36C26319B0004 437-17-102 - Install Instrument Air and RO Water in SPS - Specifications - (231 pages).pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26319B0004-0001000.docx | DOCX document | |
| 36C26319B0004-0001002.pdf | ||
| 36C26319B0004-0001001.pdf | ||
| 36C26319B0004-002.docx | DOCX document | |
| 36C26319B0004-004.pdf | ||
| 36C26319B0004-001.docx | DOCX document | |
| 36C26319B0004-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FARGO ND VAMC
INSTALL INSTRUMENT AIR AND
REVERSE OSMOSIS (RO) WATER IN
STERILE PROCESSING SERVICES
100% Construction Documents Specifications
VA PROJECT NO.: 437-17-102
February 20, 2019
U.S. DEPARTMENT OF
V E T E R ANS AF FAI R S
VA Central Iowa Health Care System
Des Moines Division
SPECIFICATIONS MANUAL
FOR
FARGO ND VAMC
2101N. Elm Street
Fargo, ND 58102
INSTALL INSTRUMENT AIR AND REVERSE
OSMOSIS (RO) WATER IN STERILE
PROCESSING SERVICES
FARGO, ND
Project No.: 437-17-102
ARCHITECT
FourFront Design, Inc.
517 Seventh Street
Rapid City, SD 57701
{605) 342-9470 Fax: {605) 342-2377
MECHANICAL ENGINEER
FourFront Design, Inc.
517 Seventh Street
{605) 342-9470 Fax: {605) 342-2377
ELECTRICAL ENGINEER
Malone Engineering, Inc.
230 Main Street
{605) 341-6939 Fax: {605) 341-6883
11-01-17
VA PROJECT #437-17-102 Table of Contents
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-17
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS – NOT USED
DIVISION 03 – CONCRETE – NOT USED
DIVISION 04 – MASONRY – NOT USED
DIVISION 05 – METALS – NOT USED
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES – NOT USED
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
DIVISION 08 – OPENINGS
08 31 13 Access doors and frames
DIVISION 09- FINISHES
09 96 59 High-Build Glazed Coatings 07-14
DIVISION 10 – SPECIALTIES – NOT USED
DIVISION 11 – EQUIPMENT – NOT USED
DIVISION 12 – FURNISHINGS – NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED
DIVISION 14– CONVEYING EQUIPEMENT – NOT USED
DIVISION 21- FIRE SUPPRESSION – NOT USED
11-01-17
VA PROJECT #437-17-102 Table of Contents
00 01 10-2
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 11 00 Facility Water Distribution 09-15
22 15 00 General Service Compressed-Air Systems 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 09 23 Direct Digital Control System for HVAC 09-11
DIVISION 25 – INTEGRATED AUTOMATION – NOT USED
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 05-14
26 24 19 Motor Control Center
26 29 21 Enclosed Switches and Circuit Breakers 01-17
DIVISION 27 – COMMUNICATIONS – NOT USED
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY – NOT USED
DIVISION 31 – EARTHWORK – NOT USED
DIVISION 32 – EXTERIOR IMPROVEMENTS – NOT USED
DIVISION 33 – UTILITIES – NOT USED
DIVISION 34 – TRANSPORTATION – NOT USED
DIVISION 48 – ELECTRICAL POWER GENERATION – NOT USED
07-01-15
VA PROJECT #437-17-102 List of Drawings
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
MECHANICAL
P00 COVER SHEET/REFERENCES
P01 PARTIAL BASEMENT/SITE PLANS
P02 ENLARGED PLANS
P03 SCHEDULE, DETAILS, SEQUENCE OF OPERATIONS, POINTS LIST
ELECTRICAL
E01 BASEMENT FLOOR PLAN – ELECTRICAL PLAN
- - - END - - -
07-01-15
VA PROJECT #437-17-102 List of Drawings
00 01 15 - 2
THIS PAGE INTENTIONALLY LEFT BLANK
VA PROJECT #437-17-102 General Requirements
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Fargo VA Health Care System
Install Instrument Air and Reverse Osmosis (RO) Water in Sterile
Processing Services (SPS) Project Number 437-17-102 as required by drawings and specifications.
