K036--COVID - Demo Package - Murfreesboro CMOP 764 Questions & Answers
Solicitation number
36C77021Q0572
Issued by

About this file

This document contains questions and answers related to a solicitation for disassembly and demolition services at the Murfreesboro VA Medical Center. The Department of Veterans Affairs intends to release Request for Quotes number 36C77021Q0572 for services including disassembling and palletizing robots, conveyors, cabinets and other equipment; removing electrical, data and pneumatic lines; and demolishing catwalks. The contractor will provide trailers for 90 days for storage and later disposition of removed equipment. The government estimates the mobilization and initial disassembly will take 30 days and aims to complete the entire project within 90 to 120 days from notice to proceed. Pricing should be provided per man hour for any additional work beyond the base requirements. The solicitation will be full and open with a small business set-aside and responses are due by September 1, 2021.

View the file

Other files

File Type Posted
36C77021Q0572_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Modification to a Previous Notice Modification to a Previous Notice

SUBJECT*
COVID - Demo Package - Murfreesboro CMOP 764 Questions & Answers

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
66048-5012
SOLICITATION NUMBER*
36C77021Q0572

BASE NOTICE TYPE

RESPONSE DATE/TIME/ZONE
09-23-2021 10AM CENTRAL TIME, CHICAGO, USA
ARCHIVE
30 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N

SET-ASIDE

PRODUCT SERVICE CODE*
K036
NAICS CODE*
238290
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

NCO 15 Contracting Ofc - CMOP 3450 S. 4th St. Trafficway Leavenworth KS 66048-5012

POINT OF CONTACT*

Esperanza Roberts

PLACE OF PERFORMANCE

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS
Esperanza.Roberts@va.gov

EMAIL DESCRIPTION

DESCRIPTION

RFQ 36C77021Q0572 – Disassembly & Demolition Murfreesboro CMOP Questions & Answers

1. What exactly needs to be palletized?

A; All items identified in the SOW that are capable of being palletized (robots, conveyor etc.…) should be palletized. Miscellaneous items that are disassembled may be placed in bins of like type items (conveyor supports, guide rails, etc.…). Cabinets and modules do not need to be palletized however components identified as being removed from those modules and cabinets should be palletized.

2. Who is providing the trailers?

A: As identified in Section 5.7 of the statement of work the contractor is to provide up to 10 semi-trailers for a period of 90 days.

3. How far back do they disconnect power?

A: As outlined in Section 3.0 of the SOW. “All disassembly work included in this section will be inclusive of electrical and pneumatic lines feeding the equipment. Such lines and cabling will be removed back to their respective control panel or piping manifold.” Contractor should take the electrical, data and pneumatic lines back to an appropriate point of disconnect.

4. Can they create a storage labelling system based on the actual module location (example: L1F4-XX)?

A:This is acceptable as long as items are inventoried for quick identification in the future.

5. Will there be a material lay down yard or storage for the contractor during construction?

A: A location for a lay down area or storage will be identified by the local COR in order to ensure the location does not impact on the operations of the facility. In addition, the contractor should also use the trailers identified in section 5.7 as laydown and storage as well.

6. Does the government want to keep items that are not marked as save or is the contractors responsibility to remove?

A: Contractor will remove.

7. Our understanding from the onsite meeting is we are only disconnecting equipment electrical to make it safe and clean. We are not taking back to the panel as state in the RFP. Is this correct?

A: Contractor should disconnect in accordance with Section 3.0 of the SOW. This requires disassembly to the nearest control panel, disconnect or manifold. This does not require everything to be removed back to the electrical panel but an appropriate point of disconnect for the equipment.

8. The catwalks are to be removed. Are those scraped or kept?

A: Catwalks are to be removed, disassembled and kept for future use.

9. Are all conveyors demoed including the one in phase 1? It came up at the pre bid that one may stay.

A: See section 3.2.1 of the SOW. Conveyor inside of the modules (flexlink) is not to be removed. All tote conveyor and external flex conveyor is to be disassembled and palletized. All Belt conveyor is to be disassembled and palletized for reuse. The local COR will identify a small portion of belt conveyor that will remain in place and do not need to be disassembled.

10. Is the government providing trailers for saved materials? If not, is the contractor to just pallet, label, wrap, and store in place? It states in the RFP the contractor is to provide 10 trailers, but I believe it was mentioned at the walk through that the government would provide trailers.

A: Contractor should provide up to 10 trailers for 90 days for the storage and disposition of the removed equipment. Anything excess to that will be identified for storage within the existing facility. The government will work to transfer, excess and dispose of equipment stored in the trailers. See section 5.7 of the SOW.

11. Does the government have a timeline for each phase so we can devote the appropriate labor hours to keep the schedule required? The government did not dictate schedule to ensure the contractor can schedule their crews in the most efficient and expeditious timeframe to complete the entire process.

A: The government is estimating approximately 30 days for mobilization and to begin the disassembly process. Please propose the ideal schedule to expedite the complete disassembly and removal of the system, recognizing this schedule should take into account the normal government holidays. Ideally the government would like to see the entire process completed within 90-120 days from notice to proceed.

12. The RFP asks for hourly pricing for additional work. Is this per man or per crew?

A: This should be a per man hour price.

13. Please confirm that all pricing to be provided in Attachment 1, and that Section B.3 of the RFQ is not required to be completed.

A: The contractor should provide their proposal as outlined in Attachment 1. Section B3 does not need to be completed.