Attachment 1 - Answers to Technical Questions.docx
DOCX document 18 KB Posted
- Attached to
- R799--EUL PMTSS IDIQ COR: DeCarol Smith Federal contract opportunity
- Solicitation number
- 36C77621Q0491
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C77621Q0491 00001.docx | DOCX document | |
| Attachment 2 - Performance Work Statement - Part B.pdf | ||
| Attachment 1 - Perfomance Work Stateent - Part A.pdf | ||
| Attachment 4 - Quality Surveillance Plan.doc | DOC document | |
| 36C77621Q0491.docx | DOCX document | |
| Attachment 3 - Pricing Schedule.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ANSWERS TO TECHNICAL QUESTIONS – EUL PMTSS IDIQ SOLICITATION – 36C77621Q0491
1. Would winning this opportunity preclude us from competing on any other design management or construction management contracts with the VA?
Answer: No.
1. Will the government consider expanding the relevant project time frame to include similar projects that were completed within the last 10 years instead of the 5-year limit listed in the RFP?
Answer: No.
1. Combined Synopsis/Solicitation Notice, Pages 8 and 9 – Quote Format (General) Instructions state the page limits for Volume I and II are 50 pages and 20 pages, respectively. The Quote Format (Content Requirements) states there is no page limit for these volumes. Please clarify page limits, if any, for Volumes I and II.
Answer: There are no page limits for Volume I & II, only a 4mb file size limit.
1. The Specific Mandatory Tasks and Associated Deliverables in Attachment 1 – Performance Work Statement – Part A (IDIQ) appear to be the same as those in Attachment 2 – Performance Work Statement – Part B (Initial Task Order – Program Support). Are the tasks and deliverables in the IDIQ PWS Part A intended to be limited to the Initial Task Order PWS Part B Program Support tasks only?
Answer: Attachment 1 – Performance Work Statement – Part A (IDIQ) is meant to be a general overview of possible deliverables. Future work on this IDIQ will be of a similar nature as Part A.
1. Combined Synopsis/Solicitation Notice, page 2, last paragraph states that similar services are being provided under the following contract: VA101F-17-D-2840 Enhanced Use Lease (EUL) Program Management - Technical and Strategic Support (PMTSS). The 2016 IDIQ solicitation for this predecessor contract included several tasks that appear to have been omitted from the current 2021 IDIQ PWS Part A, including but not limited to: Review of Lease terms, exhibits, and supporting documents, New Project support, and Review EUL projects scheduled to close. Were these tasks intentionally omitted from the current 2021 IDIQ PWS Part A?
Answer: Yes, the task in the previous VA101F-17-D-2840 Enhanced Use Lease (EUL) Program Management - Technical and Strategic Support (PMTSS) was omitted from the current 2021 IDIQ PWS Part A.