B. Only one organized site visit will be completed per FAR 52.236-27
C. Offices of FourFront Design, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain I.D. badges from the VA.
E. Prior to commencing work, general contractor shall provide proof that a
OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
F. Training:
1. All employees of general contractor or subcontractors shall have the
10-hour (Non-Supervisory employee) or 30-hour (Supervisory Employee)
OSHA Construction Safety course and other relevant competency training, as determined by PE/COR acting as the Construction Safety
Officer with input from the facility Construction Safety Committee.
2. Submit training records of all such employees for approval before the start of work.
G. VHA Directive 7715, Safety and Health during Construction, dated
4/6/2017 in its entirety is made a part of this section
1.3 BID INSTRUCTIONS
A. A single award will be made on Item No. I (Base Bid) with or without
Deduct Alternate 1. Offerors should quote a price on each item listed.
1.4 BID SCHEDULE
Project: Contractor:
01 00 00 - 2
ITEM # DESCRIPTION TOTAL BID
01 00 00 - 2
I Base Bid N/A $
II Deduct Alternate 1 $ $
1.5 STATEMENT OF BID ITEM(S)
A. ITEM I, BASE BID: Work includes plumbing alterations and electrical work, and a new instrument air compressor. See drawings and specifications.
B. Deduct Alternate 1: In lieu of replacing compressed air piping with new pipe, re-use existing piping by replacing soldered joints with brazed joints.
1.6 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, 0 sets of specifications and drawings will be furnished.
B. Additional sets of drawings may be made by the Contractor, at
Contractor's expense, from file downloaded from the Federal Business
Operations site for the project.
1.7 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees and Sub-Contractor employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” defined as weekdays from
8:00 am to 4:30 pm, the General Contractor shall give 21 days notice to the Contracting Officer’s Representative so that notice can be provided for the VA employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Document Control:
01 00 00 - 3
1. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
3. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
1.8 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
C. Working space and space available for storing materials shall be determined by the Project Engineer.
D. Workmen are subject to rules of Medical Center applicable to their conduct.
E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by Project Engineer where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
01 00 00 - 4
3. Where access by Medical Center personnel is not required, storage of
Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Project Engineer. All such actions shall be coordinated with the Project Engineer involved.
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Contractor.
G. Phasing:
1. To insure such executions, Contractor shall furnish the Project
Engineer with a schedule of approximate dates on which the
Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the Project Engineer in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to Project Engineer and
Contractor.
2. Work in the SPS rooms shall be done after normal working hours.
H. All buildings will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Selected immediate areas of alterations will be temporarily vacated while alterations are performed. Coordinate with Project Engineer.
Other areas will not be vacated during construction.
I. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Project Engineer.
01 00 00 - 5
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of Project Engineer. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
2. Contractor shall submit a request to interrupt any such services to
Project Engineer, in writing, three weeks in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical
Center may occur at other than Contractor's normal working hours at no additional cost to the Government.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the Project Engineer.
5. In case of a contract construction emergency, service will be interrupted on approval of Project Engineer. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
6. At the end of the construction workday, all water and compressed air services must be in service and available for VA employees.
K. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
L. Coordinate the work for this contract with other construction operations as directed by Project Engineer. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.9 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the Project Engineer, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting
Officer. This report shall list by rooms and spaces:
01 00 00 - 6
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Project Engineer.
B. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and Project Engineer together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
C. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.10 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by Project Engineer.
01 00 00 - 7
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government and shall be removed by the
Government in advance of work to avoid interfering with Contractor's operation.
1.11 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Articles, "Alterations", "Restoration", and "Operations and
Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.12 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
Project Engineer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Project
Engineer before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, 01 00 00 - 8 repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated.
(FAR 52.236-17)
B. Establish and plainly mark such lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established are in accordance with lines and elevations shown on contract drawings.
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the Project Engineer's review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings to the Project Engineer within 15 calendar days after each completed phase and after the acceptance of the project by the Project
Engineer.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to compliance with the following provisions:
1. Permission to use each unit or system must be given by Project
Engineer in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the Project Engineer will withdraw permission for use of the equipment.
