S05_RFIs.pdf
PDF 160 KB Posted
- Solicitation number
- 36C77624R0069
About this file
This document is a Request for Information (RFI) for a federal contract opportunity to provide Architect-Engineering (A-E) services for the development of complete construction documents, including working drawings, specifications, and reports, as well as construction period services for a Minor Construct Emergency Control Center project at the VA Medical Center in Fort Harrison, MT.
The Department of Veterans Affairs is seeking sources for this 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside contract. The anticipated A-E contract award is planned for late May 2024, with a 448-calendar-day period of performance for design completion. The estimated construction cost range is between $5,000,000 and $10,000,000. The RFI provides details on the selection process, including primary and secondary evaluation criteria focused on specialized experience, professional qualifications, capacity, past performance, and knowledge of the locality. Respondents must submit an SF 330 qualification package by March 29, 2024.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information Project #: 436-116 – Construct Emergency Control Center Minor Construction Design
Fort Harrison, MT
RFQ/RFP: 363C77624R0069
03/20/2024
ITEM
NO.
QUESTION GOVERNMENT RESPONSE
1. Would it be acceptable to include one resume for a licensed engineer which would cover the both the Mechanical, and Plumbing Engineering Disciplines?
Yes. Make sure to label the resume as covering both requirements for a mechanical engineer and plumbing engineer.
2. The RFQ states “A PPQ obtained for another SF 330 submission may be submitted for this project.” May a previously collected PPQ still be used if it is not the same form as the one provided?
Yes.
3. It appears that the preliminary design was completed already by another firm. Does this have any weight on the selection of A/E firm for this RFQ?
No. Preliminary design was not performed by an A/E firm, but MTVA.
4. Many reference standards are not the most current.
Would it be correct to assume that the most current VA design guides for HVAC, Plumbing, IBC, NFPA will be used in the design of this project?
Yes.
5. Is the ECC updated to reflect 2024 construction costs? The drawings show this was designed back in 2014. Was the estimate reflecting 2014 costs or 2024 costs?
Estimated Cost of Construction is current.
6. Our team offers in-house commissioning. Is this in conflict with the solicitation notice? If so, we have an independent third party that our engineering firm works with. Is this acceptable to the solicitation notice if in-house is not allowed?
In accordance with the RFQ and VA Specification Section 01 91 00 GENERAL COMMISSSIONING REQUIREMENTS, the A/E should be providing a third party CxA.