S06 - Amendment 0001 Att 1 - Charleston Vendor Questions.docx

DOCX document 14 KB Posted

Attached to
C1DA--534-24-706 - EHRM Data Center Upgrades for JSA-FDS (VA-23-00096861)
Solicitation number
36C77624R0003
Issued by

About this file

This document contains questions and answers related to a federal solicitation for architectural and engineering services to support data center upgrades for the Department of Veterans Affairs. The solicitation requires resumes for all key positions listed in Factor 3, though some roles like civil engineer may have limited involvement. Individuals can be "dual-hatted" to fill multiple roles provided all key positions are covered. LEED certification is required for at least one architect on the team.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Charleston Vendor Questions

1. Factor 3 states that resumes are required for all key listed positions, however some roles seem irrelevant to the project per the SOW. Are all listed positions relevant and required?

Some of the roles may have less involvement for the project needs (i.e. Civil Engineer), but an A/E firm should be able to have them available, if a specific need arises during design.

2. Does the Architect need to be LEED certified?

Yes, LEED certified Architect(s) need to be a part of the team.

3. Can roles be “dual-hatted”?

The A/E team should have members available to fill all of the key positions listed, however individuals can be “dual-hatted” as long as there is an individual on the team that meets the requirement.