01 00 00 - 9
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded.
The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
1.17 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the Project Engineer for use of elevators. The Project Engineer will ascertain that elevators are in proper condition.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.18 TEMPORARY TOILETS
A. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.19 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as
01 00 00 - 10 specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia and repair restore the infrastructure as required.
C. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. Electricity is available at no cost to the
Contractor.
D. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Chief Engineer must approve tie-in location and backflow preventer prior to installation. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at Project Engineer's discretion) of use of water from Medical Center's system.
1.20 TESTS
A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonable period of time during which operating and environmental conditions remain reasonably constant.
01 00 00 - 11
E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.21 CONSTRUCTION MEETINGS
A. Construction meetings will be held weekly to coordinate the activities of the Contractor.
1. Each meeting shall be attended by VA Representative, A/E
Representative and Field Representative of each trade.
2. The General Contractor shall be responsible for conducting and supervising the meeting and for recording and distributing minutes of the meeting to each representative.
1.22 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (Two (2) bound hard files and .pdf files on CD/DVD) for each separate piece of equipment shall be delivered to the Project Engineer coincidental with the delivery of the equipment to the job site. Omit all special characters in electronic files (i.e. #, %, &, *, :, <, >, ?, /). Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the Project Engineer and shall be considered concluded only when the
Project Engineer is satisfied in regard to complete and thorough
01 00 00 - 12 coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Project Engineer, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.23 LOCAL FARGO VA HEALTH CARE SYSTEM CONSTRUCTION CONTRACTOR ORIENTATION
AND POLICIES
A. Contracts: The following staff or resource people will be working with you at the Fargo VA HealthCare System. Please feel free to contact these individuals with any questions:
1. Chief Engineer: Shawn Bergan (701) 239-3700, ext. 93388 or (701)
239-3760
2. Project Engineer: Todd Dalzell (701) 239-3700, ext. 93362 or (701)
239-3760 or Dennis Langevin (701) 239-3700, ext. 93365 or (701) 239-
B. Vehicle Traffic Rules: All construction contractors shall park their vehicles in areas assigned by the Contracting Officer or Engineering
Service representatives. All persons coming on the premises of the
Fargo VA Health Care System must obey the posted traffic and parking rules. Police Service will issue tickets to contractor vehicles parked in areas other than those assigned.
C. Keys/ID Badges: VA ID badges must be worn while you are on Medical
Center premises. Contact Engineering Service to obtain an ID badge and any necessary keys. Contract staff are responsible for the security of keys and ID badges issued to them and may be charged for replacement cost. You must notify Engineering (ext. 3361) personnel immediately to report any loss, theft or suspected reproduction of a Medical Center key or access card.
D. Smoking: Smoking is prohibited except in designated smoking shelters or areas.
E. Use of Government Telephones and Fax Machines
1. Government telephones are for official Government business use.
Contract staff may use telephones, for local calls only, to contact your place of employment or to address unforeseen events such as injury on the job, work schedule changes etc.
F. Housekeeping
1. All construction sites shall be kept clean, orderly and in sanitary condition.
2. All rags/cloth and rubbish soaked with flammable and/or combustible material shall be placed in a covered metal receptacle until being disposed.
3. A clear and unobstructed path must be maintained to all portable fire extinguishers, hose cabinets, pull stations, fire exits and electrical panels.
01 00 00 - 13
4. Fire doors and smoke barrier doors shall not be blocked in a manner to prevent their protective operation in the event of a fire.
5. The use of wedges, stops, ropes, or other unapproved methods of holding doors open is prohibited.
6. All indoor trash containers over 20 gallons will be constructed of non-combustible materials and be covered or have a self-extinguishing cover.
G. Storage
1. Any commodities that may be hazardous in combination with each other must be stored so they cannot come in contact with each other.
