36, Safety and Health during Construction, dated
9/22/2011 in its entirety is made a part of this section
1.3 STATEMENT OF BID ITEM(S)
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1.00 JB __________________ __________________
Design Services:
1.00 JB _______________ _______________
Construction Services:
GRAND TOTAL _______________
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, Contractor shall bear the cost of providing, as necessary, complete sets of specifications and drawings to the
Contractor and his/her subcontractors by downloading electronic versions furnished by the issuing Office. The electronic files will be available from the website where the solicitation is posted. Additional copies will be at Contractor’s expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
01 00 00 -3
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project. The general contractor shall generate a site-specific security plan for VA Project Engineer (COR) and Contracting Officer review prior to mobilizing onsite.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
3. The General Contractor shall provide an index of all subcontractor personnel that will be visiting/working on-site. The index shall include the names of the workers, photo ID, and name of their employer for all personnel.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. In accordance with VA Directive 0735 Personal Identity Verification of Federal Employees and Contractors, all contractors on VA premises are required to obtain proper identification cards. The following information describes the criteria for each type of identification card. The contractor is responsible for reviewing the following information & make a determination in order to make the appropriate
PIV badge request to both the VA Project Engineer and Contracting
Officer. Final determination is made by Contracting Officer.:
a. PIV CARD is required for all unsupervised, full time, logical and/or physical access for more than 6 months OR more than 180 aggregate days in one year period. In this description, unsupervised is to mean unescorted by VA personnel into areas off public corridors that would require possession of a key or being granted access control privileges to enter through a secured door. Time onsite is determined by the Period of Performance of the contract/task order and shall include all prime and sub-contractor personnel (to include sub-subcontractors) regardless of the actual personal time on site. The issuance of a PIV Card requires two forms of acceptable identification, a favorable SAC
01 00 00 -4 adjudication and an initiated National Agency Check with Written
Inquiries (NACI).
b. Non-PIV CARD is required for all unsupervised, full time, logical and/or physical access for less than 6 months OR less than 180 aggregate days in one year period. In this description, unsupervised is to mean unescorted by VA personnel into areas off public corridors that would require possession of a key or being granted access control privileges to enter through a secured door. Time onsite is determined by the Period of Performance of the contract/task order and includes all prime and sub-contractor personnel (to include sub-subcontractors) regardless of the actual personal time on site. The issuance of a PIV Card requires two forms of acceptable identification and a favorable SAC adjudication.
c. Flash Badge is required for common access ONLY for less than 6 months or less than 180 aggregate days in one year period. Time onsite is determined by the Period of Performance of the contract/task order and includes all prime and sub-contractor personnel (to include sub-subcontractors) regardless of the actual personal time on site. The issuance of a Flash Badge requires one form of acceptable identification.
3. Contractors are required to submit to the Contracting Officer a list of personnel to be mobilized for the work associated with the contract/task order scope of work to be completed under this specification to the CO and VA Project Engineer (COR). The list is to include status of SAC background investigation, i.e. – SAC +
NACI, date completed; SAC, date completed; None.
4. Determination of the level of identification required will be based on the contract/task order scope of work and level of access required. The final determination will be made by the VA Project
Engineer and Contracting Officer.
5. Contractors are to contact the VA PROJECT ENGINEER (COR) regarding credentialing requirements.
6. VA PROJECT ENGINEER (COR) will facilitate contractor submission of information through the CO, PIV Sponsor and PIV Office at the
Medical Center to obtain proper credentials for each contractor
01 00 00 -5 personnel to be on campus to complete the contract/task order scope of work to be completed under this specification.
7. Instructions to obtain badges: The general contractor shall complete the PIV form application & submit PIV, Flash & Non-PIV card requests to the Engineering PIV Sponsor via email. Sponsor submits the request into a software application to Human Resources & will contact individuals who submitted the application. The PIV card requires a fingerprint check along with the initiation of a NACI background check. If the results are returned favorably, Human
Resources contact the PIV Sponsor to have the contractor report to the PIV Office to have their photograph taken & issued their card.
8. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
9. Work shall be accomplished during normal work hours, Monday through
Friday, 7:00am to 4:30pm (unless approved by the VA) excluding
Federal holidays, as to cause the least interferences possible with the normal activities of the facility and the surrounding areas.
a. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 5 business days’ notice to the VA Project Engineer (COR) and Contracting Officer so that notifications can be distributed if needed, services informed and coordinated with and so VA Police & Engineering M&O are made aware of off-hours work. This notice is separate from any notices required for utility shutdown described in the contract documents.
10. No photography of VA premises is allowed without written permission of the Contracting Officer.
11. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
01 00 00 -6
C. Information Technology Security: The contractor, their personnel, and their subcontractors shall be subject to the Federal laws, regulations, standards, and VA Directives and Handbooks regarding information and information system security as delineated in this contract.
1. See Appendix H for HB6500 6 Handbook requirements. Contractor personnel and their subcontractors are required to review and sign.
D. Newly Installed Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the VA Project Engineer (COR) and VA Locksmith for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
01 00 00 -7
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. As space is limited, the Contractor may not be guaranteed parking at the facility. Vehicle authorization requests shall be required for any vehicle entering the site and such requests shall be submitted to the VA PROJECT ENGINEER (COR) 72 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies. Vehicles that are authorized to be on site shall obey all standard parking regulations, and shall not obligate parking reserved for veterans. General contractors, their employees, subcontractors, vendors, manufacturer representatives, etc shall park in the designated contractor parking lot near Building 2.
2. If parking is available, separate permits will be issued for General
Contractor and its employees for parking in designated areas only.
a. All Contractor vehicles shall be parked in the designated
Contractor Parking lot, parking of Contractor vehicles outside of the designated lot is prohibited and vehicles will be towed at the
Contractors expense.
3. Special vehicles (flatbed semis or box trucks, cranes, chemical delivery, etc....) require separate special authorization and such requests shall be submitted 72 hours before the date and time of required access.
01 00 00 -8
G. Partial Road Closure
1. Contractor shall submit a Partial Road Closure Form at a minimum three (3) weeks in advance to VA Project Engineer (COR) for review, acceptance and campus notification. The general contractor and subcontractors shall not be permitted to fully close a road; only partial road closures are permitted. The written request shall include, but not be limited to, Project #, Date of Request, name of general contractor, name(s) of sub-contractor(s), date(s) of requested partial road closure, time(s) of requested road closure, location description, include a marked-up Google Earth image of the location, (showing construction activity limits, normal traffic flow routes, new proposed traffic flow reroutes, protection, barriers, cones, flagmen positions, traffic signage, etc.), description of work to be completed. Protection required, but not limited to, solid barricade with flashing lights, warning cones/signs and construction barriers, construction fencing, flagmen to direct vehicular and pedestrian traffic, traffic signage, etc. Cover partial road work with steel plates to permit traffic flow prior to performing work on other side of roadway. One lane shall always be open and passable.
The general contractor shall bear the cost to obtain West Roxbury
Police Department and/or MA State Police flagmen at work along
Spring Street, FVW Parkway, etc. VA Police do not perform flagmen duties on site; the general contractor shall include flagmen whose sole responsibility is flagmen duties during site work when necessary. Road closure requests previously accepted by engineering may be canceled or postponed, (up to 24 hours prior to work being completed) by the VA Project Engineer (COR) if required for VA
Medical Center operations, events, etc. at no delay, cost or time impact to the government.
H. Traffic Control Plan (TCP)
1. Contractor shall submit a detailed phasing narrative, Traffic
Control Plan (TCP) with marked-up site plans and Google Earth images, Partial Road Closure Permit, and proposed specific phasing schedule showing how each phase will be accomplished. TCP shall be a comprehensive method of how traffic is proposed to be handled during the duration of each Phase. The TCP shall include, but not be limited to construction sections, work zone pavement markings, 01 00 00 -9 channelization devices, signage appropriate for the various phases, detour routes, temporary signals, dynamic message signs, etc.)
