1. Equipment may take longer than 30 days to procure followed by set up and completion of work. Is there room for time extensions within reason as needed to complete the project?

Answer – The VA St. Cloud campus requires passing test results by October 13, 2020. Best efforts should be put forward to ensure this happens. If for any reason this compliance requirement cannot be met, the COR must be alerted as soon as the contractor has knowledge that this will be this case.

2. Item 18 on the offer form suggest PP Bonds. Are these bonds going to be required on a project of this size and scope?

Answer – Due to the lower estimated magnitude, bonds will not be required for this project.