2. Store flammable and combustible liquids and gasses in approved storage containers.
3. A clear space of 18 inches will be maintained below sprinkler heads.
4. Items stored in tiers will be stacked, blocked, interlocked and limited in height to prevent sliding or collapse.
5. Materials will not be stored directly on the floor.
6. Storage areas will be kept free from accumulation of materials that constitute hazards.
7. Stairwells, stairways and corridors shall not be utilized for storage.
8. Storage will not be permitted within 3 feet of an electric panel in all directions.
H. Hazardous Materials
1. Discovery of any suspected asbestos containing material shall result in the contractor stopping work in the area and reporting the discovery immediately to the Engineering Office (ext. 3361) or one of the contact persons indicated above. Engineering Service shall then evaluate the suspect material and if it contains asbestos shall arrange for the removal of the asbestos.
2. Contractors shall maintain and provide to the VA Project Engineer
MSDS’s for products used during construction which shall explain the labeling system and all other required information. Report any discovery of an existing hazardous material to Engineering Service, (ext. 3361).
I. Infection Control
1. PURPOSE: To prevent the acquisition of nosocomial infection in patients and healthcare workers during medical center renovation or construction activities.
2. The Contractor shall contact Engineering Service (239-3760 or EXT.
3361) prior to beginning construction in any areas so that a Pre-
Construction Risk Assessment (PCRA) may be performed and all
01 00 00 - 14 applicable forms completed. Once completed the Contractor shall obtain a completed and approved copy of a PCRA Form for each area of work in which the Contractor is involved. The Contractor shall conform to all of the requirements (ILSM’s, Infection Control
Precautions, etc.) as noted on the completed forms. The Contractor shall post a copy of the completed Form outside the construction barrier at each work site in plain view and accessible to VA Staff for verification that requirements noted on PCRA Form are being adhered to.
3. General: The goal of Infection Control is to identify and reduce the risks of acquiring and transmitting infections among patients, employees, service workers and visitors to the Medical Center.
During construction or renovation projects, hidden infectious disease hazards may be released into the air, carried on dust particles, on workers clothing or be present in damp areas or areas where water has collected. One particular organism of concern is a fungal organism know as Aspergillus. Aspergillus can be found in decaying leaves and compost, plaster and drywall, and settled dust.
These organisms like many others encountered in our everyday lives usually do not cause problems in healthy people, however a hospital is full of sick patients. Aspergillus and other organisms can cause severe illness and even death in some patients. Therefore, it is critical that everyone do their best to help prevent conditions that might lead to the dispersion of this or other infectious organisms by:
a. Maintaining barrier walls that keep dust and dirt inside the worksite.
b. Maintaining a state of negative air pressure within the construction site to prevent dust and dirt from dispersing into the Medical Center from the worksite. The Contractor shall install bulb type pressure differential monitoring devices or an alarm system in temporary construction barriers and shall monitor and maintain negative air pressure in construction areas.
c. Removing demolition debris in a manner that minimizes any contamination of the environment outside the worksite by dust and debris.
d. Utilizing walk off mats and making sure clothing is free of loose soil and debris when leaving the construction site.
e. Assuring that any water or sludge found during demolition of plumbing or in the construction process is collected and disposed of in a controlled manner.
f. Keeping demolition chutes sealed when not in use to maintain dust control. Use a water spray to minimize dust generation when using chutes if possible.
g. Using only designated entry and exit pathways.
01 00 00 - 15
4. Please feel free to contact Infection Control at ext. 3668 if you have questions or concerns.
5. If you find any needles, syringes, sharp medical objects please do not handle or remove yourself. Contact the Medical Center project coordinator or Project Engineer at 239-3760 or at Medical Center extension 3361 for removal.
6. Infection control activities are critical in all areas of the
Medical Center. Construction activities causing disturbance of existing dust, or generating new dust must be conducted in ways that will minimize dust generation and dispersion.
7. All construction/maintenance workers and contract workers must follow the infection control procedures as described in this guideline.
8. The following infection control procedures shall be followed at a minimum:
a. BARRIERS – Complete all critical barriers before construction begins.
1) Construction or renovation sites not capable of containment within a single room must be separated from patient-care areas and other critical areas by barriers that keep the dirt and dust inside the work site.
2) The integrity of the barrier walls must assure a complete seal of the construction area from adjacent areas.
3) Temporary barriers and enclosures must be dust proof with airtight seals maintained at the full perimeter of the walls, floors and upper decking, as well as all penetrations. Seal holes, pipes, conduits and punctures appropriately.