Detailed Phasing plan shall include all fields required from the partial road closure at a minimum, as well as a detailed sequence of work narrative, etc. Phasing shall be accomplished to minimize disruptions to the VA Medical Center operations and City of West
Roxbury, ensure safety of the traveling public and construction personnel, ensure environmental protection, ensure patient safety and construct the proposed phasing in the most effective manner possible. The general contractor, once phasing request has been accepted by the VA, shall coordinate with the City of West Roxbury, West Roxbury Fire Department, West Roxbury Police Department, MA
State Police, MA DOT, emergency forces that serve the VA Medical
Center (i.e. ambulance service, etc.) and provide written confirmation of coordination with whom was contacted, name of company/department/service, contact information (address, email, phone, etc.), date contacted, meeting minutes of conversation, etc.
General contractor shall perform all necessary work required to install the new security manhole covers the same day the existing manhole cover is removed. No grates, catch basins, inlets, manholes shall be uncovered and not covered in the same business day
I. Temporary and Permanent Paving
1. The contractor shall perform all final paving by the COB (close of business) each day. The day the general contractor performs saw cutting of the roadway and sidewalk, excavates and installs new work beneath the roadway and sidewalk, the general contractor shall also install new fill, compact, test, and install temporary or permanent paving. The contractor shall not cover the area with steel plate overnight. The contractor shall not compact fill to grade at roadway or sidewalks; paving shall be installed, no exceptions.
J. Security Manhole Covers
1. No grates, catch basins, inlets, manholes shall be uncovered and not covered in the same business day.
01 00 00 -10
1.6 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009.............Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2010..............Standard for Portable Fire Extinguishers
30-2008..............Flammable and Combustible Liquids Code
51B-2009.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2011..............National Electrical Code
101-2012.............Life Safety Code
241-2009.............Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926..........Safety and Health Regulations for Construction
4. VHA Directive 2005-007
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to Contracting Officer (CO) VA Project
Engineer (COR) and Facility Safety Manager for review for compliance with VHA Directive 2005-007, NFPA 101 and NFPA 241.Prior to beginning work, all employees of the contractor and/or any subcontractors shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc. Provide documentation to the VA Project Engineer (COR)
01 00 00 -11 that all construction workers have undergone contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separated by 3m (10 feet).
E. Temporary Construction Partitions:
1. Install and maintain temporary construction partitions to provide dust and smoke-tight separations between construction areas and adjoining areas. Construct partitions of gypsum board or treated plywood (flame spread rating of 25 or less in accordance with ASTM
E84) on both sides of fire-retardant treated wood or metal steel studs. Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. At door openings, install Class C, ¾ hour fire/smoke rated doors with self-closing devices.
2. Install fire-rated temporary construction partitions as shown on drawings to maintain integrity of existing exit stair enclosures, exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, vertical shafts and openings enclosures.
3. Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through-penetration firestop materials in accordance with Section 07 84 00, FIRESTOPPING.
F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with VA
Project Engineer (COR).
01 00 00 -12
H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to
VA Project Engineer and Facility Safety Manager.
I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA
241 and NFPA 10.
J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
K. Sprinklers: Install, test and activate new automatic sprinklers prior to removing existing sprinklers.
L. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide a fire-watch for impairments more than 8 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with VA Project Engineer (COR) and Facility Safety
Manager. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the VA Project Engineer (COR).
M. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with VA Project Engineer
(COR) and VA Safety Specialist. The general contractor shall submit on a weekly basis (by the COB each Thursday of the preceding week) a smoke shunt request (if applicable) via email to the VA Engineering M&O
Foreman copying VA Project Engineer (COR) and VA Safety Specialist. The smoke shunt request shall include the smoke detector device identification codes. VA Safety does not permit two fire protection systems (smokes and sprinklers) to be offline at the same time. The general contractor shall plan for this.
N. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with VA Project Engineer (COR).
Obtain permits from VA Safety Specialist _72_hours in advance.
01 00 00 -13
Designate contractor's responsible project-site fire prevention program manager to permit hot work.
O. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with and report findings and corrective actions weekly to VA Project Engineer (COR) and Facility
Safety Manager.
P. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
Q. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.
R. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
S. If required, submit documentation to the VA Project Engineer (COR) that personnel have been trained in the fire safety aspects of working in areas with impaired structural or compartmentalization features.
