5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

None

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

2501 W. 22nd St.

Sioux Falls SD 57105

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

2501 W. 22nd St.

Sioux Falls SD 57105

To all Offerors/Bidders

36C26321Q0688

07-22-2021

X

X X

X 1(one)

The purpose of this Amendment is to post questions from vendors. Offerors shall sign the 1449 and return 1 (one) copy to the contracting officer to be considered for this requirement. Questions and Answers are on page 2 of this Amendment. Offers are still due on Aug 11, 2021 at 10:00 AM CST.

Doug Reed Contracting Officer

VHA-VA-2020-56D92567

PAGE NO.

CONTRACT NO. ORDER NO. MODIFICATION NO.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)

STANDARD FORM 30 (CONTINUATION)

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

CONTINUATION PAGE

Questions and Answers

1. Question: Is one lump sum price for the entirety of the effort for the base year (and for subsequent Option Years) included in Line Items 0001, 1001, 2001, 3001 and 4001? Does this include the Kitchen Hood and Fire Extinguisher Maintenance in Sioux Falls and Wagner?

Response: Yes, Line Items 0001, 1001, 2001, 3001 and 4001 include the entirety of the effort for each year (the base and option years). Yes, this includes the Kitchen Hood and Fire Extinguisher Maintenance in Sioux Falls and Wagner. The Government determines the structure of the line items to best suit the requirement.

2. Question: - How is Line Item 0002 to be priced and evaluated?

Response: Please refer to the Request for Quote (RFQ), Parts for Repairs on page 15. Line Items 0002, 1002, 2002, 3002 and 4002 for Parts for Repairs will not be priced on your offer.

3. Question: Is the contractor required to drive to Wagner monthly to do the monthly inspection for the three or four FX there?

Response: Yes, this is stated on page 9 in the RFQ. This can be completed by the contractor or a subcontractor as they see appropriate.

4. Question: Under Paragraph #1 – it states, “Contractor shall provide two additional scanners for VHA HCS Use.” What does this mean?

Response: The scanner requirement is being deleted from the Statement of Work (SOW). The updated SOW will be attached to this Amendment.

5. Question: It appears the Monthly Fire Extinguisher inspections are required at the Wagner location as well as the Sioux Falls VA location.

Response: Yes, this is correct.

6. Question: Section 2. F. “Cleaning of grease filters and any baffles found in the kitchen hoods.” Will the contractor be allowed to use VA equipment in this process (sinks, dishwashers, other equipment and supplies on site)?

Response: Complete filter and baffle cleaning in each hood is required as listed in the SOW. There is no guarantee that onsite cleaning resources will be available.

7. Question: Will the contractor be required to remove the filters from the site to perform this task?

Response: Bid contract as necessary to provide services as listed in the SOW. Contractor may remove filters from the site to perform services after coordination with the technical representative. Contractor shall have filters and baffles cleaned in a two-hour timeframe coordinated directly with the service line and the technical representative of the contract. This is to be completed twice a year at inspection intervals by the contractor per the SOW.

8. Question: Will over all hood cleaning services be conducted separately by a hood cleaning professional?

Response: Grease duct shall be cleaned by a separate contractor.

9. Question: New buildings to be added in 2022 and 2024 are referenced. Are contractors to consider these in our pricing? Are contractors to factor these locations into the overall pricing for those years?

Response: Yes, the new buildings are included in the quantity of 500 extinguishers listed in the SOW. If the 500 extinguishers were exceeded, the contractor would be able to work an equitable adjustment with the contracting officer.

See attached document: P09 Final SOW.