4) Tightly sealing doors or an overlapping flap of at least 2 feet in width of a durable poly must be used at points of personnel access, where plastic/poly barriers are approved for use by VA Project Engineer.
5) Elevator shafts or stairways must be isolated outside of the construction field to prevent dispersion of dust from the work site.
b. ENVIRONMENTAL CONTROLS
1) Isolate the HVAC system in areas where work is being done to prevent contamination of the duct system.
2) Maintain negative air pressure within work site. Utilize
HEPA-filtration units if air is being re-circulated.
3) Seal holes, pipes, conduits and punctures appropriately.
4) Provide a designated area within the work site where all personnel leaving the work site can vacuum off with a HEPA-
01 00 00 - 16 filtered vacuum to remove all loose dust and debris from clothing.
5) Vacuum with a HEPA-filtered vacuum and/or wet mop frequently at entrance and exit points.
6) “Sticky” or walk-off mats shall be utilized immediately outside the construction area to remove dust and soil from shoes, cart wheels, etc. as personnel exit the area. The mats must be large enough to cover the entire exit and changed frequently to prevent accumulation of dust. Contractor shall place a form on a wall adjacent to each mat with space to record date, time and exchanger’s signature so VA Staff can monitor that mats are changed at required frequency.
7) Contain construction debris during transport in covered containers.
8) Debris must be removed from the construction area on a daily basis in covered carts using specified traffic patterns.
9) Control, collection and disposal must be provided for any drain liquid or sludge encountered when demolishing plumbing.
c. CLEANING
1) The construction zone and adjacent areas must be maintained by wet mopping the area daily or more frequently as needed to minimize dust generation.
2) Final cleaning of the area must be completed prior to acceptance of the completed project area by VA.
3) Do not remove barriers from work area until the project is completed and area is thoroughly cleaned. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
4) Clothing shall be free of loose soil and debris before exiting the construction zone.
5) Personnel entering sterile/invasive procedure areas will be provided with a disposable jump suit, head covering and shoe covers to wear while working in the area. They must be removed when exiting the area and new coverings obtained when reentering the areas.
6) Tools and equipment must be damp-wiped prior to entry and exit from sterile and invasive procedure areas.
7) Tools and equipment soiled with blood or body fluids must be cleaned with a hospital-approved disinfectant prior to removing from the area.
d. ENVIRONMENTAL MONITORING AND COMPLETION
01 00 00 - 17
1) Infection Control, in cooperation with Engineering and Safety will make periodic visits to the work site to ensure compliance with the infection control guidelines.
2) Whenever safe infection control conditions are not met the appropriate contractor will be notified to correct the conditions immediately.
3) All work will be stopped on a project if a hazardous infection control deficiency exists that would result in patients being put at significant risk.
4) Water supply lines will be flushed before placing newly renovated or constructed areas into service. Industrial
Hygiene will assure that water supply lines are safe for use.
J. Construction Safety
1. The Medical Center policy is to provide an environment for patients, visitors and staff that is free from danger. Within the Medical
Center, the NFPA Life Safety Code is followed. Interim life safety measures (ILSM’s) are applied to all construction projects as necessary and are defined in construction contracts. Minimum ILSM’s are:
2. Exits – provide free and unobstructed egress.
3. Free and unobstructed access to emergency department/service for emergency forces.
4. Temporary construction partitions are in accordance with contract requirements.
5. Smoking is permitted in designated areas only.
6. Storage, housekeeping and debris removal policies and procedures that reduce the flammable and combustible fire load are enforced.
7. Hazard surveillance is increased in construction areas.
K. Fire Safety
1. The contractors shall coordinate all construction activities with the VA Engineering Service to determine if fire alarm initiating devices are located within the construction area. Engineering
Service shall disable the appropriate alarm initiating devices.
Once work in the area is complete it is the contractor’s responsibility to contact Engineering Service to have the fire alarm initiation devices enabled.
2. Fire alarm, detection and suppression systems are not to be impaired unless there is work on the system to be performed. If fire alarm, detection and suppression systems are impaired for more than four hours the contractor shall implement a fire watch, at no additional cost to the Government, in compliance with NFPA requirements and shall obtain VA Engineering Service approval.