T. The Contractor shall submit on a weekly basis to the Contracting
Officer's Representative (COR) completed Interim Life Safety Measures
(ILSM) Forms.
1.7 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance. The general contractor shall provide a written request, at a minimum of 2 weeks prior to the mobilization and construction commencement date, a request to the VA Project Engineer (COR) and Contracting Officer to store any materials within VA interior spaces. Request shall include a detailed inventory of materials being requested to be stored, quantities of each material, material safety data sheet (and globally harmonized system of classification) information of each material, approximate duration of
01 00 00 -14 anticipated storage being requested, how the material will be stored, where in the requested space each material will be stored, etc.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
C. Working space and space available for storing materials shall be as determined by the VA Project Engineer (COR).
D. Storage (Conex) Boxes/Containers
1. Contractors shall be limited to two (2) on-site storage boxes/containers.
2. Storage boxes/containers shall be removed from site upon completion of construction.
3. Contractor shall request placement of all storage boxes/containers from the VA Project Engineer (COR) identifying on a marked-up site plan (using Google Earth screen shot) the approximate location of all containers.
E. Contractor Office Trailers
1. Contractor trailers shall be limited to one (1) and a maximum size of 8’(W) x 24’(L).
2. Trailers shall be removed from site upon completion of construction.
01 00 00 -15
3. Contractor shall request placement of all trailers from the VA
Project Engineer (COR) identifying on a marked-up site plan (using
Google Earth screen shot) the approximate location of all trailers.
F. Workmen are subject to rules of Medical Center applicable to their conduct.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Work shall be accomplished during normal work hours, Monday through Friday, 7:00AM to 3:30PM (unless approved by the VA) excluding Federal holidays, as to cause the least interferences possible with normal activities of the facility and the surrounding areas. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by VA Project Engineer (COR) where required by limited working space.
Work shall occur so as to not interfere with the medical center operations, business or patient care. Work that will transmit vibrations, create noise, emit odors, require audible testing, etc. are required to be performed during other than normal business hours, specifically other than hours the patient care and occupied business spaces are not conducting patient care or business. The general contractor shall bear the cost of performing the required off-hour work. The general contractor shall plan-ahead and determine what work
(i.e. demolition, powder actuated power tool work, select construction activities, public corridor work, door & frame replacement, etc.) could interfere with medical center operations, business or patient care and plan to perform these activities during other than normal business hours. No additional time or money shall be provided to the general contractor for not planning ahead with disruptive work in an occupied medical center.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction areas within buildings in use by Department of Veterans
Affairs in quantities sufficient for not more than two workdays.
01 00 00 -16
Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Phasing: The Medical Center must maintain its operation 24 hours a day
7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the VA Project Engineer (COR) and Contracting
Officer to ensure that no lapses in operation occur. It is the
CONTRACTOR'S responsibility to develop a detailed work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the VA Project
Engineer (COR) and Contracting Officer with a realistic construction schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall submit a request to the VA
Project Engineer (COR) & Contracting Officer at a minimum of three (3) weeks in advance of each proposed date of starting work in each specific area of site, building or portion thereof. If the written request is not accepted by the VA Project Engineer (COR) or Contracting
Officer, the general contractor shall revise and resubmit the notification at a minimum of two (2) weeks in advance of the new proposed date of starting work from the newly submitted date of the revised request. The general contractor is responsible for submitting a request with all information; disapproved submittals requiring resubmission with two (2) week advanced notice is the general contractor’s responsibility for meeting period of performance, any delays occurred, rescheduling of work, etc. Arrange such/ phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, VA Chief Engineering Service, VA
Engineering Manager, VA Chief of Police Service, VA Physical Security
Specialist, VA Project Engineer (COR), Contracting Officer and
Contractor. All Buildings will be occupied during performance of work.
