Attachment 4 - Answers to Technical Questions.docx

DOCX document 24 KB Posted

Attached to
R799--Stockton EUL Due Diligence Support COR: Lori Moore Federal contract opportunity
Solicitation number
36C77624Q0292
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a set of answers to technical questions related to a federal contract opportunity for Stockton EUL Due Diligence Support Services, Solicitation Number 36C77624Q0292. Key details include:

The contract will provide diligence support services to enable VA to accomplish an Enhanced-Use Lease (EUL) project at the VA Northern California Health Care System in Stockton, California. The proposed EUL would include construction of approximately 130 supportive housing units for senior Veterans and their families on vacant land at the VA campus. The period of performance is up to 3 years, with construction estimated to last 18 months. The contract will be awarded using a Best Value Tradeoff source selection methodology, evaluating technical approach, past performance, and price. Offerors must provide a Firm-Fixed Price proposal, and the government will review the labor categories, rates, and hours proposed. The contractor may be required to provide 508 compliance support for public documents. The government will provide a Quality Assurance Surveillance Plan after award, and may request credit reports on the selected developer.

View the file

Other files for this federal contract opportunity

Other files attached to R799--Stockton EUL Due Diligence Support COR: Lori Moore, newest first.
File Type Posted
Attachment 2 - REVISED II Price Schedule.xlsx XLSX spreadsheet
36C77624Q0292_3.docx DOCX document
Attachment 1 - REVISED II PWS - Stockton EUL Support.docx DOCX document
36C77624Q0292_2.docx DOCX document
Attachment 2 - REVISED Price Schedule.xlsx XLSX spreadsheet
Attachment 5 - Answers to Technical Questions.docx DOCX document
Attachment 1 - REVISED PWS - Stockton EUL Support.docx DOCX document
36C77624Q0292_1.docx DOCX document
Attachment 2 - Price Schedule.xlsx XLSX spreadsheet
Attachment 1 - Performance Work Statement - Stockton EUL Due Diligence Support.pdf PDF
Attachment 3 - PWS Attachments B-F.pdf PDF
36C77624Q0292.docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 – Answers to Technical Questions - 36C77624Q0292 – Stockton EUL

1. (Page 4 of 4) VA opened the Stockton VA Clinic in April/May 2024. Will VA provide the Section 106 consultation materials for that effort to inform evaluation/consultation for the proposed EUL? Has VA initiated consultation on the Logistics Building (Part 2) or the CLC (Part 3)? Should the contractor assume that analysis and consultation will take into account all phases of development? Alternately, would this proposed EUL be a continuation of consultation on the earlier development?

Answer: VA will initiate consultation for the Stockton EUL separately from other VA development. The contractor will have discussions with VA Personnel who have completed the Section 106 requirements for newly developed VA operated facilities.

2. Can you provide any details concerning the Period of Performance?

Answer: The period of performance is up to 3 years. Construction is estimated to last 18 months.

3. No statement of work is provided for the Phase II ESA work. Can VA please provide the anticipated scope for this task in order to assist our team in most accurately pricing this work?

Answer: Phase II ESA work is optional. The COR will provide the scope of work if a Phase II ESA is needed for the project.

4. No statement of work is provided for the Phase I Archaeology work. Can VA please provide the anticipated scope for this task in order to assist our team in most accurately pricing this work?

Answer: Please see Attachment E in the solicitation for details.

5. Which source selection methodology does the government intend to use to award this project? LPTA, Best Value Tradeoff, etc.

Answer: Best Value Tradeoff.

6. (Task Four / Item Number 0012) - Please provide/define the results/deliverables corresponding to No. 5 – Review facility design and/or construction documents.

Answer: Item 5, “Review facility design and/or construction documents is part of the documents (1-5) that VA will need support with reviewing and providing feedback as well as track and document project milestones and/or critical items. Deliverable 12 is stating that the selected contract support team will provide ongoing support with review of items 1-5 documents as requested by VA for the performance period of the contract.

7. (Task Four / Item Number 0012) Please provide which documents/deliverables, and quantities, that would require 508 Compliance work. As this is a priced/evaluated option, offerors need to understand the full scope of this task to accurately price.

Answer: VA requires any documents that will be made public will need to be 508 Compliant (e.g., NEPA documents). The COR will tell the selected Contractor which documents will need to be 508 Compliant.

8. The type of contract listed states Firm-Fixed Price. This aligns with the Attachment 2 Price Schedule with the unit of measure for each Item Number being JB (Job). However, Item Numbers 0001 – 0011 are deliverable-based services with a clear acceptance and invoicing milestone. Item Number 0012 is for ongoing support. (1) Please confirm invoicing and payment for this will be the total Line Item cost, divided by the number of months in the full PoP. (2) if all other Line Items are complete prior to the end of the PoP, please confirm the contractor would then invoice for the balance of Line Item 0012 costs, as this is firm-fixed price

Answer: The Total Contract Cost will be the total of all Deliverables identified in the Price Schedule. Invoicing will be done upon completion of COR approved Deliverables.

9. Page 2 of Attachment 1 lists tasks may include “credit reports”. Please define under which Item Number this task would fall and provide additional clarification of the scope and frequency/number of “credit reports”.

Answer: As apart of VA’s due diligence, the COR may request the Contractor pull credit reports on the selected Developer, or business entities prior to lease execution.

10. Page 5 discusses incentive/disincentive plans. (1) Please confirm that VA will provide/determine any incentive/disincentive plans, as a component of the Quality Assurance Plan, that is to be provided post-award. If so, and as such, that those plans may result in a modification to the solution/pricing.(2) If VA is requesting that offerors propose its own incentive/disincentive plan, please confirm if this will be a component of the Government’s evaluation and how it will impact both Technical (Factor) and price (how will this impact evaluation of the overall evaluated price, as defined in the solicitation)?

Answer: A simple Quality Assurance Surveillance Plan (QASP) will be provided to track Performance Measures upon contract award.

11. Attachment 1 states that personnel supporting this scope shall be assigned a Position Sensitivity Level of “Limited Risk” and require a NACI background investigation. As this is tied to “employees that require access”, please confirm no support personnel on this contract will require a Background Investigation.

Answer: At the time of contractor selection, VA will determine if a Background Investigation will be required.

12. Attachment 1, Page 5 states that the contractor shall provide a quarterly Program Management Report; however, Attachment A does not list this requirement. Please clarify the requirement.

Answer: The COR will discuss the format for the quarterly Program Management Report at the time of selection.

13. No SOW is provided for the Title Search. Can you please provide a statement of work?

Answer: Please see Attachment B: Sample Title Search and Chain of Title Scope of Work., page 1, A. Scope, and C. Deliverables.

14. Page 3/8 of the NEPA EA statement of work (Attachment G, page 3, Task 2, paragraph c) in Attachment 3 indicates that the subcontractor is required to develop the EA in accordance with the SOW and VA’s “Instruction to Contractor for Environmental Assessment” document. Our team has performed several NEPA EA’s for VA, and are not familiar with this document. Can you please provide it for scoping purposes?

Answer: Please disregard paragraph c. under section 10. Task 2 – Environmental Assessment, page 3 of 8. Excluding paragraph c., all other listed requirements under this section are sufficient.