01 00 00 - 18
3. Additional firefighting equipment is provided and employees are trained in its use.
4. Hot works permits and fire extinguishers are required when working with open flames, or hot items and for activities that may generate sparks. Contact Engineering Service to obtain a hot work permit.
5. In the event of a fire alarm, “CODE RED” and the location of a fire will be communicated by an overhead announcement. The "all clear" is authorized by the Fargo Fire Department or by the personnel conducting the fire drill and will be communicated by an overhead announcement. If a fire or fire drill is located in or adjacent to the construction area, construction contractor staff shall be responsible for the following:
a. Be alert to the Code 5 announcement.
b. Participate in fire drills.
c. Follow the RACE Plan (Rescue, Alarm, Contain, Extinguish) if fire is discovered by a construction contractor.
d. Close all corridor doors within the construction area.
e. Evacuate the immediate area.
L. Utilities
1. Engineering (ext. 3361) is responsible for all utilities within the
Medical Center. If there are problems or failures of the utilities, call extension 3361 during normal business hours (Monday through
Friday, 8:00 a.m. to 4:30 p.m.). After hours and on weekends, contact the Police Service at ext. 3251 to report problems and failures. A utilities failure and its type/location will be communicated by a “Utility Failure” overhead announcement.
2. All utility service connections shall be reviewed with and approved by Engineering Service just prior to the connection being made with the existing utility. This condition shall apply to both temporary and permanent connections. This final utility system connection check is meant to ensure the following:
a. The Medical Center is prepared for the connection.
b. The contractor is prepared for the connection work, which shall include but not be limited to, all safety measures have been taken or are in place, backflow preventers are in place, hot work permits have been issued, fire watch is in place, fire alarm initiation devices have been disabled if necessary, etc.
M. Emergencies
1. “Disaster Alert” - The Medical Center has initiated a process that provides an "all-hazard" approach to disaster management.
Construction contractor staff shall ensure corridors are free of obstructions and a foreman or representative shall report to the
Engineering Service office for further instructions.
01 00 00 - 19
2. Hostage Situations – Immediately report to Police Service (ext.
2222), any incident in which the safety of any person is threatened by another.
3. “Bomb Threat” - React calmly and evacuate. Notify Police Service
(ext. 2222) if the threat poses immediate danger to a person or destruction of property. If you discover a suspicious object, do not touch or move the object.
4. Severe Weather – In the event of an overhead announcement, all personnel are expected to take cover in windowless interior corridors that are not on the top floor of the building.
5. “Armed Assailant” – React calmly and evacuate. Avoid area(s) where it has been indicated an armed assailant is in the building or on the ground.
- - - E N D - - -
01 00 00 - 20
PRE-CONSTRUCTION RISK ASSESSMENT <PCRA)
Project#
Project Title: Est. Start Date:
Area of Construction: Est. Duration:
Contractor/Supervisor:
PCRA Completed by:
SAFETY/ENGINEERING
X lfYF.S, CIRCU: II.SM from lisl below or describe olher inlervention
Will exits or exit egress routes from occupied areas change? A, E,H,J, L
Will the construction area have less than two remote exits? A, E, H, J, L
Will there be excessive distance to exit? A, E, H,J, L
Will access to Emergency Services become blocked or obstructed? A, B, I, J, L
Will any part of the fire protection systems (detection, notification or suppression) be shut down or imoaired for >4 hours in a 24-hour perio d?
C, E, H, I, K
Will smoke or firewalls be breached? A, E, G, II
Will any temporary construction partitions be built? D Will the project result in the accumulation of construction debris? E, F, G, H
Will construction aITect grounds safety (pits, storage, equipment, etc.)? H
Will construction present other life safety hazards? H, J
Will protection ofha7.ardous areas be compromised? H
INTERVENTION
A. Ensure Alternate Egress Routes E. Additional Fire Fighting Equipment I. Additional Training of Emergency Personnel
13. Ensure Alternate Emergency…
This is the start of the file's text. The full file is on GovTribe.