01 00 00 -17
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veteran’s Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes, whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc.... to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area/lay-down area/dumpster location/trailer location/Conex trailer location/etc. that was requested by the general contractor and accepted by the VA Project
Engineer (COR) and Contracting Officer prior to construction commencement or mobilization. Provide gates as required for access with necessary hardware, including hasps and padlocks. Provide three (3) keys to VA Project Engineer (COR). Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Fence portable feet shall utilize concrete filled plastic (HDPE + UV stabilized) mold bottoms in safety orange color (not-fade, sun/weather material). Bottom of fences shall extend to no greater than 25mm (one inch) above grade.
Construction fences shall be entirely wrapped (full fence height and length) with heavy-duty knitted HDPE construction coupled with high grade privacy fence screen. Screen shall be mold and mildew resistant.
Privacy screen material shall conform to ASTM D-5041. Privacy screens shall be enforced with 12-gauge galvanized steel, hog ring C shaped fasteners that are crimped into the grommet holes for a secure and
01 00 00 -18 strong attachment. Remove the fence when directed by VA Project
Engineer (COR) & Contracting Officer.
J. When a building or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall always maintain a minimum temperature of 4°C
(40°F), except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
K. Utilities Services: Always Maintain existing utility services for
Medical Center. Provide temporary facilities, labor, materials, equipment, connections, and utilities to ensure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by VA Project Engineer
(COR).
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of VA Project Engineer (COR).
Electrical work shall be accomplished with all affected circuits or equipment de-energized.
2. Contractor shall submit a request to interrupt any such services to
VA Project Engineer (COR), in writing, three (3) weeks in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption. It shall include a smoke shunt request if applicable with the smoke detector device identification codes.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least
01 00 00 -19 inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours. Most utility service interruptions shall be performed during other than normal business hours. VA Safety does not permit two fire protection systems (smokes and sprinklers) to be offline at the same time. The general contractor shall plan for this.
4. Major interruptions of any system must be requested, in writing, at least three (3) weeks prior to the desired time and shall be performed as directed by the VA Project Engineer (COR).
5. In case of a contract construction emergency, service will be interrupted on approval of VA Project Engineer (COR). Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Contractor.
L. Abandoned Lines: No service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports shall be permitted to be abandoned in place. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of
Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours. Most utility service interruptions shall be performed during other than normal business hours. VA Safety does not permit two fire protection systems (smokes and sprinklers) to be offline at the same time. The general contractor shall plan for this.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, parking and occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads or parking areas, at least one lane must always be open to traffic. Roadways are not
01 00 00 -20 permitted to be closed at any time. Work shall be completed to accommodate at least one lane always remaining open, even during off-hours work.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the VA
Project Engineer (COR).
3. The general contractor is responsible for costs associated with
Police details; the VA Police do not perform detail work. The general contractor shall provide a full-time designated flagman to direct vehicular and pedestrian traffic when work crosses and impacts roads, parking areas, sidewalks, etc. The general contractor shall furnish and install all necessary barriers, signage, power for signs, etc. required.
N. Coordinate the work for this contract with other construction operations, as directed by VA Project Engineer (COR). This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS. This also includes coordination with City of Boston
Conservation Commission, MA EPA, West Roxbury Police Department, West
Roxbury Fire Department MA DOT, MA State Police, etc
O. Coordination: Coordinate work and products meeting the requirements associated with all applicable specification sections and plans to produce a system complete, functional and ready for the purpose intended. No statements here in shall relieve the Contractor of responsibilities described elsewhere in the contract documents.
1. Pre-worksite Re-visit Requirements … Before starting work in a particular area, visit the worksite and carefully examine the areas to verify complexity, existing conditions and difficulties that will affect work including all work done under various specification sections and the VA. Commencement of work shall be construed as acceptance of the existing conditions and difficulties. No change to the contract price or schedule shall be allowed for work caused by unfamiliarity with the site conditions that are visible or readily construed by an experienced observer.
2. Coordinate the location of all work, equipment and components with other trades and equipment installers to prevent interferences and
01 00 00 -21 maintain proper use and access to all items and spaces. General
Contractor is responsible for coordinating all equipment and components being installed with the placement location and dimension requirements.
Prior to job execution each trade shall formally submit “complete” coordinated shop drawings indicating all equipment and material layouts with locations from walls/columns, bottom/top elevations, vibration isolators, supports, dimensions, utility requirements and equipment submittal numbers for review and approval. Each trade shall maintain a set of working drawings to document as-built information as the work progresses and submit it to the Project Engineer monthly for review.
3. All work shall be installed and connected to existing work neatly and carefully and shall be coordinated with other trades to avoid conflicts and to obtain a neat competent installation that will afford maximum accessibility for easy and proper operation, maintenance, service and headroom. All work shall be installed in a manner that permits easy accessibility and proper removal of system components requiring periodic service. Disturbed or damaged work shall be replaced or repaired to new conditions. Any items determined to be in non-compliance shall be corrected by the Contractor at no additional expense to the Government.
4. The drawings show or describe the general arrangement of equipment, articles, assemblies, and appurtenances but do not show all required fittings, drains, air vents, supports and may not identify all required accessories, components, fittings, and offsets that are necessary to properly complete the installation for the purpose intended. The contract drawings are diagrammatic only intended to show general layout of conduit, ductwork, piping, equipment, terminals, specialties and not intended to show all required offsets, details, accessories and equipment to be connected. Provide all necessary fittings, offsets and pipe runs based on field measurements and reviewed coordination drawings. Coordinate with other trades for space available and relative location of equipment and accessories to be connected at all locations.
The Contractor shall alter locations of items where necessary to avoid interference and clearance difficulties. Locations of components and equipment shall be adjusted to accommodate the work with interferences anticipated and encountered. The Contractor shall determine the exact routing and location of systems prior to fabrication and installation.
01 00 00 -22
Accurate field measurements and coordination drawings shall be prepared to establish the locations and characteristics of the various systems
(new and existing to remain). It is the intent of the drawings/specifications that the Contractor provides all materials, labor and coordination necessary to complete the work described or implied by the contract documents at no additional cost/time to the
Government. The Contractor shall propose with submitted coordination drawings other dimensions with similar characteristics where necessary to avoid interferences and clearance difficulties. Should the contract documents not agree with themselves the greater quantity of superior work and materials shall be performed.
5. Coordinate all mechanical (e.g., HVAC) electrical, plumbing (MEP) utility service, fire protection sprinkler system shutdowns and space access three (3) weeks in advance with the VA PROJECT ENGINEER (COR).
Due to facility scheduling and access difficulties, some shutdowns and the performance of certain work, as determined by the VA PROJECT
ENGINEER (COR), shall be performed during off-hours (after normal working hours) after coordination with the VA PROJECT ENGINEER (COR).
Arrange phases and perform work to ensure utility services for other buildings and areas at all times as required. All work being done in staff and patient areas of the Medical Center shall be done after normal working hours.
6. Before placement and installation of work subject to tests the
Contractor shall coordinate and notify the VA Project Engineer (COR) in sufficient time to enable VA personnel to be present at the site in time for proper witnessing, and field inspection. Such prior notice shall be not less than two (2) weeks unless otherwise designated by the
VA PROJECT ENGINEER (COR).
P. AE shall review all work that is to occur in construction phase as it relates to buildings, adjacent spaces/buildings, occupied areas, etc.
and discuss with VA Project Engineer & other services, the concerns of disrupting adjacent areas with noise, vibrations, etc. and the possibility of clearly identifying specific work to be conducted off-hours and performed other than normal hours. (I.e. demolition, drilling, etc.)
01 00 00 -23
1.8 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall conduct a thorough survey with the VA PROJECT ENGINEER (COR), of buildings, areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the
Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and VA Project
Engineer (COR).
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of VA
PROJECT ENGINEER (COR), to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government.
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and VA Project Engineer (COR) together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of
01 00 00 -24
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
E. Drilling/Coring: Prior to drilling or coring into or through any concrete floor, beam, column, or other structural element the contractor shall conduct non-destructive surveys to identify the presence of any embedded items such as conduits, piping, reinforcing steel, or other items that may be damaged by the proposed drilling or coring. Contractor shall use the results of this survey to determine a location for drilling or coring that will not damage embedded items in the structure.
F. Cutting and Patching: Cutting of existing surfaces shall be made along neat, straight lines and shall extend only to the limits needed for the new work.